I recently moved. Packing a mostly finished airframe and a "used" workshop and then moving it across town is harder than you would think.
First the plane with the gear was about two inches wider than the trailer. This required removing one wheel. Next there is the organizational issue. The new garage is smaller and needs more organization. The plane needs to sit at a diagonal to fit. Once the engine is hung the door from the garage into the house will need to be removed to fit the plane.
Recent progress has included mounting the rudder pedals, brakes and nose steering. I also fabricated the rudder cable pulleys and some rudder mounting parts.
Here is the new workspace ( Requires Silverlight )
Tuesday, April 07, 2009
Wednesday, April 01, 2009
Monday, February 16, 2009
Friday, February 13, 2009
This picture illustrates that I placed the horizontal stabilizer mounts 10mm to far inside on both sides.Two options exist in my mind for fixing this.
The first option is to create a custom mount from the fuselage side shaped to clear the flange of the stabilizer's mount. This would require a spacer and a much longer bolt. It also increases the chance of the mount cracking.
The second option is to open the stabilizer and move the mounts 10mm outside. This may require some work to the spar.
The controls are coming along nicely. The push rods and flaperon bellcranks are all connected. The flaperon mixer is also connected. The pushrods terminate where they will exit the fuselage.
I also figured out the wiring for the strobes and nav lights. They were pretty easy to deal with, but finding a suitable location for the control unit may be tricky.
Thursday, January 08, 2009
I have been very bad about posting recently, but this should not be construed as the project not being worked on.The whole workbench was partially redone and lowered about half a foot. This is so the plane can sit on its wheels on the ground.
The engine mount holes were drilled out to their final size and bolted on.
Work has started on the controls. All three bell cranks have been fabricated. The lower torque tube bearing was un-riveted to allow for the torque tube to be placed. I then found an unacceptable amount of ply, so a new lower bushing was fabricated to raise the torque tube up and remove the wiggle.
In addition I have fabricated the flaperon mixer bearings and started placing the "L" angle that supports them.
Tuesday, December 16, 2008
Sunday, November 16, 2008
Another monster six hour session finished the drilling for the slats. Only a few "gotchas" were hit.
First with the trailing edge skin be careful with the holes of the ribs. The last hole for each rib intersected the skin. This normally would not be a big deal but the ribs were already riveted ( per instructions ) to the bottom half of the main skin. In two cases ( outboard skins ) there was enough edge distance to drill out the rivets and use a strap duplicator to carry the hole onto the edge skin. With my inboard skins I had to make notches for the rivet heads.
All four slat pieces are drilled to final hole sizes and are ready to be deburred, primed and riveted.
First with the trailing edge skin be careful with the holes of the ribs. The last hole for each rib intersected the skin. This normally would not be a big deal but the ribs were already riveted ( per instructions ) to the bottom half of the main skin. In two cases ( outboard skins ) there was enough edge distance to drill out the rivets and use a strap duplicator to carry the hole onto the edge skin. With my inboard skins I had to make notches for the rivet heads.
All four slat pieces are drilled to final hole sizes and are ready to be deburred, primed and riveted.
Saturday, November 15, 2008
First, to anyone who is about to order their wheels please, please, please pay attention. Just spend the extra $30 a wheel and buy the tubes. The Matco tubeless tires are a nightmare. Seriously, I would rather rivet my hand to a rabid raccoon than deal with those things again.
I probably spent 15 hours trying to get them to inflate.
Some of that time was spent trying to separate the wheels. They can be really tight a large amounts of brute force will need to be applied.
The valve stems are a pain to install. A local tire shop was kind and let me borrow a valve stem installer. After that you need to get the wheel somehow beaded with the tire AND then slip a crazy rubber band gasket on between the two halves of the wheel.
If you use the tubes then the valve just slips on through and the wheels self bead.
A huge amount of progress was made thanks to the help of another local 701 builder. Together we made substantial progress on the slats. The slats are pretty straight forward, except for a few gotchas that got me. The biggest has to do with the "L" angle that reinforces the slat skin near the supports.
Trying to be industrious I went and cut the "L", notched it, bent it to match and then located the holes and drilled them into one piece. I used one of the ribs to back drill into a mirrored rib and then duplicated the holes to all the ribs.
What I forgot to do was check that all the holes of the "L" went into the support. Luckily all the holes that made it into the support were within minimum edge distances, but one hole missed. So I had to drill a fifth hole into the "L" that then made it into the slat support.
In one monster eight hour session we got the "L" spar drilled into all four slat skins, all the ribs, supports and "L"s riveted together and on one piece the ribs drilled into the skin.
I probably spent 15 hours trying to get them to inflate.
Some of that time was spent trying to separate the wheels. They can be really tight a large amounts of brute force will need to be applied.
The valve stems are a pain to install. A local tire shop was kind and let me borrow a valve stem installer. After that you need to get the wheel somehow beaded with the tire AND then slip a crazy rubber band gasket on between the two halves of the wheel.
If you use the tubes then the valve just slips on through and the wheels self bead.
A huge amount of progress was made thanks to the help of another local 701 builder. Together we made substantial progress on the slats. The slats are pretty straight forward, except for a few gotchas that got me. The biggest has to do with the "L" angle that reinforces the slat skin near the supports.
Trying to be industrious I went and cut the "L", notched it, bent it to match and then located the holes and drilled them into one piece. I used one of the ribs to back drill into a mirrored rib and then duplicated the holes to all the ribs.
What I forgot to do was check that all the holes of the "L" went into the support. Luckily all the holes that made it into the support were within minimum edge distances, but one hole missed. So I had to drill a fifth hole into the "L" that then made it into the slat support.
In one monster eight hour session we got the "L" spar drilled into all four slat skins, all the ribs, supports and "L"s riveted together and on one piece the ribs drilled into the skin.
Sunday, November 02, 2008
Quick status update:
The doors are on, the latches installed, the hinges hinging.
The main gear have had their notches made and are test fit. The front fork is ready for the wheel and tire. The landing gear and strut fittings have finally been bolted into place.
I did have some problems with the Matco wheels. Despite following the drawing, I can not separate the front wheel halves. There does not seem to be a retainer clip or anything like it.



The doors are on, the latches installed, the hinges hinging.
The main gear have had their notches made and are test fit. The front fork is ready for the wheel and tire. The landing gear and strut fittings have finally been bolted into place.
I did have some problems with the Matco wheels. Despite following the drawing, I can not separate the front wheel halves. There does not seem to be a retainer clip or anything like it.



Sunday, October 05, 2008
The pilot side door is now installed along with the door handle and strike plate. The directions were lacking, and a backing plate needed to be made for the provided handle. I unscrewed the inside latch and measured the distance between the screw posts and the center piece.
After making the backing plates the handle was positioned using the backing plate and internal handle to determine where the strike plate needed to be.
The backing plate was then used as a template to drill into the fiberglass door and the handle as screwed together.
On the passenger side the door was thicker than the pilot side. This caused the screws not to reach through and thread into the door handle.
PROGRESS:
Controls ~2h ( 2h )
Fuselage ~251h ( 3h, 3h, 2h, 3h, 7h, 2h, 5h, 2h, 3h, 2h, 2h, 3h, 6h, 2h, 2h, 1.5h, 2.5h, 1h, 2h, 3h, 2h, 3h, 4h, 1h, 2h, 1h, 3h, 4h, 3h, 3h, 4h, 3h, 4h, 4h, 6h, 3h, 3h, 4h, 2h, 2h, 2h, 4h, 2h, 2h, 10h, 4h, 4h, 6h, 3h, 4h , 6h, 3h, 2h, 2h, 5h, 2h, 3h, 3h, 2h , 2h, 3h, 4h, 1h, 1h, 1h, 1h, 3h, 1h, 2h, 2h, 5h, 6h, 3h, 5h )
Wings: ~157.5h ( 1h, 1h, 0.5h, 2.5h, 4h, 1h, 1.5h, 1h, 1.5, 4.5, 1h, 1h, 2h, 4h, 1h, 3h, 1h, 2h, .5h, 1.5h, 2h, 2h, 2h, .5h, 1h, .5h, .5h, 2h,3h, 1h, 3h, 3h, 4h, 2h, 3h, 7h, 3h, 1h, 4h, 1h, 1h, 1h, 4h, 2h, 2h, 2h, 2h, 1h, 2h, 3h, 2h, 1h, 3h, 2h, 2h, 1h, 2h, 3h, 2h, 1h, 1h, 1.5, 2h, 2h, 3h, 2h, 1h, 3h, 2h, 1h, 2h, 1h, 5h, 2h, 1h, 2h, 4h, 2h, 3h, 3h, 3h, 2h, 3h, 2h, 3h, 6h, 3h )
Flaperons: ( DONE! ) 23.5 hours spent ( 3h, 1h, 1h, 1h, 1.5h, 3h, 6h, 3h, 4h, 1h )
Paint Design: 2 hours spent ( 1h, 1h )
Elevator DONE!: ~31.5 hours spent ( 3h, 1.5h, 3h, .5h, 3.5h, 2h, 4h, 1.5h, 2h, 4.5h, 1h, 6h )
Horizontal Stabilizer DONE!: ~28 hours spent, 3 pieces replaced ( 3h, 2h, 2h, 2h, .5h, 1.5h, 3.5h, 1.5h, 5, 4.5, 2h, .5h )
Rudder DONE!, minus horn : ~16 hours spent, ( ~8h, ~8h )
-----------------------
Total Done: ~510h
After making the backing plates the handle was positioned using the backing plate and internal handle to determine where the strike plate needed to be.
The backing plate was then used as a template to drill into the fiberglass door and the handle as screwed together.
On the passenger side the door was thicker than the pilot side. This caused the screws not to reach through and thread into the door handle.
PROGRESS:
Controls ~2h ( 2h )
Fuselage ~251h ( 3h, 3h, 2h, 3h, 7h, 2h, 5h, 2h, 3h, 2h, 2h, 3h, 6h, 2h, 2h, 1.5h, 2.5h, 1h, 2h, 3h, 2h, 3h, 4h, 1h, 2h, 1h, 3h, 4h, 3h, 3h, 4h, 3h, 4h, 4h, 6h, 3h, 3h, 4h, 2h, 2h, 2h, 4h, 2h, 2h, 10h, 4h, 4h, 6h, 3h, 4h , 6h, 3h, 2h, 2h, 5h, 2h, 3h, 3h, 2h , 2h, 3h, 4h, 1h, 1h, 1h, 1h, 3h, 1h, 2h, 2h, 5h, 6h, 3h, 5h )
Wings: ~157.5h ( 1h, 1h, 0.5h, 2.5h, 4h, 1h, 1.5h, 1h, 1.5, 4.5, 1h, 1h, 2h, 4h, 1h, 3h, 1h, 2h, .5h, 1.5h, 2h, 2h, 2h, .5h, 1h, .5h, .5h, 2h,3h, 1h, 3h, 3h, 4h, 2h, 3h, 7h, 3h, 1h, 4h, 1h, 1h, 1h, 4h, 2h, 2h, 2h, 2h, 1h, 2h, 3h, 2h, 1h, 3h, 2h, 2h, 1h, 2h, 3h, 2h, 1h, 1h, 1.5, 2h, 2h, 3h, 2h, 1h, 3h, 2h, 1h, 2h, 1h, 5h, 2h, 1h, 2h, 4h, 2h, 3h, 3h, 3h, 2h, 3h, 2h, 3h, 6h, 3h )
Flaperons: ( DONE! ) 23.5 hours spent ( 3h, 1h, 1h, 1h, 1.5h, 3h, 6h, 3h, 4h, 1h )
Paint Design: 2 hours spent ( 1h, 1h )
Elevator DONE!: ~31.5 hours spent ( 3h, 1.5h, 3h, .5h, 3.5h, 2h, 4h, 1.5h, 2h, 4.5h, 1h, 6h )
Horizontal Stabilizer DONE!: ~28 hours spent, 3 pieces replaced ( 3h, 2h, 2h, 2h, .5h, 1.5h, 3.5h, 1.5h, 5, 4.5, 2h, .5h )
Rudder DONE!, minus horn : ~16 hours spent, ( ~8h, ~8h )
-----------------------
Total Done: ~510h
Sunday, September 28, 2008
The door problem has been resolve. the solution was to trim 20mm off the top edges of the door sills. The major issue was matching the already existing holes into the fuselage frame. This was achieved by using a strap duplicator and the trimmed section of metal itself.Once that was done, the hinges were drilled into the top of the door frame, then the hing was drilled into the door at some key spots to make sure the holes would clear.
After that one of the Dremels was revived with new motor brushes and the doors marked and trimmed.
PROGRESS:
Controls ~2h ( 2h )
Fuselage ~243h ( 3h, 3h, 2h, 3h, 7h, 2h, 5h, 2h, 3h, 2h, 2h, 3h, 6h, 2h, 2h, 1.5h, 2.5h, 1h, 2h, 3h, 2h, 3h, 4h, 1h, 2h, 1h, 3h, 4h, 3h, 3h, 4h, 3h, 4h, 4h, 6h, 3h, 3h, 4h, 2h, 2h, 2h, 4h, 2h, 2h, 10h, 4h, 4h, 6h, 3h, 4h , 6h, 3h, 2h, 2h, 5h, 2h, 3h, 3h, 2h , 2h, 3h, 4h, 1h, 1h, 1h, 1h, 3h, 1h, 2h, 2h, 5h, 6h )
Wings: ~157.5h ( 1h, 1h, 0.5h, 2.5h, 4h, 1h, 1.5h, 1h, 1.5, 4.5, 1h, 1h, 2h, 4h, 1h, 3h, 1h, 2h, .5h, 1.5h, 2h, 2h, 2h, .5h, 1h, .5h, .5h, 2h,3h, 1h, 3h, 3h, 4h, 2h, 3h, 7h, 3h, 1h, 4h, 1h, 1h, 1h, 4h, 2h, 2h, 2h, 2h, 1h, 2h, 3h, 2h, 1h, 3h, 2h, 2h, 1h, 2h, 3h, 2h, 1h, 1h, 1.5, 2h, 2h, 3h, 2h, 1h, 3h, 2h, 1h, 2h, 1h, 5h, 2h, 1h, 2h, 4h, 2h, 3h, 3h, 3h, 2h, 3h, 2h, 3h, 6h, 3h )
Flaperons: ( DONE! ) 23.5 hours spent ( 3h, 1h, 1h, 1h, 1.5h, 3h, 6h, 3h, 4h, 1h )
Paint Design: 2 hours spent ( 1h, 1h )
Elevator DONE!: ~31.5 hours spent ( 3h, 1.5h, 3h, .5h, 3.5h, 2h, 4h, 1.5h, 2h, 4.5h, 1h, 6h )
Horizontal Stabilizer DONE!: ~28 hours spent, 3 pieces replaced ( 3h, 2h, 2h, 2h, .5h, 1.5h, 3.5h, 1.5h, 5, 4.5, 2h, .5h )
Rudder DONE!, minus horn : ~16 hours spent, ( ~8h, ~8h )
-----------------------
Total Done: ~502h
Sunday, August 24, 2008
It has been a while since the log has been updated, but that is not to say progress has not been made.The roof has been drilled into place. The doors have been test fitted, and problems have been found. The windshield is sitting in place. The front landing gear is not being worked on.
PROGRESS:
Controls ~2h ( 2h )
Fuselage ~237h ( 3h, 3h, 2h, 3h, 7h, 2h, 5h, 2h, 3h, 2h, 2h, 3h, 6h, 2h, 2h, 1.5h, 2.5h, 1h, 2h, 3h, 2h, 3h, 4h, 1h, 2h, 1h, 3h, 4h, 3h, 3h, 4h, 3h, 4h, 4h, 6h, 3h, 3h, 4h, 2h, 2h, 2h, 4h, 2h, 2h, 10h, 4h, 4h, 6h, 3h, 4h , 6h, 3h, 2h, 2h, 5h, 2h, 3h, 3h, 2h , 2h, 3h, 4h, 1h, 1h, 1h, 1h, 3h, 1h, 2h, 2h, 5h )
Wings: ~157.5h ( 1h, 1h, 0.5h, 2.5h, 4h, 1h, 1.5h, 1h, 1.5, 4.5, 1h, 1h, 2h, 4h, 1h, 3h, 1h, 2h, .5h, 1.5h, 2h, 2h, 2h, .5h, 1h, .5h, .5h, 2h,3h, 1h, 3h, 3h, 4h, 2h, 3h, 7h, 3h, 1h, 4h, 1h, 1h, 1h, 4h, 2h, 2h, 2h, 2h, 1h, 2h, 3h, 2h, 1h, 3h, 2h, 2h, 1h, 2h, 3h, 2h, 1h, 1h, 1.5, 2h, 2h, 3h, 2h, 1h, 3h, 2h, 1h, 2h, 1h, 5h, 2h, 1h, 2h, 4h, 2h, 3h, 3h, 3h, 2h, 3h, 2h, 3h, 6h, 3h )
Flaperons: ( DONE! ) 23.5 hours spent ( 3h, 1h, 1h, 1h, 1.5h, 3h, 6h, 3h, 4h, 1h )
Paint Design: 2 hours spent ( 1h, 1h )
Elevator DONE!: ~31.5 hours spent ( 3h, 1.5h, 3h, .5h, 3.5h, 2h, 4h, 1.5h, 2h, 4.5h, 1h, 6h )
Horizontal Stabilizer DONE!: ~28 hours spent, 3 pieces replaced ( 3h, 2h, 2h, 2h, .5h, 1.5h, 3.5h, 1.5h, 5, 4.5, 2h, .5h )
Rudder DONE!, minus horn : ~16 hours spent, ( ~8h, ~8h )
-----------------------
Total Done: ~496h
Tuesday, July 22, 2008
Three hours were spent trimming the door sills and getting them drilled into place on the outside.
I decided to modify the trimming on the inside rear. Having the flap of aluminum that goes up next to the wing mount seemed wrong. It could not have provided any strength to the hinge mounting below, it made installation a pain in the ass, it would be hard to reach for riveting and it obscures an inspection point. Given that, I just lopped it off.
PROGRESS:
Fuselage ~232h ( 3h, 3h, 2h, 3h, 7h, 2h, 5h, 2h, 3h, 2h, 2h, 3h, 6h, 2h, 2h, 1.5h, 2.5h, 1h, 2h, 3h, 2h, 3h, 4h, 1h, 2h, 1h, 3h, 4h, 3h, 3h, 4h, 3h, 4h, 4h, 6h, 3h, 3h, 4h, 2h, 2h, 2h, 4h, 2h, 2h, 10h, 4h, 4h, 6h, 3h, 4h , 6h, 3h, 2h, 2h, 5h, 2h, 3h, 3h, 2h , 2h, 3h, 4h, 1h, 1h, 1h, 1h, 3h, 1h, 2h, 2h )
Wings: ~157.5h ( 1h, 1h, 0.5h, 2.5h, 4h, 1h, 1.5h, 1h, 1.5, 4.5, 1h, 1h, 2h, 4h, 1h, 3h, 1h, 2h, .5h, 1.5h, 2h, 2h, 2h, .5h, 1h, .5h, .5h, 2h,3h, 1h, 3h, 3h, 4h, 2h, 3h, 7h, 3h, 1h, 4h, 1h, 1h, 1h, 4h, 2h, 2h, 2h, 2h, 1h, 2h, 3h, 2h, 1h, 3h, 2h, 2h, 1h, 2h, 3h, 2h, 1h, 1h, 1.5, 2h, 2h, 3h, 2h, 1h, 3h, 2h, 1h, 2h, 1h, 5h, 2h, 1h, 2h, 4h, 2h, 3h, 3h, 3h, 2h, 3h, 2h, 3h, 6h, 3h )
Flaperons: ( DONE! ) 23.5 hours spent ( 3h, 1h, 1h, 1h, 1.5h, 3h, 6h, 3h, 4h, 1h )
Paint Design: 2 hours spent ( 1h, 1h )
Elevator DONE!: ~31.5 hours spent ( 3h, 1.5h, 3h, .5h, 3.5h, 2h, 4h, 1.5h, 2h, 4.5h, 1h, 6h )
Horizontal Stabilizer DONE!: ~28 hours spent, 3 pieces replaced ( 3h, 2h, 2h, 2h, .5h, 1.5h, 3.5h, 1.5h, 5, 4.5, 2h, .5h )
Rudder DONE!, minus horn : ~16 hours spent, ( ~8h, ~8h )
-----------------------
Total Done: ~489h
I decided to modify the trimming on the inside rear. Having the flap of aluminum that goes up next to the wing mount seemed wrong. It could not have provided any strength to the hinge mounting below, it made installation a pain in the ass, it would be hard to reach for riveting and it obscures an inspection point. Given that, I just lopped it off.
PROGRESS:
Fuselage ~232h ( 3h, 3h, 2h, 3h, 7h, 2h, 5h, 2h, 3h, 2h, 2h, 3h, 6h, 2h, 2h, 1.5h, 2.5h, 1h, 2h, 3h, 2h, 3h, 4h, 1h, 2h, 1h, 3h, 4h, 3h, 3h, 4h, 3h, 4h, 4h, 6h, 3h, 3h, 4h, 2h, 2h, 2h, 4h, 2h, 2h, 10h, 4h, 4h, 6h, 3h, 4h , 6h, 3h, 2h, 2h, 5h, 2h, 3h, 3h, 2h , 2h, 3h, 4h, 1h, 1h, 1h, 1h, 3h, 1h, 2h, 2h )
Wings: ~157.5h ( 1h, 1h, 0.5h, 2.5h, 4h, 1h, 1.5h, 1h, 1.5, 4.5, 1h, 1h, 2h, 4h, 1h, 3h, 1h, 2h, .5h, 1.5h, 2h, 2h, 2h, .5h, 1h, .5h, .5h, 2h,3h, 1h, 3h, 3h, 4h, 2h, 3h, 7h, 3h, 1h, 4h, 1h, 1h, 1h, 4h, 2h, 2h, 2h, 2h, 1h, 2h, 3h, 2h, 1h, 3h, 2h, 2h, 1h, 2h, 3h, 2h, 1h, 1h, 1.5, 2h, 2h, 3h, 2h, 1h, 3h, 2h, 1h, 2h, 1h, 5h, 2h, 1h, 2h, 4h, 2h, 3h, 3h, 3h, 2h, 3h, 2h, 3h, 6h, 3h )
Flaperons: ( DONE! ) 23.5 hours spent ( 3h, 1h, 1h, 1h, 1.5h, 3h, 6h, 3h, 4h, 1h )
Paint Design: 2 hours spent ( 1h, 1h )
Elevator DONE!: ~31.5 hours spent ( 3h, 1.5h, 3h, .5h, 3.5h, 2h, 4h, 1.5h, 2h, 4.5h, 1h, 6h )
Horizontal Stabilizer DONE!: ~28 hours spent, 3 pieces replaced ( 3h, 2h, 2h, 2h, .5h, 1.5h, 3.5h, 1.5h, 5, 4.5, 2h, .5h )
Rudder DONE!, minus horn : ~16 hours spent, ( ~8h, ~8h )
-----------------------
Total Done: ~489h
I spent about two hours trying to figure out how to trim the door sill ( 7F19-12 ).The plans and directions are very lacking about the door sills. The forward half of the sill is easy to figure out, the outside rear is strange ( but figure-out-able ), but the rear inside is an enigma.
A quick search of the Matronics list and Google provided nothing.
PROGRESS:
Fuselage ~229h ( 3h, 3h, 2h, 3h, 7h, 2h, 5h, 2h, 3h, 2h, 2h, 3h, 6h, 2h, 2h, 1.5h, 2.5h, 1h, 2h, 3h, 2h, 3h, 4h, 1h, 2h, 1h, 3h, 4h, 3h, 3h, 4h, 3h, 4h, 4h, 6h, 3h, 3h, 4h, 2h, 2h, 2h, 4h, 2h, 2h, 10h, 4h, 4h, 6h, 3h, 4h , 6h, 3h, 2h, 2h, 5h, 2h, 3h, 3h, 2h , 2h, 3h, 4h, 1h, 1h, 1h, 1h, 3h, 1h, 2h, 2h )
Wings: ~157.5h ( 1h, 1h, 0.5h, 2.5h, 4h, 1h, 1.5h, 1h, 1.5, 4.5, 1h, 1h, 2h, 4h, 1h, 3h, 1h, 2h, .5h, 1.5h, 2h, 2h, 2h, .5h, 1h, .5h, .5h, 2h,3h, 1h, 3h, 3h, 4h, 2h, 3h, 7h, 3h, 1h, 4h, 1h, 1h, 1h, 4h, 2h, 2h, 2h, 2h, 1h, 2h, 3h, 2h, 1h, 3h, 2h, 2h, 1h, 2h, 3h, 2h, 1h, 1h, 1.5, 2h, 2h, 3h, 2h, 1h, 3h, 2h, 1h, 2h, 1h, 5h, 2h, 1h, 2h, 4h, 2h, 3h, 3h, 3h, 2h, 3h, 2h, 3h, 6h )
Flaperons: ( DONE! ) 23.5 hours spent ( 3h, 1h, 1h, 1h, 1.5h, 3h, 6h, 3h, 4h, 1h )
Paint Design: 2 hours spent ( 1h, 1h )
Elevator DONE!: ~31.5 hours spent ( 3h, 1.5h, 3h, .5h, 3.5h, 2h, 4h, 1.5h, 2h, 4.5h, 1h, 6h )
Horizontal Stabilizer DONE!: ~28 hours spent, 3 pieces replaced ( 3h, 2h, 2h, 2h, .5h, 1.5h, 3.5h, 1.5h, 5, 4.5, 2h, .5h )
Rudder DONE!, minus horn : ~16 hours spent, ( ~8h, ~8h )
-----------------------
Total Done: ~486h
Wednesday, July 16, 2008
It has been a while since the worklog has been updated, but progress has not totally stalled.About six hours of work have gotten snuck into the project between life and Arlington.
The firewall has been fully clean, protected, reassembled and riveted together. In addition all the forward fuselage parts have been clecoed back together.
Some amount of time has been spent enlarging holes, finding missed holes, ect.
The next order of business are the doors. The directions are skimpier on these parts, so inferences need to be made. One issue is the existing holes that join the V-brace with the aluminum tubing along the top. The door sill sits on top of the tube, and it is impossible to back drill from the tube side. After talking to Zenith it is acceptable to 1) Use a strap duplicator to find the holes OR 2) Trim the door sill in such a way that these holes are bypassed.
Also I received clarification on the install order. 1) Doors 2) Skylight 3) Windshield.
PROGRESS:
Fuselage ~227h ( 3h, 3h, 2h, 3h, 7h, 2h, 5h, 2h, 3h, 2h, 2h, 3h, 6h, 2h, 2h, 1.5h, 2.5h, 1h, 2h, 3h, 2h, 3h, 4h, 1h, 2h, 1h, 3h, 4h, 3h, 3h, 4h, 3h, 4h, 4h, 6h, 3h, 3h, 4h, 2h, 2h, 2h, 4h, 2h, 2h, 10h, 4h, 4h, 6h, 3h, 4h , 6h, 3h, 2h, 2h, 5h, 2h, 3h, 3h, 2h , 2h, 3h, 4h, 1h, 1h, 1h, 1h, 3h, 1h, 2h )
Wings: ~157.5h ( 1h, 1h, 0.5h, 2.5h, 4h, 1h, 1.5h, 1h, 1.5, 4.5, 1h, 1h, 2h, 4h, 1h, 3h, 1h, 2h, .5h, 1.5h, 2h, 2h, 2h, .5h, 1h, .5h, .5h, 2h,3h, 1h, 3h, 3h, 4h, 2h, 3h, 7h, 3h, 1h, 4h, 1h, 1h, 1h, 4h, 2h, 2h, 2h, 2h, 1h, 2h, 3h, 2h, 1h, 3h, 2h, 2h, 1h, 2h, 3h, 2h, 1h, 1h, 1.5, 2h, 2h, 3h, 2h, 1h, 3h, 2h, 1h, 2h, 1h, 5h, 2h, 1h, 2h, 4h, 2h, 3h, 3h, 3h, 2h, 3h, 2h, 3h, 6h )
Flaperons: ( DONE! ) 23.5 hours spent ( 3h, 1h, 1h, 1h, 1.5h, 3h, 6h, 3h, 4h, 1h )
Paint Design: 2 hours spent ( 1h, 1h )
Elevator DONE!: ~31.5 hours spent ( 3h, 1.5h, 3h, .5h, 3.5h, 2h, 4h, 1.5h, 2h, 4.5h, 1h, 6h )
Horizontal Stabilizer DONE!: ~28 hours spent, 3 pieces replaced ( 3h, 2h, 2h, 2h, .5h, 1.5h, 3.5h, 1.5h, 5, 4.5, 2h, .5h )
Rudder DONE!, minus horn : ~16 hours spent, ( ~8h, ~8h )
-----------------------
Total Done: ~486h
Sunday, June 22, 2008
I spent about two hours Sunday cleaning up most of the firewall and then applying corrosion protections. The landing fork section still needs to be drilled to size.
One major problem is the lack of A5 clecos. Make sure you have at least 100 of them.
PROGRESS:
Fuselage ~221h ( 3h, 3h, 2h, 3h, 7h, 2h, 5h, 2h, 3h, 2h, 2h, 3h, 6h, 2h, 2h, 1.5h, 2.5h, 1h, 2h, 3h, 2h, 3h, 4h, 1h, 2h, 1h, 3h, 4h, 3h, 3h, 4h, 3h, 4h, 4h, 6h, 3h, 3h, 4h, 2h, 2h, 2h, 4h, 2h, 2h, 10h, 4h, 4h, 6h, 3h, 4h , 6h, 3h, 2h, 2h, 5h, 2h, 3h, 3h, 2h , 2h, 3h, 4h, 1h, 1h, 1h, 1h, 3h, 1h, 2h )
Wings: ~157.5h ( 1h, 1h, 0.5h, 2.5h, 4h, 1h, 1.5h, 1h, 1.5, 4.5, 1h, 1h, 2h, 4h, 1h, 3h, 1h, 2h, .5h, 1.5h, 2h, 2h, 2h, .5h, 1h, .5h, .5h, 2h,3h, 1h, 3h, 3h, 4h, 2h, 3h, 7h, 3h, 1h, 4h, 1h, 1h, 1h, 4h, 2h, 2h, 2h, 2h, 1h, 2h, 3h, 2h, 1h, 3h, 2h, 2h, 1h, 2h, 3h, 2h, 1h, 1h, 1.5, 2h, 2h, 3h, 2h, 1h, 3h, 2h, 1h, 2h, 1h, 5h, 2h, 1h, 2h, 4h, 2h, 3h, 3h, 3h, 2h, 3h, 2h, 3h )
Flaperons: ( DONE! ) 23.5 hours spent ( 3h, 1h, 1h, 1h, 1.5h, 3h, 6h, 3h, 4h, 1h )
Paint Design: 2 hours spent ( 1h, 1h )
Elevator DONE!: ~31.5 hours spent ( 3h, 1.5h, 3h, .5h, 3.5h, 2h, 4h, 1.5h, 2h, 4.5h, 1h, 6h )
Horizontal Stabilizer DONE!: ~28 hours spent, 3 pieces replaced ( 3h, 2h, 2h, 2h, .5h, 1.5h, 3.5h, 1.5h, 5, 4.5, 2h, .5h )
Rudder DONE!, minus horn : ~16 hours spent, ( ~8h, ~8h )
-----------------------
Total Done: ~480h
One major problem is the lack of A5 clecos. Make sure you have at least 100 of them.
PROGRESS:
Fuselage ~221h ( 3h, 3h, 2h, 3h, 7h, 2h, 5h, 2h, 3h, 2h, 2h, 3h, 6h, 2h, 2h, 1.5h, 2.5h, 1h, 2h, 3h, 2h, 3h, 4h, 1h, 2h, 1h, 3h, 4h, 3h, 3h, 4h, 3h, 4h, 4h, 6h, 3h, 3h, 4h, 2h, 2h, 2h, 4h, 2h, 2h, 10h, 4h, 4h, 6h, 3h, 4h , 6h, 3h, 2h, 2h, 5h, 2h, 3h, 3h, 2h , 2h, 3h, 4h, 1h, 1h, 1h, 1h, 3h, 1h, 2h )
Wings: ~157.5h ( 1h, 1h, 0.5h, 2.5h, 4h, 1h, 1.5h, 1h, 1.5, 4.5, 1h, 1h, 2h, 4h, 1h, 3h, 1h, 2h, .5h, 1.5h, 2h, 2h, 2h, .5h, 1h, .5h, .5h, 2h,3h, 1h, 3h, 3h, 4h, 2h, 3h, 7h, 3h, 1h, 4h, 1h, 1h, 1h, 4h, 2h, 2h, 2h, 2h, 1h, 2h, 3h, 2h, 1h, 3h, 2h, 2h, 1h, 2h, 3h, 2h, 1h, 1h, 1.5, 2h, 2h, 3h, 2h, 1h, 3h, 2h, 1h, 2h, 1h, 5h, 2h, 1h, 2h, 4h, 2h, 3h, 3h, 3h, 2h, 3h, 2h, 3h )
Flaperons: ( DONE! ) 23.5 hours spent ( 3h, 1h, 1h, 1h, 1.5h, 3h, 6h, 3h, 4h, 1h )
Paint Design: 2 hours spent ( 1h, 1h )
Elevator DONE!: ~31.5 hours spent ( 3h, 1.5h, 3h, .5h, 3.5h, 2h, 4h, 1.5h, 2h, 4.5h, 1h, 6h )
Horizontal Stabilizer DONE!: ~28 hours spent, 3 pieces replaced ( 3h, 2h, 2h, 2h, .5h, 1.5h, 3.5h, 1.5h, 5, 4.5, 2h, .5h )
Rudder DONE!, minus horn : ~16 hours spent, ( ~8h, ~8h )
-----------------------
Total Done: ~480h
I have finally started drilling out the holes in the firewall. These have been A3 size since the initial assembly just in case I needed to adjust something when working on the rest of the fuselage.
Today I noticed a small amount of corrosion around one of the clecos on the firewall, so it was decided to drill everything out, deburr, acid etch, scotchbrite and then zinc as soon as possible.
All of the holes ( save the engine mount bolt holes ) that lay in the horizontal plane are drilled.
PROGRESS:
Fuselage ~219h ( 3h, 3h, 2h, 3h, 7h, 2h, 5h, 2h, 3h, 2h, 2h, 3h, 6h, 2h, 2h, 1.5h, 2.5h, 1h, 2h, 3h, 2h, 3h, 4h, 1h, 2h, 1h, 3h, 4h, 3h, 3h, 4h, 3h, 4h, 4h, 6h, 3h, 3h, 4h, 2h, 2h, 2h, 4h, 2h, 2h, 10h, 4h, 4h, 6h, 3h, 4h , 6h, 3h, 2h, 2h, 5h, 2h, 3h, 3h, 2h , 2h, 3h, 4h, 1h, 1h, 1h, 1h, 3h, 1h )
Wings: ~157.5h ( 1h, 1h, 0.5h, 2.5h, 4h, 1h, 1.5h, 1h, 1.5, 4.5, 1h, 1h, 2h, 4h, 1h, 3h, 1h, 2h, .5h, 1.5h, 2h, 2h, 2h, .5h, 1h, .5h, .5h, 2h,3h, 1h, 3h, 3h, 4h, 2h, 3h, 7h, 3h, 1h, 4h, 1h, 1h, 1h, 4h, 2h, 2h, 2h, 2h, 1h, 2h, 3h, 2h, 1h, 3h, 2h, 2h, 1h, 2h, 3h, 2h, 1h, 1h, 1.5, 2h, 2h, 3h, 2h, 1h, 3h, 2h, 1h, 2h, 1h, 5h, 2h, 1h, 2h, 4h, 2h, 3h, 3h, 3h, 2h, 3h, 2h, 3h )
Flaperons: ( DONE! ) 23.5 hours spent ( 3h, 1h, 1h, 1h, 1.5h, 3h, 6h, 3h, 4h, 1h )
Paint Design: 2 hours spent ( 1h, 1h )
Elevator DONE!: ~31.5 hours spent ( 3h, 1.5h, 3h, .5h, 3.5h, 2h, 4h, 1.5h, 2h, 4.5h, 1h, 6h )
Horizontal Stabilizer DONE!: ~28 hours spent, 3 pieces replaced ( 3h, 2h, 2h, 2h, .5h, 1.5h, 3.5h, 1.5h, 5, 4.5, 2h, .5h )
Rudder DONE!, minus horn : ~16 hours spent, ( ~8h, ~8h )
-----------------------
Total Done: ~478h
Today I noticed a small amount of corrosion around one of the clecos on the firewall, so it was decided to drill everything out, deburr, acid etch, scotchbrite and then zinc as soon as possible.
All of the holes ( save the engine mount bolt holes ) that lay in the horizontal plane are drilled.
PROGRESS:
Fuselage ~219h ( 3h, 3h, 2h, 3h, 7h, 2h, 5h, 2h, 3h, 2h, 2h, 3h, 6h, 2h, 2h, 1.5h, 2.5h, 1h, 2h, 3h, 2h, 3h, 4h, 1h, 2h, 1h, 3h, 4h, 3h, 3h, 4h, 3h, 4h, 4h, 6h, 3h, 3h, 4h, 2h, 2h, 2h, 4h, 2h, 2h, 10h, 4h, 4h, 6h, 3h, 4h , 6h, 3h, 2h, 2h, 5h, 2h, 3h, 3h, 2h , 2h, 3h, 4h, 1h, 1h, 1h, 1h, 3h, 1h )
Wings: ~157.5h ( 1h, 1h, 0.5h, 2.5h, 4h, 1h, 1.5h, 1h, 1.5, 4.5, 1h, 1h, 2h, 4h, 1h, 3h, 1h, 2h, .5h, 1.5h, 2h, 2h, 2h, .5h, 1h, .5h, .5h, 2h,3h, 1h, 3h, 3h, 4h, 2h, 3h, 7h, 3h, 1h, 4h, 1h, 1h, 1h, 4h, 2h, 2h, 2h, 2h, 1h, 2h, 3h, 2h, 1h, 3h, 2h, 2h, 1h, 2h, 3h, 2h, 1h, 1h, 1.5, 2h, 2h, 3h, 2h, 1h, 3h, 2h, 1h, 2h, 1h, 5h, 2h, 1h, 2h, 4h, 2h, 3h, 3h, 3h, 2h, 3h, 2h, 3h )
Flaperons: ( DONE! ) 23.5 hours spent ( 3h, 1h, 1h, 1h, 1.5h, 3h, 6h, 3h, 4h, 1h )
Paint Design: 2 hours spent ( 1h, 1h )
Elevator DONE!: ~31.5 hours spent ( 3h, 1.5h, 3h, .5h, 3.5h, 2h, 4h, 1.5h, 2h, 4.5h, 1h, 6h )
Horizontal Stabilizer DONE!: ~28 hours spent, 3 pieces replaced ( 3h, 2h, 2h, 2h, .5h, 1.5h, 3.5h, 1.5h, 5, 4.5, 2h, .5h )
Rudder DONE!, minus horn : ~16 hours spent, ( ~8h, ~8h )
-----------------------
Total Done: ~478h
Tuesday, June 03, 2008
The color of the clecos on the nose skins have been changed from silver to copper.
PROGRESS:
Fuselage ~216h ( 3h, 3h, 2h, 3h, 7h, 2h, 5h, 2h, 3h, 2h, 2h, 3h, 6h, 2h, 2h, 1.5h, 2.5h, 1h, 2h, 3h, 2h, 3h, 4h, 1h, 2h, 1h, 3h, 4h, 3h, 3h, 4h, 3h, 4h, 4h, 6h, 3h, 3h, 4h, 2h, 2h, 2h, 4h, 2h, 2h, 10h, 4h, 4h, 6h, 3h, 4h , 6h, 3h, 2h, 2h, 5h, 2h, 3h, 3h, 2h , 2h, 3h, 4h, 1h, 1h, 1h, 1h, 3h, 1h )
Wings: ~157.5h ( 1h, 1h, 0.5h, 2.5h, 4h, 1h, 1.5h, 1h, 1.5, 4.5, 1h, 1h, 2h, 4h, 1h, 3h, 1h, 2h, .5h, 1.5h, 2h, 2h, 2h, .5h, 1h, .5h, .5h, 2h,3h, 1h, 3h, 3h, 4h, 2h, 3h, 7h, 3h, 1h, 4h, 1h, 1h, 1h, 4h, 2h, 2h, 2h, 2h, 1h, 2h, 3h, 2h, 1h, 3h, 2h, 2h, 1h, 2h, 3h, 2h, 1h, 1h, 1.5, 2h, 2h, 3h, 2h, 1h, 3h, 2h, 1h, 2h, 1h, 5h, 2h, 1h, 2h, 4h, 2h, 3h, 3h, 3h, 2h, 3h, 2h )
Flaperons: ( DONE! ) 23.5 hours spent ( 3h, 1h, 1h, 1h, 1.5h, 3h, 6h, 3h, 4h, 1h )
Paint Design: 2 hours spent ( 1h, 1h )
Elevator DONE!: ~31.5 hours spent ( 3h, 1.5h, 3h, .5h, 3.5h, 2h, 4h, 1.5h, 2h, 4.5h, 1h, 6h )
Horizontal Stabilizer DONE!: ~28 hours spent, 3 pieces replaced ( 3h, 2h, 2h, 2h, .5h, 1.5h, 3.5h, 1.5h, 5, 4.5, 2h, .5h )
Rudder DONE!, minus horn : ~16 hours spent, ( ~8h, ~8h )
-----------------------
Total Done: ~478h
PROGRESS:
Fuselage ~216h ( 3h, 3h, 2h, 3h, 7h, 2h, 5h, 2h, 3h, 2h, 2h, 3h, 6h, 2h, 2h, 1.5h, 2.5h, 1h, 2h, 3h, 2h, 3h, 4h, 1h, 2h, 1h, 3h, 4h, 3h, 3h, 4h, 3h, 4h, 4h, 6h, 3h, 3h, 4h, 2h, 2h, 2h, 4h, 2h, 2h, 10h, 4h, 4h, 6h, 3h, 4h , 6h, 3h, 2h, 2h, 5h, 2h, 3h, 3h, 2h , 2h, 3h, 4h, 1h, 1h, 1h, 1h, 3h, 1h )
Wings: ~157.5h ( 1h, 1h, 0.5h, 2.5h, 4h, 1h, 1.5h, 1h, 1.5, 4.5, 1h, 1h, 2h, 4h, 1h, 3h, 1h, 2h, .5h, 1.5h, 2h, 2h, 2h, .5h, 1h, .5h, .5h, 2h,3h, 1h, 3h, 3h, 4h, 2h, 3h, 7h, 3h, 1h, 4h, 1h, 1h, 1h, 4h, 2h, 2h, 2h, 2h, 1h, 2h, 3h, 2h, 1h, 3h, 2h, 2h, 1h, 2h, 3h, 2h, 1h, 1h, 1.5, 2h, 2h, 3h, 2h, 1h, 3h, 2h, 1h, 2h, 1h, 5h, 2h, 1h, 2h, 4h, 2h, 3h, 3h, 3h, 2h, 3h, 2h )
Flaperons: ( DONE! ) 23.5 hours spent ( 3h, 1h, 1h, 1h, 1.5h, 3h, 6h, 3h, 4h, 1h )
Paint Design: 2 hours spent ( 1h, 1h )
Elevator DONE!: ~31.5 hours spent ( 3h, 1.5h, 3h, .5h, 3.5h, 2h, 4h, 1.5h, 2h, 4.5h, 1h, 6h )
Horizontal Stabilizer DONE!: ~28 hours spent, 3 pieces replaced ( 3h, 2h, 2h, 2h, .5h, 1.5h, 3.5h, 1.5h, 5, 4.5, 2h, .5h )
Rudder DONE!, minus horn : ~16 hours spent, ( ~8h, ~8h )
-----------------------
Total Done: ~478h
Sunday, May 11, 2008
Saturday brought another two hours of work on the dashboard.The upper ( "L" ) angle was drilled into place. The lower rivet lines of the top skin were also drilled into place.
In addition the top skin was trimmed per the plans.
After getting some unexpected time off, I have decided to fly the 150 to Oshkosh this year. The preliminary planning has started. It will be a long flight in the 150 as it cruises at only about 85MPH... about the same speed as the 701!
PROGRESS:
Fuselage ~215h ( 3h, 3h, 2h, 3h, 7h, 2h, 5h, 2h, 3h, 2h, 2h, 3h, 6h, 2h, 2h, 1.5h, 2.5h, 1h, 2h, 3h, 2h, 3h, 4h, 1h, 2h, 1h, 3h, 4h, 3h, 3h, 4h, 3h, 4h, 4h, 6h, 3h, 3h, 4h, 2h, 2h, 2h, 4h, 2h, 2h, 10h, 4h, 4h, 6h, 3h, 4h , 6h, 3h, 2h, 2h, 5h, 2h, 3h, 3h, 2h , 2h, 3h, 4h, 1h, 1h, 1h, 1h, 3h )
Wings: ~157.5h ( 1h, 1h, 0.5h, 2.5h, 4h, 1h, 1.5h, 1h, 1.5, 4.5, 1h, 1h, 2h, 4h, 1h, 3h, 1h, 2h, .5h, 1.5h, 2h, 2h, 2h, .5h, 1h, .5h, .5h, 2h,3h, 1h, 3h, 3h, 4h, 2h, 3h, 7h, 3h, 1h, 4h, 1h, 1h, 1h, 4h, 2h, 2h, 2h, 2h, 1h, 2h, 3h, 2h, 1h, 3h, 2h, 2h, 1h, 2h, 3h, 2h, 1h, 1h, 1.5, 2h, 2h, 3h, 2h, 1h, 3h, 2h, 1h, 2h, 1h, 5h, 2h, 1h, 2h, 4h, 2h, 3h, 3h, 3h, 2h, 3h, 2h )
Flaperons: ( DONE! ) 23.5 hours spent ( 3h, 1h, 1h, 1h, 1.5h, 3h, 6h, 3h, 4h, 1h )
Paint Design: 2 hours spent ( 1h, 1h )
Elevator DONE!: ~31.5 hours spent ( 3h, 1.5h, 3h, .5h, 3.5h, 2h, 4h, 1.5h, 2h, 4.5h, 1h, 6h )
Horizontal Stabilizer DONE!: ~28 hours spent, 3 pieces replaced ( 3h, 2h, 2h, 2h, .5h, 1.5h, 3.5h, 1.5h, 5, 4.5, 2h, .5h )
Rudder DONE!, minus horn : ~16 hours spent, ( ~8h, ~8h )
-----------------------
Total Done: ~477h
Monday, May 05, 2008
Sunday, April 06, 2008
Saturday night saw three hours of progress.The first draft of layout for the instrument panel was done. I found various pictures of the planed instruments and then printed them out at actual size. Some items got a hand drawn picture as a placeholder. A single piece of tape was used for each "instrument" or "control" to hold it onto the panel. Everything is very easily repositioned.
The instrument plane's flange was also drilled in preparation for the dashboard, and a piece of ("L") was drilled into place that holds the instrument plane at equidistance from the firewall.
I laid out and cut 7F14-2 per the plans, and had to open up the holes to make it fit well. The holes extend too far forward and are too wide at the inside to be a perfect fit. A much better plan would have been to cut a template from cardboard THEN use that to make the real piece. In the end I am going to cover the dashboard anyway with upholstery, but anyone wanting to keep it as bare metal may want to take precautions.
The big issue of the night was with the instrument plane and some ("L") angle that runs from it forward. The basic idea of the piece is to be even along the top edge with 7F14-3, the forward side skin. The problem is that a crimp in the flange of the instrument plane would interfere with it.
The obvious solution seems to move the ("L") down ~10mm, but since 7F14-6R ( aluminum plate ) is already drilled into position, I can not trim the side skin to be even. Given the size of 7F14-4 ( top skin ) there may be enough play for it to not matter.

PROGRESS:
Fuselage ~211h ( 3h, 3h, 2h, 3h, 7h, 2h, 5h, 2h, 3h, 2h, 2h, 3h, 6h, 2h, 2h, 1.5h, 2.5h, 1h, 2h, 3h, 2h, 3h, 4h, 1h, 2h, 1h, 3h, 4h, 3h, 3h, 4h, 3h, 4h, 4h, 6h, 3h, 3h, 4h, 2h, 2h, 2h, 4h, 2h, 2h, 10h, 4h, 4h, 6h, 3h, 4h , 6h, 3h, 2h, 2h, 5h, 2h, 3h, 3h, 2h , 2h, 3h, 4h, 1h, 1h, 1h, 1h, 3h )
Wings: ~157.5h ( 1h, 1h, 0.5h, 2.5h, 4h, 1h, 1.5h, 1h, 1.5, 4.5, 1h, 1h, 2h, 4h, 1h, 3h, 1h, 2h, .5h, 1.5h, 2h, 2h, 2h, .5h, 1h, .5h, .5h, 2h,3h, 1h, 3h, 3h, 4h, 2h, 3h, 7h, 3h, 1h, 4h, 1h, 1h, 1h, 4h, 2h, 2h, 2h, 2h, 1h, 2h, 3h, 2h, 1h, 3h, 2h, 2h, 1h, 2h, 3h, 2h, 1h, 1h, 1.5, 2h, 2h, 3h, 2h, 1h, 3h, 2h, 1h, 2h, 1h, 5h, 2h, 1h, 2h, 4h, 2h, 3h, 3h, 3h, 3h )
Flaperons: ( DONE! ) 23.5 hours spent ( 3h, 1h, 1h, 1h, 1.5h, 3h, 6h, 3h, 4h, 1h )
Paint Design: 2 hours spent ( 1h, 1h )
Elevator DONE!: ~31.5 hours spent ( 3h, 1.5h, 3h, .5h, 3.5h, 2h, 4h, 1.5h, 2h, 4.5h, 1h, 6h )
Horizontal Stabilizer DONE!: ~28 hours spent, 3 pieces replaced ( 3h, 2h, 2h, 2h, .5h, 1.5h, 3.5h, 1.5h, 5, 4.5, 2h, .5h )
Rudder DONE!, minus horn : ~16 hours spent, ( ~8h, ~8h )
-----------------------
Total Done: ~473h
Sunday, March 30, 2008
Spent three hours working on the instrument panel.The gussets that join the panel to the cabin frame were fabricated and drilled into place. The panel bottom channel ( 7F15-1 ) was also drilled into place.
First I would suggest drilling the channel into the panel first. This gives you a better idea of where the gussets should go.
Despite some careful initial fitting and measurement, the gussets ( 7F15-2 ) are a little further inside that I would like. By centering the panel channel first you can get a better idea of where the radius of the gusset should be.
Also you will have to trim the top of the gusset so it can clear the panel. The plans call for a line at 75mm up, but try making the line at ~100mm. Of course, your milage may vary.
PROGRESS:
Fuselage ~208h ( 3h, 3h, 2h, 3h, 7h, 2h, 5h, 2h, 3h, 2h, 2h, 3h, 6h, 2h, 2h, 1.5h, 2.5h, 1h, 2h, 3h, 2h, 3h, 4h, 1h, 2h, 1h, 3h, 4h, 3h, 3h, 4h, 3h, 4h, 4h, 6h, 3h, 3h, 4h, 2h, 2h, 2h, 4h, 2h, 2h, 10h, 4h, 4h, 6h, 3h, 4h , 6h, 3h, 2h, 2h, 5h, 2h, 3h, 3h, 2h , 2h, 3h, 4h, 1h, 1h, 1h, 1h, 3h )
Wings: ~157.5h ( 1h, 1h, 0.5h, 2.5h, 4h, 1h, 1.5h, 1h, 1.5, 4.5, 1h, 1h, 2h, 4h, 1h, 3h, 1h, 2h, .5h, 1.5h, 2h, 2h, 2h, .5h, 1h, .5h, .5h, 2h,3h, 1h, 3h, 3h, 4h, 2h, 3h, 7h, 3h, 1h, 4h, 1h, 1h, 1h, 4h, 2h, 2h, 2h, 2h, 1h, 2h, 3h, 2h, 1h, 3h, 2h, 2h, 1h, 2h, 3h, 2h, 1h, 1h, 1.5, 2h, 2h, 3h, 2h, 1h, 3h, 2h, 1h, 2h, 1h, 5h, 2h, 1h, 2h, 4h, 2h, 3h, 3h, 3h )
Flaperons: ( DONE! ) 23.5 hours spent ( 3h, 1h, 1h, 1h, 1.5h, 3h, 6h, 3h, 4h, 1h )
Paint Design: 2 hours spent ( 1h, 1h )
Elevator DONE!: ~31.5 hours spent ( 3h, 1.5h, 3h, .5h, 3.5h, 2h, 4h, 1.5h, 2h, 4.5h, 1h, 6h )
Horizontal Stabilizer DONE!: ~28 hours spent, 3 pieces replaced ( 3h, 2h, 2h, 2h, .5h, 1.5h, 3.5h, 1.5h, 5, 4.5, 2h, .5h )
Rudder DONE!, minus horn : ~16 hours spent, ( ~8h, ~8h )
-----------------------
Total Done: ~470h
Sunday, March 23, 2008
Got about an hour of work in. The ("Z") angle on the forward fuselage skin on the passenger side got measured, trimmed and drilled into place.
Once the initial rear hole is drilled into place and the position where it crosses the plate is determined, it is much easier to predrill the required holes into the channel, then drill into the fuselage skin.
The Rotax was finally uncrated ( mostly ). The shipping crate was secured in an unusual manner and required bending of metal to open. A quick inspection did not reveal anything missing or damaged.
PROGRESS:
Fuselage ~204h ( 3h, 3h, 2h, 3h, 7h, 2h, 5h, 2h, 3h, 2h, 2h, 3h, 6h, 2h, 2h, 1.5h, 2.5h, 1h, 2h, 3h, 2h, 3h, 4h, 1h, 2h, 1h, 3h, 4h, 3h, 3h, 4h, 3h, 4h, 4h, 6h, 3h, 3h, 4h, 2h, 2h, 2h, 4h, 2h, 2h, 10h, 4h, 4h, 6h, 3h, 4h , 6h, 3h, 2h, 2h, 5h, 2h, 3h, 3h, 2h , 2h, 3h, 4h, 1h, 1h, 1h )
Wings: ~157.5h ( 1h, 1h, 0.5h, 2.5h, 4h, 1h, 1.5h, 1h, 1.5, 4.5, 1h, 1h, 2h, 4h, 1h, 3h, 1h, 2h, .5h, 1.5h, 2h, 2h, 2h, .5h, 1h, .5h, .5h, 2h,3h, 1h, 3h, 3h, 4h, 2h, 3h, 7h, 3h, 1h, 4h, 1h, 1h, 1h, 4h, 2h, 2h, 2h, 2h, 1h, 2h, 3h, 2h, 1h, 3h, 2h, 2h, 1h, 2h, 3h, 2h, 1h, 1h, 1.5, 2h, 2h, 3h, 2h, 1h, 3h, 2h, 1h, 2h, 1h, 5h, 2h, 1h, 2h, 4h, 2h, 3h, 3h, 3h )
Flaperons: ( DONE! ) 23.5 hours spent ( 3h, 1h, 1h, 1h, 1.5h, 3h, 6h, 3h, 4h, 1h )
Paint Design: 2 hours spent ( 1h, 1h )
Elevator DONE!: ~31.5 hours spent ( 3h, 1.5h, 3h, .5h, 3.5h, 2h, 4h, 1.5h, 2h, 4.5h, 1h, 6h )
Horizontal Stabilizer DONE!: ~28 hours spent, 3 pieces replaced ( 3h, 2h, 2h, 2h, .5h, 1.5h, 3.5h, 1.5h, 5, 4.5, 2h, .5h )
Rudder DONE!, minus horn : ~16 hours spent, ( ~8h, ~8h )
-----------------------
Total Done: ~466h
Wednesday, March 19, 2008
Saturday, March 15, 2008
I spent about an hour on the fuselage. First we finished drilling the side skin extrusions into the nose skin, then we trimmed and drilled into place the upper ("Z") length that runs along the nose skin.
It turns out that the best way to approach the placement is to drill the aft most hole, then have a help hold the piece AND provide a buttress on the outside while you drill from the inside.
Also one of our EAA chapter members held a project visit today for their very nice looking 5151. Metal really dominates building so seeing how a wood project goes together was refreshing.
PROGRESS:
Fuselage ~203h ( 3h, 3h, 2h, 3h, 7h, 2h, 5h, 2h, 3h, 2h, 2h, 3h, 6h, 2h, 2h, 1.5h, 2.5h, 1h, 2h, 3h, 2h, 3h, 4h, 1h, 2h, 1h, 3h, 4h, 3h, 3h, 4h, 3h, 4h, 4h, 6h, 3h, 3h, 4h, 2h, 2h, 2h, 4h, 2h, 2h, 10h, 4h, 4h, 6h, 3h, 4h , 6h, 3h, 2h, 2h, 5h, 2h, 3h, 3h, 2h , 2h, 3h, 4h, 1h, 1h )
Wings: ~157.5h ( 1h, 1h, 0.5h, 2.5h, 4h, 1h, 1.5h, 1h, 1.5, 4.5, 1h, 1h, 2h, 4h, 1h, 3h, 1h, 2h, .5h, 1.5h, 2h, 2h, 2h, .5h, 1h, .5h, .5h, 2h,3h, 1h, 3h, 3h, 4h, 2h, 3h, 7h, 3h, 1h, 4h, 1h, 1h, 1h, 4h, 2h, 2h, 2h, 2h, 1h, 2h, 3h, 2h, 1h, 3h, 2h, 2h, 1h, 2h, 3h, 2h, 1h, 1h, 1.5, 2h, 2h, 3h, 2h, 1h, 3h, 2h, 1h, 2h, 1h, 5h, 2h, 1h, 2h, 4h, 2h, 3h, 3h, 3h )
Flaperons: ( DONE! ) 23.5 hours spent ( 3h, 1h, 1h, 1h, 1.5h, 3h, 6h, 3h, 4h, 1h )
Paint Design: 2 hours spent ( 1h, 1h )
Elevator DONE!: ~31.5 hours spent ( 3h, 1.5h, 3h, .5h, 3.5h, 2h, 4h, 1.5h, 2h, 4.5h, 1h, 6h )
Horizontal Stabilizer DONE!: ~28 hours spent, 3 pieces replaced ( 3h, 2h, 2h, 2h, .5h, 1.5h, 3.5h, 1.5h, 5, 4.5, 2h, .5h )
Rudder DONE!, minus horn : ~16 hours spent, ( ~8h, ~8h )
-----------------------
Total Done: ~465h
It turns out that the best way to approach the placement is to drill the aft most hole, then have a help hold the piece AND provide a buttress on the outside while you drill from the inside.
Also one of our EAA chapter members held a project visit today for their very nice looking 5151. Metal really dominates building so seeing how a wood project goes together was refreshing.
PROGRESS:
Fuselage ~203h ( 3h, 3h, 2h, 3h, 7h, 2h, 5h, 2h, 3h, 2h, 2h, 3h, 6h, 2h, 2h, 1.5h, 2.5h, 1h, 2h, 3h, 2h, 3h, 4h, 1h, 2h, 1h, 3h, 4h, 3h, 3h, 4h, 3h, 4h, 4h, 6h, 3h, 3h, 4h, 2h, 2h, 2h, 4h, 2h, 2h, 10h, 4h, 4h, 6h, 3h, 4h , 6h, 3h, 2h, 2h, 5h, 2h, 3h, 3h, 2h , 2h, 3h, 4h, 1h, 1h )
Wings: ~157.5h ( 1h, 1h, 0.5h, 2.5h, 4h, 1h, 1.5h, 1h, 1.5, 4.5, 1h, 1h, 2h, 4h, 1h, 3h, 1h, 2h, .5h, 1.5h, 2h, 2h, 2h, .5h, 1h, .5h, .5h, 2h,3h, 1h, 3h, 3h, 4h, 2h, 3h, 7h, 3h, 1h, 4h, 1h, 1h, 1h, 4h, 2h, 2h, 2h, 2h, 1h, 2h, 3h, 2h, 1h, 3h, 2h, 2h, 1h, 2h, 3h, 2h, 1h, 1h, 1.5, 2h, 2h, 3h, 2h, 1h, 3h, 2h, 1h, 2h, 1h, 5h, 2h, 1h, 2h, 4h, 2h, 3h, 3h, 3h )
Flaperons: ( DONE! ) 23.5 hours spent ( 3h, 1h, 1h, 1h, 1.5h, 3h, 6h, 3h, 4h, 1h )
Paint Design: 2 hours spent ( 1h, 1h )
Elevator DONE!: ~31.5 hours spent ( 3h, 1.5h, 3h, .5h, 3.5h, 2h, 4h, 1.5h, 2h, 4.5h, 1h, 6h )
Horizontal Stabilizer DONE!: ~28 hours spent, 3 pieces replaced ( 3h, 2h, 2h, 2h, .5h, 1.5h, 3.5h, 1.5h, 5, 4.5, 2h, .5h )
Rudder DONE!, minus horn : ~16 hours spent, ( ~8h, ~8h )
-----------------------
Total Done: ~465h
Saturday, March 08, 2008
Saturday was the first building session attempted since the birth.
I reconfirmed the positioning of 7F14-6 on the pilot and passenger side and then laid out the drill holes on the extrusion that extends from the fuselage sides.
Instead of drilling from the outside as was suggested by the HBH video, I ended up drilling from the inside to ensure edge distances.
At first I took a contortionist's approach by laying on the seats with my elbow resting on the floor pan, but I realized that I could simply sit on the edge of the workbench and lean in.
PROGRESS:
Fuselage ~203h ( 3h, 3h, 2h, 3h, 7h, 2h, 5h, 2h, 3h, 2h, 2h, 3h, 6h, 2h, 2h, 1.5h, 2.5h, 1h, 2h, 3h, 2h, 3h, 4h, 1h, 2h, 1h, 3h, 4h, 3h, 3h, 4h, 3h, 4h, 4h, 6h, 3h, 3h, 4h, 2h, 2h, 2h, 4h, 2h, 2h, 10h, 4h, 4h, 6h, 3h, 4h , 6h, 3h, 2h, 2h, 5h, 2h, 3h, 3h, 2h , 2h, 3h, 4h, 1h, 1h )
Wings: ~157.5h ( 1h, 1h, 0.5h, 2.5h, 4h, 1h, 1.5h, 1h, 1.5, 4.5, 1h, 1h, 2h, 4h, 1h, 3h, 1h, 2h, .5h, 1.5h, 2h, 2h, 2h, .5h, 1h, .5h, .5h, 2h,3h, 1h, 3h, 3h, 4h, 2h, 3h, 7h, 3h, 1h, 4h, 1h, 1h, 1h, 4h, 2h, 2h, 2h, 2h, 1h, 2h, 3h, 2h, 1h, 3h, 2h, 2h, 1h, 2h, 3h, 2h, 1h, 1h, 1.5, 2h, 2h, 3h, 2h, 1h, 3h, 2h, 1h, 2h, 1h, 5h, 2h, 1h, 2h, 4h, 2h, 3h, 3h, 3h )
Flaperons: ( DONE! ) 23.5 hours spent ( 3h, 1h, 1h, 1h, 1.5h, 3h, 6h, 3h, 4h, 1h )
Paint Design: 2 hours spent ( 1h, 1h )
Elevator DONE!: ~31.5 hours spent ( 3h, 1.5h, 3h, .5h, 3.5h, 2h, 4h, 1.5h, 2h, 4.5h, 1h, 6h )
Horizontal Stabilizer DONE!: ~28 hours spent, 3 pieces replaced ( 3h, 2h, 2h, 2h, .5h, 1.5h, 3.5h, 1.5h, 5, 4.5, 2h, .5h )
Rudder DONE!, minus horn : ~16 hours spent, ( ~8h, ~8h )
-----------------------
Total Done: ~465h
I reconfirmed the positioning of 7F14-6 on the pilot and passenger side and then laid out the drill holes on the extrusion that extends from the fuselage sides.
Instead of drilling from the outside as was suggested by the HBH video, I ended up drilling from the inside to ensure edge distances.
At first I took a contortionist's approach by laying on the seats with my elbow resting on the floor pan, but I realized that I could simply sit on the edge of the workbench and lean in.
PROGRESS:
Fuselage ~203h ( 3h, 3h, 2h, 3h, 7h, 2h, 5h, 2h, 3h, 2h, 2h, 3h, 6h, 2h, 2h, 1.5h, 2.5h, 1h, 2h, 3h, 2h, 3h, 4h, 1h, 2h, 1h, 3h, 4h, 3h, 3h, 4h, 3h, 4h, 4h, 6h, 3h, 3h, 4h, 2h, 2h, 2h, 4h, 2h, 2h, 10h, 4h, 4h, 6h, 3h, 4h , 6h, 3h, 2h, 2h, 5h, 2h, 3h, 3h, 2h , 2h, 3h, 4h, 1h, 1h )
Wings: ~157.5h ( 1h, 1h, 0.5h, 2.5h, 4h, 1h, 1.5h, 1h, 1.5, 4.5, 1h, 1h, 2h, 4h, 1h, 3h, 1h, 2h, .5h, 1.5h, 2h, 2h, 2h, .5h, 1h, .5h, .5h, 2h,3h, 1h, 3h, 3h, 4h, 2h, 3h, 7h, 3h, 1h, 4h, 1h, 1h, 1h, 4h, 2h, 2h, 2h, 2h, 1h, 2h, 3h, 2h, 1h, 3h, 2h, 2h, 1h, 2h, 3h, 2h, 1h, 1h, 1.5, 2h, 2h, 3h, 2h, 1h, 3h, 2h, 1h, 2h, 1h, 5h, 2h, 1h, 2h, 4h, 2h, 3h, 3h, 3h )
Flaperons: ( DONE! ) 23.5 hours spent ( 3h, 1h, 1h, 1h, 1.5h, 3h, 6h, 3h, 4h, 1h )
Paint Design: 2 hours spent ( 1h, 1h )
Elevator DONE!: ~31.5 hours spent ( 3h, 1.5h, 3h, .5h, 3.5h, 2h, 4h, 1.5h, 2h, 4.5h, 1h, 6h )
Horizontal Stabilizer DONE!: ~28 hours spent, 3 pieces replaced ( 3h, 2h, 2h, 2h, .5h, 1.5h, 3.5h, 1.5h, 5, 4.5, 2h, .5h )
Rudder DONE!, minus horn : ~16 hours spent, ( ~8h, ~8h )
-----------------------
Total Done: ~465h
Friday, March 07, 2008
Tuesday, March 04, 2008
So it will be some time before the plane gets worked on again. My wife just finished a nine month long project, and we just started a project that will take a minimum of 18 years...

http://www.genevievemarzulli.org/

http://www.genevievemarzulli.org/
Tuesday, February 19, 2008
Most of Monday night was spent doing the inventory for the remaining FWF shipment. There were a few small parts back ordered, and I accidentally received the 601 equivalent part... but most of it was there. The cowling is night and smooth, really slick looking.The actual hour of work logged was getting the aluminum plate measure and clamped into place before hitting a realization about needing to drill the side skins partially into the firewall for a smooth fit.
PROGRESS:
Fuselage ~202h ( 3h, 3h, 2h, 3h, 7h, 2h, 5h, 2h, 3h, 2h, 2h, 3h, 6h, 2h, 2h, 1.5h, 2.5h, 1h, 2h, 3h, 2h, 3h, 4h, 1h, 2h, 1h, 3h, 4h, 3h, 3h, 4h, 3h, 4h, 4h, 6h, 3h, 3h, 4h, 2h, 2h, 2h, 4h, 2h, 2h, 10h, 4h, 4h, 6h, 3h, 4h , 6h, 3h, 2h, 2h, 5h, 2h, 3h, 3h, 2h , 2h, 3h, 4h, 1h )
Wings: ~157.5h ( 1h, 1h, 0.5h, 2.5h, 4h, 1h, 1.5h, 1h, 1.5, 4.5, 1h, 1h, 2h, 4h, 1h, 3h, 1h, 2h, .5h, 1.5h, 2h, 2h, 2h, .5h, 1h, .5h, .5h, 2h,3h, 1h, 3h, 3h, 4h, 2h, 3h, 7h, 3h, 1h, 4h, 1h, 1h, 1h, 4h, 2h, 2h, 2h, 2h, 1h, 2h, 3h, 2h, 1h, 3h, 2h, 2h, 1h, 2h, 3h, 2h, 1h, 1h, 1.5, 2h, 2h, 3h, 2h, 1h, 3h, 2h, 1h, 2h, 1h, 5h, 2h, 1h, 2h, 4h, 2h, 3h, 3h, 3h )
Flaperons: ( DONE! ) 23.5 hours spent ( 3h, 1h, 1h, 1h, 1.5h, 3h, 6h, 3h, 4h, 1h )
Paint Design: 2 hours spent ( 1h, 1h )
Elevator DONE!: ~31.5 hours spent ( 3h, 1.5h, 3h, .5h, 3.5h, 2h, 4h, 1.5h, 2h, 4.5h, 1h, 6h )
Horizontal Stabilizer DONE!: ~28 hours spent, 3 pieces replaced ( 3h, 2h, 2h, 2h, .5h, 1.5h, 3.5h, 1.5h, 5, 4.5, 2h, .5h )
Rudder DONE!, minus horn : ~16 hours spent, ( ~8h, ~8h )
-----------------------
Total Done: ~464h
Sunday, February 17, 2008
Saturday night we trimmed and drilled into place the ("Z") angle that runs along the floor and the ("L") angle that supports the forward skins right above that.
The ("Z") was fairly easy, except I had to remove the firewall to slip the ("Z") in. Replacing the side skin and the firewall took effort as nothing wanted to line up initially.
The side skin support angles were another story.
Wanting a tight fit, the ("L") was crimped before it was drilled into place so the end point that connected to the firewall would be just right.
The problem with this is the actually accessing of the point. I had to crawl into the cabin at a crazy angle such that my shoulder was resting on the floor panels, but my hip was on the seat.
PROGRESS:
Fuselage ~201h ( 3h, 3h, 2h, 3h, 7h, 2h, 5h, 2h, 3h, 2h, 2h, 3h, 6h, 2h, 2h, 1.5h, 2.5h, 1h, 2h, 3h, 2h, 3h, 4h, 1h, 2h, 1h, 3h, 4h, 3h, 3h, 4h, 3h, 4h, 4h, 6h, 3h, 3h, 4h, 2h, 2h, 2h, 4h, 2h, 2h, 10h, 4h, 4h, 6h, 3h, 4h , 6h, 3h, 2h, 2h, 5h, 2h, 3h, 3h, 2h , 2h, 3h, 4h )
Wings: ~157.5h ( 1h, 1h, 0.5h, 2.5h, 4h, 1h, 1.5h, 1h, 1.5, 4.5, 1h, 1h, 2h, 4h, 1h, 3h, 1h, 2h, .5h, 1.5h, 2h, 2h, 2h, .5h, 1h, .5h, .5h, 2h,3h, 1h, 3h, 3h, 4h, 2h, 3h, 7h, 3h, 1h, 4h, 1h, 1h, 1h, 4h, 2h, 2h, 2h, 2h, 1h, 2h, 3h, 2h, 1h, 3h, 2h, 2h, 1h, 2h, 3h, 2h, 1h, 1h, 1.5, 2h, 2h, 3h, 2h, 1h, 3h, 2h, 1h, 2h, 1h, 5h, 2h, 1h, 2h, 4h, 2h, 3h, 3h, 3h )
Flaperons: ( DONE! ) 23.5 hours spent ( 3h, 1h, 1h, 1h, 1.5h, 3h, 6h, 3h, 4h, 1h )
Paint Design: 2 hours spent ( 1h, 1h )
Elevator DONE!: ~31.5 hours spent ( 3h, 1.5h, 3h, .5h, 3.5h, 2h, 4h, 1.5h, 2h, 4.5h, 1h, 6h )
Horizontal Stabilizer DONE!: ~28 hours spent, 3 pieces replaced ( 3h, 2h, 2h, 2h, .5h, 1.5h, 3.5h, 1.5h, 5, 4.5, 2h, .5h )
Rudder DONE!, minus horn : ~16 hours spent, ( ~8h, ~8h )
-----------------------
Total Done: ~463h
The ("Z") was fairly easy, except I had to remove the firewall to slip the ("Z") in. Replacing the side skin and the firewall took effort as nothing wanted to line up initially.
The side skin support angles were another story.
Wanting a tight fit, the ("L") was crimped before it was drilled into place so the end point that connected to the firewall would be just right.
The problem with this is the actually accessing of the point. I had to crawl into the cabin at a crazy angle such that my shoulder was resting on the floor panels, but my hip was on the seat.
PROGRESS:
Fuselage ~201h ( 3h, 3h, 2h, 3h, 7h, 2h, 5h, 2h, 3h, 2h, 2h, 3h, 6h, 2h, 2h, 1.5h, 2.5h, 1h, 2h, 3h, 2h, 3h, 4h, 1h, 2h, 1h, 3h, 4h, 3h, 3h, 4h, 3h, 4h, 4h, 6h, 3h, 3h, 4h, 2h, 2h, 2h, 4h, 2h, 2h, 10h, 4h, 4h, 6h, 3h, 4h , 6h, 3h, 2h, 2h, 5h, 2h, 3h, 3h, 2h , 2h, 3h, 4h )
Wings: ~157.5h ( 1h, 1h, 0.5h, 2.5h, 4h, 1h, 1.5h, 1h, 1.5, 4.5, 1h, 1h, 2h, 4h, 1h, 3h, 1h, 2h, .5h, 1.5h, 2h, 2h, 2h, .5h, 1h, .5h, .5h, 2h,3h, 1h, 3h, 3h, 4h, 2h, 3h, 7h, 3h, 1h, 4h, 1h, 1h, 1h, 4h, 2h, 2h, 2h, 2h, 1h, 2h, 3h, 2h, 1h, 3h, 2h, 2h, 1h, 2h, 3h, 2h, 1h, 1h, 1.5, 2h, 2h, 3h, 2h, 1h, 3h, 2h, 1h, 2h, 1h, 5h, 2h, 1h, 2h, 4h, 2h, 3h, 3h, 3h )
Flaperons: ( DONE! ) 23.5 hours spent ( 3h, 1h, 1h, 1h, 1.5h, 3h, 6h, 3h, 4h, 1h )
Paint Design: 2 hours spent ( 1h, 1h )
Elevator DONE!: ~31.5 hours spent ( 3h, 1.5h, 3h, .5h, 3.5h, 2h, 4h, 1.5h, 2h, 4.5h, 1h, 6h )
Horizontal Stabilizer DONE!: ~28 hours spent, 3 pieces replaced ( 3h, 2h, 2h, 2h, .5h, 1.5h, 3.5h, 1.5h, 5, 4.5, 2h, .5h )
Rudder DONE!, minus horn : ~16 hours spent, ( ~8h, ~8h )
-----------------------
Total Done: ~463h
Monday, February 11, 2008
Friday, Saturday, Sunday - Work picked back up. The engine mount finally got drilled into the firewall and into the V-Brace. After that work started on the forward side skins. These were easy, but I found that the bottom edge of the skins will interfere the forward most rivets of the extrusion.The trick to achieving a good fit is to have someone pushing on the skin while a second person drills.
Before I can drill the supporting Z-Angle into the side skins I will have to do some amount of trimming so the engine mount can hold the firewall into position.
PROGRESS:
Fuselage ~197h ( 3h, 3h, 2h, 3h, 7h, 2h, 5h, 2h, 3h, 2h, 2h, 3h, 6h, 2h, 2h, 1.5h, 2.5h, 1h, 2h, 3h, 2h, 3h, 4h, 1h, 2h, 1h, 3h, 4h, 3h, 3h, 4h, 3h, 4h, 4h, 6h, 3h, 3h, 4h, 2h, 2h, 2h, 4h, 2h, 2h, 10h, 4h, 4h, 6h, 3h, 4h , 6h, 3h, 2h, 2h, 5h, 2h, 3h, 3h, 2h , 2h, 3h )
Wings: ~157.5h ( 1h, 1h, 0.5h, 2.5h, 4h, 1h, 1.5h, 1h, 1.5, 4.5, 1h, 1h, 2h, 4h, 1h, 3h, 1h, 2h, .5h, 1.5h, 2h, 2h, 2h, .5h, 1h, .5h, .5h, 2h,3h, 1h, 3h, 3h, 4h, 2h, 3h, 7h, 3h, 1h, 4h, 1h, 1h, 1h, 4h, 2h, 2h, 2h, 2h, 1h, 2h, 3h, 2h, 1h, 3h, 2h, 2h, 1h, 2h, 3h, 2h, 1h, 1h, 1.5, 2h, 2h, 3h, 2h, 1h, 3h, 2h, 1h, 2h, 1h, 5h, 2h, 1h, 2h, 4h, 2h, 3h, 3h, 3h )
Flaperons: ( DONE! ) 23.5 hours spent ( 3h, 1h, 1h, 1h, 1.5h, 3h, 6h, 3h, 4h, 1h )
Paint Design: 2 hours spent ( 1h, 1h )
Elevator DONE!: ~31.5 hours spent ( 3h, 1.5h, 3h, .5h, 3.5h, 2h, 4h, 1.5h, 2h, 4.5h, 1h, 6h )
Horizontal Stabilizer DONE!: ~28 hours spent, 3 pieces replaced ( 3h, 2h, 2h, 2h, .5h, 1.5h, 3.5h, 1.5h, 5, 4.5, 2h, .5h )
Rudder DONE!, minus horn : ~16 hours spent, ( ~8h, ~8h )
-----------------------
Total Done: ~459h
Tuesday, January 29, 2008
We had a streak of great weather ( for the winter ). It would have been criminal not to take advantage of it.
Lake Cushman And Back from John Marzulli on Vimeo
Lake Cushman And Back from John Marzulli on Vimeo
Wednesday, January 23, 2008
The fuselage is corrosion protected, deburred and riveted together ( excluding the tubular frame ).One thing to consider is the accessibility of the small piece ("L") angle that ties the side skins together with the seat pans on the outboard side. If I could call a mulligan then I would rivet the ("L") to the pan first, then cleco it to the side skin and rivet it with the rest of the seat.
Of course the momentous occasion was celebrated with the first sitting in the plane. The seats are as comfortable as can be hoped for. Skyshops really did a great job matching my colors and providing an overall well made product.
Next I will drill the engine mount to the firewall ( finally ) and make the instrument panel.
PROGRESS:
Fuselage ~190h ( 3h, 3h, 2h, 3h, 7h, 2h, 5h, 2h, 3h, 2h, 2h, 3h, 6h, 2h, 2h, 1.5h, 2.5h, 1h, 2h, 3h, 2h, 3h, 4h, 1h, 2h, 1h, 3h, 4h, 3h, 3h, 4h, 3h, 4h, 4h, 6h, 3h, 3h, 4h, 2h, 2h, 2h, 4h, 2h, 2h, 10h, 4h, 4h, 6h, 3h, 4h , 6h, 3h, 2h, 2h, 5h, 2h, 3h, 3h )
Wings: ~157.5h ( 1h, 1h, 0.5h, 2.5h, 4h, 1h, 1.5h, 1h, 1.5, 4.5, 1h, 1h, 2h, 4h, 1h, 3h, 1h, 2h, .5h, 1.5h, 2h, 2h, 2h, .5h, 1h, .5h, .5h, 2h,3h, 1h, 3h, 3h, 4h, 2h, 3h, 7h, 3h, 1h, 4h, 1h, 1h, 1h, 4h, 2h, 2h, 2h, 2h, 1h, 2h, 3h, 2h, 1h, 3h, 2h, 2h, 1h, 2h, 3h, 2h, 1h, 1h, 1.5, 2h, 2h, 3h, 2h, 1h, 3h, 2h, 1h, 2h, 1h, 5h, 2h, 1h, 2h, 4h, 2h, 3h, 3h, 3h )
Flaperons: ( DONE! ) 23.5 hours spent ( 3h, 1h, 1h, 1h, 1.5h, 3h, 6h, 3h, 4h, 1h )
Paint Design: 2 hours spent ( 1h, 1h )
Elevator DONE!: ~31.5 hours spent ( 3h, 1.5h, 3h, .5h, 3.5h, 2h, 4h, 1.5h, 2h, 4.5h, 1h, 6h )
Horizontal Stabilizer DONE!: ~28 hours spent, 3 pieces replaced ( 3h, 2h, 2h, 2h, .5h, 1.5h, 3.5h, 1.5h, 5, 4.5, 2h, .5h )
Rudder DONE!, minus horn : ~16 hours spent, ( ~8h, ~8h )
-----------------------
Total Done: ~452h
Sunday, January 20, 2008
Spent three hours drilling out the remaining holes and corrosion protecting. The gear strut fittings were somewhat brutal to drill as I broke a bit on the left and right side each.
PROGRESS:
Fuselage ~184h ( 3h, 3h, 2h, 3h, 7h, 2h, 5h, 2h, 3h, 2h, 2h, 3h, 6h, 2h, 2h, 1.5h, 2.5h, 1h, 2h, 3h, 2h, 3h, 4h, 1h, 2h, 1h, 3h, 4h, 3h, 3h, 4h, 3h, 4h, 4h, 6h, 3h, 3h, 4h, 2h, 2h, 2h, 4h, 2h, 2h, 10h, 4h, 4h, 6h, 3h, 4h , 6h, 3h, 2h, 2h, 5h, 2h, 3h, 3h )
Wings: ~157.5h ( 1h, 1h, 0.5h, 2.5h, 4h, 1h, 1.5h, 1h, 1.5, 4.5, 1h, 1h, 2h, 4h, 1h, 3h, 1h, 2h, .5h, 1.5h, 2h, 2h, 2h, .5h, 1h, .5h, .5h, 2h,3h, 1h, 3h, 3h, 4h, 2h, 3h, 7h, 3h, 1h, 4h, 1h, 1h, 1h, 4h, 2h, 2h, 2h, 2h, 1h, 2h, 3h, 2h, 1h, 3h, 2h, 2h, 1h, 2h, 3h, 2h, 1h, 1h, 1.5, 2h, 2h, 3h, 2h, 1h, 3h, 2h, 1h, 2h, 1h, 5h, 2h, 1h, 2h, 4h, 2h, 3h )
Flaperons: ( DONE! ) 23.5 hours spent ( 3h, 1h, 1h, 1h, 1.5h, 3h, 6h, 3h, 4h, 1h )
Paint Design: 2 hours spent ( 1h, 1h )
Elevator DONE!: ~31.5 hours spent ( 3h, 1.5h, 3h, .5h, 3.5h, 2h, 4h, 1.5h, 2h, 4.5h, 1h, 6h )
Horizontal Stabilizer DONE!: ~28 hours spent, 3 pieces replaced ( 3h, 2h, 2h, 2h, .5h, 1.5h, 3.5h, 1.5h, 5, 4.5, 2h, .5h )
Rudder DONE!, minus horn : ~16 hours spent, ( ~8h, ~8h )
-----------------------
Total Done: ~446h
PROGRESS:
Fuselage ~184h ( 3h, 3h, 2h, 3h, 7h, 2h, 5h, 2h, 3h, 2h, 2h, 3h, 6h, 2h, 2h, 1.5h, 2.5h, 1h, 2h, 3h, 2h, 3h, 4h, 1h, 2h, 1h, 3h, 4h, 3h, 3h, 4h, 3h, 4h, 4h, 6h, 3h, 3h, 4h, 2h, 2h, 2h, 4h, 2h, 2h, 10h, 4h, 4h, 6h, 3h, 4h , 6h, 3h, 2h, 2h, 5h, 2h, 3h, 3h )
Wings: ~157.5h ( 1h, 1h, 0.5h, 2.5h, 4h, 1h, 1.5h, 1h, 1.5, 4.5, 1h, 1h, 2h, 4h, 1h, 3h, 1h, 2h, .5h, 1.5h, 2h, 2h, 2h, .5h, 1h, .5h, .5h, 2h,3h, 1h, 3h, 3h, 4h, 2h, 3h, 7h, 3h, 1h, 4h, 1h, 1h, 1h, 4h, 2h, 2h, 2h, 2h, 1h, 2h, 3h, 2h, 1h, 3h, 2h, 2h, 1h, 2h, 3h, 2h, 1h, 1h, 1.5, 2h, 2h, 3h, 2h, 1h, 3h, 2h, 1h, 2h, 1h, 5h, 2h, 1h, 2h, 4h, 2h, 3h )
Flaperons: ( DONE! ) 23.5 hours spent ( 3h, 1h, 1h, 1h, 1.5h, 3h, 6h, 3h, 4h, 1h )
Paint Design: 2 hours spent ( 1h, 1h )
Elevator DONE!: ~31.5 hours spent ( 3h, 1.5h, 3h, .5h, 3.5h, 2h, 4h, 1.5h, 2h, 4.5h, 1h, 6h )
Horizontal Stabilizer DONE!: ~28 hours spent, 3 pieces replaced ( 3h, 2h, 2h, 2h, .5h, 1.5h, 3.5h, 1.5h, 5, 4.5, 2h, .5h )
Rudder DONE!, minus horn : ~16 hours spent, ( ~8h, ~8h )
-----------------------
Total Done: ~446h
Saturday, January 19, 2008
I finished drilling out the side skin attachments to the rear fuselage. I also fabbed the side skin doublers ( 7F16-6? ). Due to having already pilot drilled the seat gussets into place the first holes in the doubler were back drilled from the bottom. This required an extra person, a flashlight, an inspection mirror and an angle drill.
The only holes remaining are in the gear strut attachment.
Everything was deburred and is now ready for priming.
PROGRESS:
Fuselage ~181h ( 3h, 3h, 2h, 3h, 7h, 2h, 5h, 2h, 3h, 2h, 2h, 3h, 6h, 2h, 2h, 1.5h, 2.5h, 1h, 2h, 3h, 2h, 3h, 4h, 1h, 2h, 1h, 3h, 4h, 3h, 3h, 4h, 3h, 4h, 4h, 6h, 3h, 3h, 4h, 2h, 2h, 2h, 4h, 2h, 2h, 10h, 4h, 4h, 6h, 3h, 4h , 6h, 3h, 2h, 2h, 5h, 2h, 3h, 3h )
Wings: ~157.5h ( 1h, 1h, 0.5h, 2.5h, 4h, 1h, 1.5h, 1h, 1.5, 4.5, 1h, 1h, 2h, 4h, 1h, 3h, 1h, 2h, .5h, 1.5h, 2h, 2h, 2h, .5h, 1h, .5h, .5h, 2h,3h, 1h, 3h, 3h, 4h, 2h, 3h, 7h, 3h, 1h, 4h, 1h, 1h, 1h, 4h, 2h, 2h, 2h, 2h, 1h, 2h, 3h, 2h, 1h, 3h, 2h, 2h, 1h, 2h, 3h, 2h, 1h, 1h, 1.5, 2h, 2h, 3h, 2h, 1h, 3h, 2h, 1h, 2h, 1h, 5h, 2h, 1h, 2h, 4h, 2h )
Flaperons: ( DONE! ) 23.5 hours spent ( 3h, 1h, 1h, 1h, 1.5h, 3h, 6h, 3h, 4h, 1h )
Paint Design: 2 hours spent ( 1h, 1h )
Elevator DONE!: ~31.5 hours spent ( 3h, 1.5h, 3h, .5h, 3.5h, 2h, 4h, 1.5h, 2h, 4.5h, 1h, 6h )
Horizontal Stabilizer DONE!: ~28 hours spent, 3 pieces replaced ( 3h, 2h, 2h, 2h, .5h, 1.5h, 3.5h, 1.5h, 5, 4.5, 2h, .5h )
Rudder DONE!, minus horn : ~16 hours spent, ( ~8h, ~8h )
-----------------------
Total Done: ~443h
The only holes remaining are in the gear strut attachment.
Everything was deburred and is now ready for priming.
PROGRESS:
Fuselage ~181h ( 3h, 3h, 2h, 3h, 7h, 2h, 5h, 2h, 3h, 2h, 2h, 3h, 6h, 2h, 2h, 1.5h, 2.5h, 1h, 2h, 3h, 2h, 3h, 4h, 1h, 2h, 1h, 3h, 4h, 3h, 3h, 4h, 3h, 4h, 4h, 6h, 3h, 3h, 4h, 2h, 2h, 2h, 4h, 2h, 2h, 10h, 4h, 4h, 6h, 3h, 4h , 6h, 3h, 2h, 2h, 5h, 2h, 3h, 3h )
Wings: ~157.5h ( 1h, 1h, 0.5h, 2.5h, 4h, 1h, 1.5h, 1h, 1.5, 4.5, 1h, 1h, 2h, 4h, 1h, 3h, 1h, 2h, .5h, 1.5h, 2h, 2h, 2h, .5h, 1h, .5h, .5h, 2h,3h, 1h, 3h, 3h, 4h, 2h, 3h, 7h, 3h, 1h, 4h, 1h, 1h, 1h, 4h, 2h, 2h, 2h, 2h, 1h, 2h, 3h, 2h, 1h, 3h, 2h, 2h, 1h, 2h, 3h, 2h, 1h, 1h, 1.5, 2h, 2h, 3h, 2h, 1h, 3h, 2h, 1h, 2h, 1h, 5h, 2h, 1h, 2h, 4h, 2h )
Flaperons: ( DONE! ) 23.5 hours spent ( 3h, 1h, 1h, 1h, 1.5h, 3h, 6h, 3h, 4h, 1h )
Paint Design: 2 hours spent ( 1h, 1h )
Elevator DONE!: ~31.5 hours spent ( 3h, 1.5h, 3h, .5h, 3.5h, 2h, 4h, 1.5h, 2h, 4.5h, 1h, 6h )
Horizontal Stabilizer DONE!: ~28 hours spent, 3 pieces replaced ( 3h, 2h, 2h, 2h, .5h, 1.5h, 3.5h, 1.5h, 5, 4.5, 2h, .5h )
Rudder DONE!, minus horn : ~16 hours spent, ( ~8h, ~8h )
-----------------------
Total Done: ~443h
Friday, January 18, 2008
Some nights just do not got the way you want. The whole session ended just about where I thought I started.
First the rear and front fuselage would not cooperate and mate together. Then I realized that the middle baggage area truss was not riveted to the baggage area flooe, so I drilled out the rivets... to the doubler extension that I had to fab... only to find out I drilled out the wrong row of rivets and that the truss was upside down... and had to be drilled out.
Everything fits together now AND I riveted a portion of the rear fuselage that had been kept clecoed together just in case.
Instead of a photo, here is a quick tour of the Seattle skyline:
Seattle Skyline Tour from John Marzulli on Vimeo
PROGRESS:
Fuselage ~178h ( 3h, 3h, 2h, 3h, 7h, 2h, 5h, 2h, 3h, 2h, 2h, 3h, 6h, 2h, 2h, 1.5h, 2.5h, 1h, 2h, 3h, 2h, 3h, 4h, 1h, 2h, 1h, 3h, 4h, 3h, 3h, 4h, 3h, 4h, 4h, 6h, 3h, 3h, 4h, 2h, 2h, 2h, 4h, 2h, 2h, 10h, 4h, 4h, 6h, 3h, 4h , 6h, 3h, 2h, 2h, 5h, 2h, 3h )
Wings: ~157.5h ( 1h, 1h, 0.5h, 2.5h, 4h, 1h, 1.5h, 1h, 1.5, 4.5, 1h, 1h, 2h, 4h, 1h, 3h, 1h, 2h, .5h, 1.5h, 2h, 2h, 2h, .5h, 1h, .5h, .5h, 2h,3h, 1h, 3h, 3h, 4h, 2h, 3h, 7h, 3h, 1h, 4h, 1h, 1h, 1h, 4h, 2h, 2h, 2h, 2h, 1h, 2h, 3h, 2h, 1h, 3h, 2h, 2h, 1h, 2h, 3h, 2h, 1h, 1h, 1.5, 2h, 2h, 3h, 2h, 1h, 3h, 2h, 1h, 2h, 1h, 5h, 2h, 1h, 2h, 4h, 2h )
Flaperons: ( DONE! ) 23.5 hours spent ( 3h, 1h, 1h, 1h, 1.5h, 3h, 6h, 3h, 4h, 1h )
Paint Design: 2 hours spent ( 1h, 1h )
Elevator DONE!: ~31.5 hours spent ( 3h, 1.5h, 3h, .5h, 3.5h, 2h, 4h, 1.5h, 2h, 4.5h, 1h, 6h )
Horizontal Stabilizer DONE!: ~28 hours spent, 3 pieces replaced ( 3h, 2h, 2h, 2h, .5h, 1.5h, 3.5h, 1.5h, 5, 4.5, 2h, .5h )
Rudder DONE!, minus horn : ~16 hours spent, ( ~8h, ~8h )
-----------------------
Total Done: ~440h
First the rear and front fuselage would not cooperate and mate together. Then I realized that the middle baggage area truss was not riveted to the baggage area flooe, so I drilled out the rivets... to the doubler extension that I had to fab... only to find out I drilled out the wrong row of rivets and that the truss was upside down... and had to be drilled out.
Everything fits together now AND I riveted a portion of the rear fuselage that had been kept clecoed together just in case.
Instead of a photo, here is a quick tour of the Seattle skyline:
Seattle Skyline Tour from John Marzulli on Vimeo
PROGRESS:
Fuselage ~178h ( 3h, 3h, 2h, 3h, 7h, 2h, 5h, 2h, 3h, 2h, 2h, 3h, 6h, 2h, 2h, 1.5h, 2.5h, 1h, 2h, 3h, 2h, 3h, 4h, 1h, 2h, 1h, 3h, 4h, 3h, 3h, 4h, 3h, 4h, 4h, 6h, 3h, 3h, 4h, 2h, 2h, 2h, 4h, 2h, 2h, 10h, 4h, 4h, 6h, 3h, 4h , 6h, 3h, 2h, 2h, 5h, 2h, 3h )
Wings: ~157.5h ( 1h, 1h, 0.5h, 2.5h, 4h, 1h, 1.5h, 1h, 1.5, 4.5, 1h, 1h, 2h, 4h, 1h, 3h, 1h, 2h, .5h, 1.5h, 2h, 2h, 2h, .5h, 1h, .5h, .5h, 2h,3h, 1h, 3h, 3h, 4h, 2h, 3h, 7h, 3h, 1h, 4h, 1h, 1h, 1h, 4h, 2h, 2h, 2h, 2h, 1h, 2h, 3h, 2h, 1h, 3h, 2h, 2h, 1h, 2h, 3h, 2h, 1h, 1h, 1.5, 2h, 2h, 3h, 2h, 1h, 3h, 2h, 1h, 2h, 1h, 5h, 2h, 1h, 2h, 4h, 2h )
Flaperons: ( DONE! ) 23.5 hours spent ( 3h, 1h, 1h, 1h, 1.5h, 3h, 6h, 3h, 4h, 1h )
Paint Design: 2 hours spent ( 1h, 1h )
Elevator DONE!: ~31.5 hours spent ( 3h, 1.5h, 3h, .5h, 3.5h, 2h, 4h, 1.5h, 2h, 4.5h, 1h, 6h )
Horizontal Stabilizer DONE!: ~28 hours spent, 3 pieces replaced ( 3h, 2h, 2h, 2h, .5h, 1.5h, 3.5h, 1.5h, 5, 4.5, 2h, .5h )
Rudder DONE!, minus horn : ~16 hours spent, ( ~8h, ~8h )
-----------------------
Total Done: ~440h
Monday, January 14, 2008
Weekend roundup ( Friday, Saturday, Sunday )First, my upholstery arrived late Friday. It looks great. I am making a big push to be able to finally sit in the plane... which leads me to the next part:
Drill out, debur, prime, rivet.
There are still a few holes that need to be drilled out that I am finding. Most everything is now covered in primer. The entire torque tube cover assembly is now riveted together. I also have the baggage compartment riveted together. To avoid some installation and reach issues the side skin gussets have been riveted.
I also fixed a mistake caused by misinterpreting the plans. For some reason I installed the interior gussets with the cutout for the rudder cables on the upper locations. These were drilled out and replacements were made without the cutout. The lower gussets were modified to include the rounded notch.
As getting in and out of the rear fuselage is a pain, it is highly suggested to install them the correct way before riveting any of the baggage area.
PROGRESS:
Fuselage ~175h ( 3h, 3h, 2h, 3h, 7h, 2h, 5h, 2h, 3h, 2h, 2h, 3h, 6h, 2h, 2h, 1.5h, 2.5h, 1h, 2h, 3h, 2h, 3h, 4h, 1h, 2h, 1h, 3h, 4h, 3h, 3h, 4h, 3h, 4h, 4h, 6h, 3h, 3h, 4h, 2h, 2h, 2h, 4h, 2h, 2h, 10h, 4h, 4h, 6h, 3h, 4h , 6h, 3h, 2h, 2h, 5h, 2h )
Wings: ~157.5h ( 1h, 1h, 0.5h, 2.5h, 4h, 1h, 1.5h, 1h, 1.5, 4.5, 1h, 1h, 2h, 4h, 1h, 3h, 1h, 2h, .5h, 1.5h, 2h, 2h, 2h, .5h, 1h, .5h, .5h, 2h,3h, 1h, 3h, 3h, 4h, 2h, 3h, 7h, 3h, 1h, 4h, 1h, 1h, 1h, 4h, 2h, 2h, 2h, 2h, 1h, 2h, 3h, 2h, 1h, 3h, 2h, 2h, 1h, 2h, 3h, 2h, 1h, 1h, 1.5, 2h, 2h, 3h, 2h, 1h, 3h, 2h, 1h, 2h, 1h, 5h, 2h, 1h, 2h, 4h, 2h )
Flaperons: ( DONE! ) 23.5 hours spent ( 3h, 1h, 1h, 1h, 1.5h, 3h, 6h, 3h, 4h, 1h )
Paint Design: 2 hours spent ( 1h, 1h )
Elevator DONE!: ~31.5 hours spent ( 3h, 1.5h, 3h, .5h, 3.5h, 2h, 4h, 1.5h, 2h, 4.5h, 1h, 6h )
Horizontal Stabilizer DONE!: ~28 hours spent, 3 pieces replaced ( 3h, 2h, 2h, 2h, .5h, 1.5h, 3.5h, 1.5h, 5, 4.5, 2h, .5h )
Rudder DONE!, minus horn : ~16 hours spent, ( ~8h, ~8h )
-----------------------
Total Done: ~437h
Saturday, January 12, 2008
Tuesday, January 08, 2008
Monday night I drilled out almost all of the remaining holes in the forward fuselage. When the holes in 7F3-3SP got enlarged to A5 it became very apparent that distance between the holes was not sufficient for my standards. I ordered a new tube and a sheet of .040 from OnlineMetals.com so I could fab up new pieces. I finished the night by deburring a good bit of the fuselage.
Tuesday night I un-installed the passenger side 7F3-3SP lined it up with a flat edge of my new 0.040 sheet and clamped and back drilled all the holes that did not go into the diagonal tube. I then expanded the gusset about 20mm inboard so as to gain an additional 15mm or so on the diagonal. I left the width of the gusset the same as before at the fore and aft, connected up my lines, cut it out and cleaned it up.
The new piece fit perfectly. I then trimmed the tube, inserted it into the fuselage receiver, clamped, lined up and drilled. The new holes are dead on with about 4D space between holes. I back drilled the remaining holes in the frame and the lower gusset.
PROGRESS:
Fuselage ~166h ( 3h, 3h, 2h, 3h, 7h, 2h, 5h, 2h, 3h, 2h, 2h, 3h, 6h, 2h, 2h, 1.5h, 2.5h, 1h, 2h, 3h, 2h, 3h, 4h, 1h, 2h, 1h, 3h, 4h, 3h, 3h, 4h, 3h, 4h, 4h, 6h, 3h, 3h, 4h, 2h, 2h, 2h, 4h, 2h, 2h, 10h, 4h, 4h, 6h, 3h, 4h , 6h, 3h, 2h)
Wings: ~157.5h ( 1h, 1h, 0.5h, 2.5h, 4h, 1h, 1.5h, 1h, 1.5, 4.5, 1h, 1h, 2h, 4h, 1h, 3h, 1h, 2h, .5h, 1.5h, 2h, 2h, 2h, .5h, 1h, .5h, .5h, 2h,3h, 1h, 3h, 3h, 4h, 2h, 3h, 7h, 3h, 1h, 4h, 1h, 1h, 1h, 4h, 2h, 2h, 2h, 2h, 1h, 2h, 3h, 2h, 1h, 3h, 2h, 2h, 1h, 2h, 3h, 2h, 1h, 1h, 1.5, 2h, 2h, 3h, 2h, 1h, 3h, 2h, 1h, 2h, 1h, 5h, 2h, 1h, 2h, 4h, 2h )
Flaperons: ( DONE! ) 23.5 hours spent ( 3h, 1h, 1h, 1h, 1.5h, 3h, 6h, 3h, 4h, 1h )
Paint Design: 2 hours spent ( 1h, 1h )
Elevator DONE!: ~31.5 hours spent ( 3h, 1.5h, 3h, .5h, 3.5h, 2h, 4h, 1.5h, 2h, 4.5h, 1h, 6h )
Horizontal Stabilizer DONE!: ~28 hours spent, 3 pieces replaced ( 3h, 2h, 2h, 2h, .5h, 1.5h, 3.5h, 1.5h, 5, 4.5, 2h, .5h )
Rudder DONE!, minus horn : ~16 hours spent, ( ~8h, ~8h )
-----------------------
Total Done: ~428h
Tuesday night I un-installed the passenger side 7F3-3SP lined it up with a flat edge of my new 0.040 sheet and clamped and back drilled all the holes that did not go into the diagonal tube. I then expanded the gusset about 20mm inboard so as to gain an additional 15mm or so on the diagonal. I left the width of the gusset the same as before at the fore and aft, connected up my lines, cut it out and cleaned it up.
The new piece fit perfectly. I then trimmed the tube, inserted it into the fuselage receiver, clamped, lined up and drilled. The new holes are dead on with about 4D space between holes. I back drilled the remaining holes in the frame and the lower gusset.
PROGRESS:
Fuselage ~166h ( 3h, 3h, 2h, 3h, 7h, 2h, 5h, 2h, 3h, 2h, 2h, 3h, 6h, 2h, 2h, 1.5h, 2.5h, 1h, 2h, 3h, 2h, 3h, 4h, 1h, 2h, 1h, 3h, 4h, 3h, 3h, 4h, 3h, 4h, 4h, 6h, 3h, 3h, 4h, 2h, 2h, 2h, 4h, 2h, 2h, 10h, 4h, 4h, 6h, 3h, 4h , 6h, 3h, 2h)
Wings: ~157.5h ( 1h, 1h, 0.5h, 2.5h, 4h, 1h, 1.5h, 1h, 1.5, 4.5, 1h, 1h, 2h, 4h, 1h, 3h, 1h, 2h, .5h, 1.5h, 2h, 2h, 2h, .5h, 1h, .5h, .5h, 2h,3h, 1h, 3h, 3h, 4h, 2h, 3h, 7h, 3h, 1h, 4h, 1h, 1h, 1h, 4h, 2h, 2h, 2h, 2h, 1h, 2h, 3h, 2h, 1h, 3h, 2h, 2h, 1h, 2h, 3h, 2h, 1h, 1h, 1.5, 2h, 2h, 3h, 2h, 1h, 3h, 2h, 1h, 2h, 1h, 5h, 2h, 1h, 2h, 4h, 2h )
Flaperons: ( DONE! ) 23.5 hours spent ( 3h, 1h, 1h, 1h, 1.5h, 3h, 6h, 3h, 4h, 1h )
Paint Design: 2 hours spent ( 1h, 1h )
Elevator DONE!: ~31.5 hours spent ( 3h, 1.5h, 3h, .5h, 3.5h, 2h, 4h, 1.5h, 2h, 4.5h, 1h, 6h )
Horizontal Stabilizer DONE!: ~28 hours spent, 3 pieces replaced ( 3h, 2h, 2h, 2h, .5h, 1.5h, 3.5h, 1.5h, 5, 4.5, 2h, .5h )
Rudder DONE!, minus horn : ~16 hours spent, ( ~8h, ~8h )
-----------------------
Total Done: ~428h
Monday, January 07, 2008
The pilot and passenger seat pans are now both drilled into place. In addition the seat corner gussets were both fabricated and drilled into place, the backing ("L") of the seats is in place and several tie together gussets were put into place to deal with over trimming of the side extrusion.In addition, most of the A3 holes were drilled out into A4, with some becoming A5.
Drilling seat backing ("L") angle into place took two people and the access hole. First I trimmed the piece to length and drew the centerline. Then I identified the center position ( left to right ) drilled the pilot side most hole that was not shared with extrusion. Then the helper from the outside clecoed the seat back, seat pan and ("L") together and removed some of the clecos that pushed against the ("L"). It was then a job of matching the line and back drilling through the seat, clecoing and then moving more towards the passenger side.
PROGRESS:
Fuselage ~161h ( 3h, 3h, 2h, 3h, 7h, 2h, 5h, 2h, 3h, 2h, 2h, 3h, 6h, 2h, 2h, 1.5h, 2.5h, 1h, 2h, 3h, 2h, 3h, 4h, 1h, 2h, 1h, 3h, 4h, 3h, 3h, 4h, 3h, 4h, 4h, 6h, 3h, 3h, 4h, 2h, 2h, 2h, 4h, 2h, 2h, 10h, 4h, 4h, 6h, 3h, 4h , 6h)
Wings: ~157.5h ( 1h, 1h, 0.5h, 2.5h, 4h, 1h, 1.5h, 1h, 1.5, 4.5, 1h, 1h, 2h, 4h, 1h, 3h, 1h, 2h, .5h, 1.5h, 2h, 2h, 2h, .5h, 1h, .5h, .5h, 2h,3h, 1h, 3h, 3h, 4h, 2h, 3h, 7h, 3h, 1h, 4h, 1h, 1h, 1h, 4h, 2h, 2h, 2h, 2h, 1h, 2h, 3h, 2h, 1h, 3h, 2h, 2h, 1h, 2h, 3h, 2h, 1h, 1h, 1.5, 2h, 2h, 3h, 2h, 1h, 3h, 2h, 1h, 2h, 1h, 5h, 2h, 1h, 2h, 4h, 2h )
Flaperons: ( DONE! ) 23.5 hours spent ( 3h, 1h, 1h, 1h, 1.5h, 3h, 6h, 3h, 4h, 1h )
Paint Design: 2 hours spent ( 1h, 1h )
Elevator DONE!: ~31.5 hours spent ( 3h, 1.5h, 3h, .5h, 3.5h, 2h, 4h, 1.5h, 2h, 4.5h, 1h, 6h )
Horizontal Stabilizer DONE!: ~28 hours spent, 3 pieces replaced ( 3h, 2h, 2h, 2h, .5h, 1.5h, 3.5h, 1.5h, 5, 4.5, 2h, .5h )
Rudder DONE!, minus horn : ~16 hours spent, ( ~8h, ~8h )
-----------------------
Total Done: ~423h
Friday, January 04, 2008
We spent about three hours getting the seat floors ready. First figuring out the procedure, then determining what needed to be fabricated. The pilot side seat is mostly drilled into place. A gusset needs to be fabricated and a supporting piece of ("L") needs to be positioned.Tip: When drilling the seat pan into the ("L") angle that runs along the torque tube cover, the proper place for the holes was significantly further in than 10mm ( referenced by the skin ). The curvature of the skin combined with the closed angle of the ("L) essentially moved the skin edge more inside than I expected. The 10mm edge line drawn on the skin translated to the holes being about 4mm from the radius of the ("L").
I also found that to place the ("L") the seat front channel had to be pulled forward away from the torque tube cover to allow space for the angle to get slipped in.
PROGRESS:
Fuselage ~151h ( 3h, 3h, 2h, 3h, 7h, 2h, 5h, 2h, 3h, 2h, 2h, 3h, 6h, 2h, 2h, 1.5h, 2.5h, 1h, 2h, 3h, 2h, 3h, 4h, 1h, 2h, 1h, 3h, 4h, 3h, 3h, 4h, 3h, 4h, 4h, 6h, 3h, 3h, 4h, 2h, 2h, 2h, 4h, 2h, 2h, 10h, 4h, 4h, 6h, 3h)
Wings: ~157.5h ( 1h, 1h, 0.5h, 2.5h, 4h, 1h, 1.5h, 1h, 1.5, 4.5, 1h, 1h, 2h, 4h, 1h, 3h, 1h, 2h, .5h, 1.5h, 2h, 2h, 2h, .5h, 1h, .5h, .5h, 2h,3h, 1h, 3h, 3h, 4h, 2h, 3h, 7h, 3h, 1h, 4h, 1h, 1h, 1h, 4h, 2h, 2h, 2h, 2h, 1h, 2h, 3h, 2h, 1h, 3h, 2h, 2h, 1h, 2h, 3h, 2h, 1h, 1h, 1.5, 2h, 2h, 3h, 2h, 1h, 3h, 2h, 1h, 2h, 1h, 5h, 2h, 1h, 2h, 4h, 2h )
Flaperons: ( DONE! ) 23.5 hours spent ( 3h, 1h, 1h, 1h, 1.5h, 3h, 6h, 3h, 4h, 1h )
Paint Design: 2 hours spent ( 1h, 1h )
Elevator DONE!: ~31.5 hours spent ( 3h, 1.5h, 3h, .5h, 3.5h, 2h, 4h, 1.5h, 2h, 4.5h, 1h, 6h )
Horizontal Stabilizer DONE!: ~28 hours spent, 3 pieces replaced ( 3h, 2h, 2h, 2h, .5h, 1.5h, 3.5h, 1.5h, 5, 4.5, 2h, .5h )
Rudder DONE!, minus horn : ~16 hours spent, ( ~8h, ~8h )
-----------------------
Total Done: ~413h
Wednesday, January 02, 2008
First some building footage:
Grinding Metal from John Marzulli on Vimeo.
And then some flying video.
Flying and Sunset from John Marzulli on Vimeo.
Grinding Metal from John Marzulli on Vimeo.
And then some flying video.
Flying and Sunset from John Marzulli on Vimeo.
Monday, December 31, 2007
It funny, there is no mention of drilling one of the seat back channels into place with the seat back. And when I say no mention... nothing the manual, nothing in the HBH videos, nothing in the Matronics archives. Here is a method for drilling 7F6-5 into place that I used:First, finding the notes in the plans was hard, so it is A4, pitch 40.
Don't worry about drilling it into the extrusion gusset yet. Draw your centerline on the flange that meets the seat back and push into place. I had one hole on the side extrusion that I had to match, but you are lucky you can just drill the flange into the uprights. Once the back support is positioned, extend the center line onto the uprights.
Cleco the seat back into place over 7F6-5. Now extend the centerline from the uprights onto the seat back. Now space your rivets making sure to take into account where the vertical ("L") will go in the seat back.
I drilled four test holes to make sure I had extended the line properly, which I had. The remaining holes were then drilled.
I also had to trim the bottom tabs of the engine mount for a good fit. Sadly the radius bend in the lower mount is causing fit issues. the solution may be shims, grinding away part of the frame rails, or both.
Here are some pictures detailing the issue.
PROGRESS:
Fuselage ~148h ( 3h, 3h, 2h, 3h, 7h, 2h, 5h, 2h, 3h, 2h, 2h, 3h, 6h, 2h, 2h, 1.5h, 2.5h, 1h, 2h, 3h, 2h, 3h, 4h, 1h, 2h, 1h, 3h, 4h, 3h, 3h, 4h, 3h, 4h, 4h, 6h, 3h, 3h, 4h, 2h, 2h, 2h, 4h, 2h, 2h, 10h, 4h, 4h, 6h)
Wings: ~157.5h ( 1h, 1h, 0.5h, 2.5h, 4h, 1h, 1.5h, 1h, 1.5, 4.5, 1h, 1h, 2h, 4h, 1h, 3h, 1h, 2h, .5h, 1.5h, 2h, 2h, 2h, .5h, 1h, .5h, .5h, 2h,3h, 1h, 3h, 3h, 4h, 2h, 3h, 7h, 3h, 1h, 4h, 1h, 1h, 1h, 4h, 2h, 2h, 2h, 2h, 1h, 2h, 3h, 2h, 1h, 3h, 2h, 2h, 1h, 2h, 3h, 2h, 1h, 1h, 1.5, 2h, 2h, 3h, 2h, 1h, 3h, 2h, 1h, 2h, 1h, 5h, 2h, 1h, 2h, 4h, 2h )
Flaperons: ( DONE! ) 23.5 hours spent ( 3h, 1h, 1h, 1h, 1.5h, 3h, 6h, 3h, 4h, 1h )
Paint Design: 2 hours spent ( 1h, 1h )
Elevator DONE!: ~31.5 hours spent ( 3h, 1.5h, 3h, .5h, 3.5h, 2h, 4h, 1.5h, 2h, 4.5h, 1h, 6h )
Horizontal Stabilizer DONE!: ~28 hours spent, 3 pieces replaced ( 3h, 2h, 2h, 2h, .5h, 1.5h, 3.5h, 1.5h, 5, 4.5, 2h, .5h )
Rudder DONE!, minus horn : ~16 hours spent, ( ~8h, ~8h )
-----------------------
Total Done: ~410h
Sunday, December 30, 2007

More stuff that has gotten done:
1) Trimmed and readied the cross wise fuselage tube. The holes are close together, but I over estimated the spacing on the aft side. If the spacing is too close for me when the holes are drilled out, then I will fabricate a new gusset and new tube and use that extra spacing.
2) Drilled the bottom fuselage tube gussets into place.
3) Fabricated the fuselage side extrusion gussets.
4) Trimmed the uprights to clear the gussets.
6) Drilled the fuselage extrusion gussets into place.
7) Drilled the fuselage extrusion into place.
On the pilot side the fuselage extrusion was trimmed 8mm too much and could not be placed to tie into the rear uprights. I am considering making a gusset out of 0.080 that would then tie the extrusion into uprights.
PROGRESS:
Fuselage ~142h ( 3h, 3h, 2h, 3h, 7h, 2h, 5h, 2h, 3h, 2h, 2h, 3h, 6h, 2h, 2h, 1.5h, 2.5h, 1h, 2h, 3h, 2h, 3h, 4h, 1h, 2h, 1h, 3h, 4h, 3h, 3h, 4h, 3h, 4h, 4h, 6h, 3h, 3h, 4h, 2h, 2h, 2h, 4h, 2h, 2h, 10h, 4h, 4h)
Wings: ~157.5h ( 1h, 1h, 0.5h, 2.5h, 4h, 1h, 1.5h, 1h, 1.5, 4.5, 1h, 1h, 2h, 4h, 1h, 3h, 1h, 2h, .5h, 1.5h, 2h, 2h, 2h, .5h, 1h, .5h, .5h, 2h,3h, 1h, 3h, 3h, 4h, 2h, 3h, 7h, 3h, 1h, 4h, 1h, 1h, 1h, 4h, 2h, 2h, 2h, 2h, 1h, 2h, 3h, 2h, 1h, 3h, 2h, 2h, 1h, 2h, 3h, 2h, 1h, 1h, 1.5, 2h, 2h, 3h, 2h, 1h, 3h, 2h, 1h, 2h, 1h, 5h, 2h, 1h, 2h, 4h, 2h )
Flaperons: ( DONE! ) 23.5 hours spent ( 3h, 1h, 1h, 1h, 1.5h, 3h, 6h, 3h, 4h, 1h )
Paint Design: 2 hours spent ( 1h, 1h )
Elevator DONE!: ~31.5 hours spent ( 3h, 1.5h, 3h, .5h, 3.5h, 2h, 4h, 1.5h, 2h, 4.5h, 1h, 6h )
Horizontal Stabilizer DONE!: ~28 hours spent, 3 pieces replaced ( 3h, 2h, 2h, 2h, .5h, 1.5h, 3.5h, 1.5h, 5, 4.5, 2h, .5h )
Rudder DONE!, minus horn : ~16 hours spent, ( ~8h, ~8h )
-----------------------
Total Done: ~404h
Thursday, December 27, 2007
Several short building sessions worth about 10 hours:1) Built the wing pickup templates ( go slow and get this right! )
2) Did more trimming to the fuselage side extrusion
3) Trimmed the fuselage tubing
4) Fabricated a Festivus pole, burning out the Dremel
5) Fitted the fuselage frame together with the front and rear. This required taking the fuselage and wings into our front yard... in view of the street. Several people walked by not even looking.
6) Test fitted the wings together with the fuselage.
All the work was easy, but stuff that you want to get right. When making the wing pickup templates test fit them from the top of the template to ensure the fit. The entire template can not be shoved into the wing root since the template front is cut at an angle.
PROGRESS:
Fuselage ~134h ( 3h, 3h, 2h, 3h, 7h, 2h, 5h, 2h, 3h, 2h, 2h, 3h, 6h, 2h, 2h, 1.5h, 2.5h, 1h, 2h, 3h, 2h, 3h, 4h, 1h, 2h, 1h, 3h, 4h, 3h, 3h, 4h, 3h, 4h, 4h, 6h, 3h, 3h, 4h, 2h, 2h, 2h, 4h, 2h, 2h, 10h)
Wings: ~157.5h ( 1h, 1h, 0.5h, 2.5h, 4h, 1h, 1.5h, 1h, 1.5, 4.5, 1h, 1h, 2h, 4h, 1h, 3h, 1h, 2h, .5h, 1.5h, 2h, 2h, 2h, .5h, 1h, .5h, .5h, 2h,3h, 1h, 3h, 3h, 4h, 2h, 3h, 7h, 3h, 1h, 4h, 1h, 1h, 1h, 4h, 2h, 2h, 2h, 2h, 1h, 2h, 3h, 2h, 1h, 3h, 2h, 2h, 1h, 2h, 3h, 2h, 1h, 1h, 1.5, 2h, 2h, 3h, 2h, 1h, 3h, 2h, 1h, 2h, 1h, 5h, 2h, 1h, 2h, 4h, 2h )
Flaperons: ( DONE! ) 23.5 hours spent ( 3h, 1h, 1h, 1h, 1.5h, 3h, 6h, 3h, 4h, 1h )
Paint Design: 2 hours spent ( 1h, 1h )
Elevator DONE!: ~31.5 hours spent ( 3h, 1.5h, 3h, .5h, 3.5h, 2h, 4h, 1.5h, 2h, 4.5h, 1h, 6h )
Horizontal Stabilizer DONE!: ~28 hours spent, 3 pieces replaced ( 3h, 2h, 2h, 2h, .5h, 1.5h, 3.5h, 1.5h, 5, 4.5, 2h, .5h )
Rudder DONE!, minus horn : ~16 hours spent, ( ~8h, ~8h )
-----------------------
Total Done: ~396h
Monday, December 17, 2007
Friday night two hours were spent installing the grommets in the fuselage front and riveting the doublers and front together with the forward fuselage. The first attempts to align the rear and front fuselage were also made. The flaperon stop fabrication was finished and a few initial holes were made to join the firewall to the bottom fuselage skins.Sunday night we finished joining the forward and rear fuselage halves along the the bottom seem. This took a great deal of time adjusting making sure that the front and rear were straight with each other.
To make the job easier we raised the entire fuselage up using steel beams and then drilled several holes on each side with the angle drill after the alignment was completed. The fuselage was then pulled forward off the table ( still using beams to support it ) so I could reach under and drill all the remaining holes.
While preparing the start work with 7F12-1, I got out the new engine mount that Zenith provided along with the remaining steal tube frame and started test fitting them. While the engine mount mostly fit on the firewall, much to my horror the middle side mounts are below the flange of the channel by about 10mm. My first thought was that the channel was up too high, but the gear strut is in perfect alignment and length with it, I measure carefully AND the other flange interferes with the engine mount. The upper tubes of the mount descend relative to the fuselage, but in order for the tubes to clear the channel they would have to ascend.
Update:
So before contacting Zenith I realized I should check the builder's area of the 701 site. Right there was a new updated builder's manual section for the new engine mounts. It turns out that the middle mounts are not intended to join the firewall at the channel, and the bottom mount needs to be trimmed to an angle so they attach below the longerons, which should place the middle mounts exactly where they should be.
PROGRESS:
Fuselage ~124h ( 3h, 3h, 2h, 3h, 7h, 2h, 5h, 2h, 3h, 2h, 2h, 3h, 6h, 2h, 2h, 1.5h, 2.5h, 1h, 2h, 3h, 2h, 3h, 4h, 1h, 2h, 1h, 3h, 4h, 3h, 3h, 4h, 3h, 4h, 4h, 6h, 3h, 3h, 4h, 2h, 2h, 2h, 4h, 2h, 2h)
Wings: ~157.5h ( 1h, 1h, 0.5h, 2.5h, 4h, 1h, 1.5h, 1h, 1.5, 4.5, 1h, 1h, 2h, 4h, 1h, 3h, 1h, 2h, .5h, 1.5h, 2h, 2h, 2h, .5h, 1h, .5h, .5h, 2h,3h, 1h, 3h, 3h, 4h, 2h, 3h, 7h, 3h, 1h, 4h, 1h, 1h, 1h, 4h, 2h, 2h, 2h, 2h, 1h, 2h, 3h, 2h, 1h, 3h, 2h, 2h, 1h, 2h, 3h, 2h, 1h, 1h, 1.5, 2h, 2h, 3h, 2h, 1h, 3h, 2h, 1h, 2h, 1h, 5h, 2h, 1h, 2h, 4h, 2h )
Flaperons: ( DONE! ) 23.5 hours spent ( 3h, 1h, 1h, 1h, 1.5h, 3h, 6h, 3h, 4h, 1h )
Paint Design: 2 hours spent ( 1h, 1h )
Elevator DONE!: ~31.5 hours spent ( 3h, 1.5h, 3h, .5h, 3.5h, 2h, 4h, 1.5h, 2h, 4.5h, 1h, 6h )
Horizontal Stabilizer DONE!: ~28 hours spent, 3 pieces replaced ( 3h, 2h, 2h, 2h, .5h, 1.5h, 3.5h, 1.5h, 5, 4.5, 2h, .5h )
Rudder DONE!, minus horn : ~16 hours spent, ( ~8h, ~8h )
-----------------------
Total Done: ~386h
Saturday, December 08, 2007
Friday night we spent two hours drilling out the remaining holes, fabricating 7F11-8 ( float reinforcement plate ) and priming the parts.Saturday night we riveted most of the forward fuselage together. I opted not to rivet the seat front yet since I have still not bought the grommets or fitted the fairlead. The flap stop also was not riveted.
Properly riveting the longerons was challenging due to the size of the flange. Luckily the metal was still thin enough to allow the riveter head to push in and become flush.
After the riveting was done I did a test fit between the forward and rear fuselage. The obtain a good fit the uprights had to be trimmed and the extrusion that is part of the side skins required additional trimming. Of course the doors had to be put in their approximate place along with the firewall.

PROGRESS:
Fuselage ~120h ( 3h, 3h, 2h, 3h, 7h, 2h, 5h, 2h, 3h, 2h, 2h, 3h, 6h, 2h, 2h, 1.5h, 2.5h, 1h, 2h, 3h, 2h, 3h, 4h, 1h, 2h, 1h, 3h, 4h, 3h, 3h, 4h, 3h, 4h, 4h, 6h, 3h, 3h, 4h, 2h, 2h, 2h, 4h)
Wings: ~157.5h ( 1h, 1h, 0.5h, 2.5h, 4h, 1h, 1.5h, 1h, 1.5, 4.5, 1h, 1h, 2h, 4h, 1h, 3h, 1h, 2h, .5h, 1.5h, 2h, 2h, 2h, .5h, 1h, .5h, .5h, 2h,3h, 1h, 3h, 3h, 4h, 2h, 3h, 7h, 3h, 1h, 4h, 1h, 1h, 1h, 4h, 2h, 2h, 2h, 2h, 1h, 2h, 3h, 2h, 1h, 3h, 2h, 2h, 1h, 2h, 3h, 2h, 1h, 1h, 1.5, 2h, 2h, 3h, 2h, 1h, 3h, 2h, 1h, 2h, 1h, 5h, 2h, 1h, 2h, 4h, 2h )
Flaperons: ( DONE! ) 23.5 hours spent ( 3h, 1h, 1h, 1h, 1.5h, 3h, 6h, 3h, 4h, 1h )
Paint Design: 2 hours spent ( 1h, 1h )
Elevator DONE!: ~31.5 hours spent ( 3h, 1.5h, 3h, .5h, 3.5h, 2h, 4h, 1.5h, 2h, 4.5h, 1h, 6h )
Horizontal Stabilizer DONE!: ~28 hours spent, 3 pieces replaced ( 3h, 2h, 2h, 2h, .5h, 1.5h, 3.5h, 1.5h, 5, 4.5, 2h, .5h )
Rudder DONE!, minus horn : ~16 hours spent, ( ~8h, ~8h )
-----------------------
Total Done: ~382h
Friday, December 07, 2007
Two hours were spent Thursday night drilling out the remaining holes to A4s and A5s and starting the long slow deburring process.
PROGRESS:
Fuselage ~114h ( 3h, 3h, 2h, 3h, 7h, 2h, 5h, 2h, 3h, 2h, 2h, 3h, 6h, 2h, 2h, 1.5h, 2.5h, 1h, 2h, 3h, 2h, 3h, 4h, 1h, 2h, 1h, 3h, 4h, 3h, 3h, 4h, 3h, 4h, 4h, 6h, 3h, 3h, 4h, 2h, 2h)
Wings: ~157.5h ( 1h, 1h, 0.5h, 2.5h, 4h, 1h, 1.5h, 1h, 1.5, 4.5, 1h, 1h, 2h, 4h, 1h, 3h, 1h, 2h, .5h, 1.5h, 2h, 2h, 2h, .5h, 1h, .5h, .5h, 2h,3h, 1h, 3h, 3h, 4h, 2h, 3h, 7h, 3h, 1h, 4h, 1h, 1h, 1h, 4h, 2h, 2h, 2h, 2h, 1h, 2h, 3h, 2h, 1h, 3h, 2h, 2h, 1h, 2h, 3h, 2h, 1h, 1h, 1.5, 2h, 2h, 3h, 2h, 1h, 3h, 2h, 1h, 2h, 1h, 5h, 2h, 1h, 2h, 4h, 2h )
Flaperons: ( DONE! ) 23.5 hours spent ( 3h, 1h, 1h, 1h, 1.5h, 3h, 6h, 3h, 4h, 1h )
Paint Design: 2 hours spent ( 1h, 1h )
Elevator DONE!: ~31.5 hours spent ( 3h, 1.5h, 3h, .5h, 3.5h, 2h, 4h, 1.5h, 2h, 4.5h, 1h, 6h )
Horizontal Stabilizer DONE!: ~28 hours spent, 3 pieces replaced ( 3h, 2h, 2h, 2h, .5h, 1.5h, 3.5h, 1.5h, 5, 4.5, 2h, .5h )
Rudder DONE!, minus horn : ~16 hours spent, ( ~8h, ~8h )
-----------------------
Total Done: ~376h
PROGRESS:
Fuselage ~114h ( 3h, 3h, 2h, 3h, 7h, 2h, 5h, 2h, 3h, 2h, 2h, 3h, 6h, 2h, 2h, 1.5h, 2.5h, 1h, 2h, 3h, 2h, 3h, 4h, 1h, 2h, 1h, 3h, 4h, 3h, 3h, 4h, 3h, 4h, 4h, 6h, 3h, 3h, 4h, 2h, 2h)
Wings: ~157.5h ( 1h, 1h, 0.5h, 2.5h, 4h, 1h, 1.5h, 1h, 1.5, 4.5, 1h, 1h, 2h, 4h, 1h, 3h, 1h, 2h, .5h, 1.5h, 2h, 2h, 2h, .5h, 1h, .5h, .5h, 2h,3h, 1h, 3h, 3h, 4h, 2h, 3h, 7h, 3h, 1h, 4h, 1h, 1h, 1h, 4h, 2h, 2h, 2h, 2h, 1h, 2h, 3h, 2h, 1h, 3h, 2h, 2h, 1h, 2h, 3h, 2h, 1h, 1h, 1.5, 2h, 2h, 3h, 2h, 1h, 3h, 2h, 1h, 2h, 1h, 5h, 2h, 1h, 2h, 4h, 2h )
Flaperons: ( DONE! ) 23.5 hours spent ( 3h, 1h, 1h, 1h, 1.5h, 3h, 6h, 3h, 4h, 1h )
Paint Design: 2 hours spent ( 1h, 1h )
Elevator DONE!: ~31.5 hours spent ( 3h, 1.5h, 3h, .5h, 3.5h, 2h, 4h, 1.5h, 2h, 4.5h, 1h, 6h )
Horizontal Stabilizer DONE!: ~28 hours spent, 3 pieces replaced ( 3h, 2h, 2h, 2h, .5h, 1.5h, 3.5h, 1.5h, 5, 4.5, 2h, .5h )
Rudder DONE!, minus horn : ~16 hours spent, ( ~8h, ~8h )
-----------------------
Total Done: ~376h
Monday, December 03, 2007
On Sunday we spent two hours opening up all the holes to at least A4.
The bigger effort was taking care of the flooding that took place. The driveway and workshops drains clogged with silt, causing several inches of standing water. By the time I realized what was happening, about 100 gallons had filled the garage. Luckily a neighbor had a 12 gallon wetvac that we used to sump the water out with and the clog was cleared with a snake.
PROGRESS:
Fuselage ~112h ( 3h, 3h, 2h, 3h, 7h, 2h, 5h, 2h, 3h, 2h, 2h, 3h, 6h, 2h, 2h, 1.5h, 2.5h, 1h, 2h, 3h, 2h, 3h, 4h, 1h, 2h, 1h, 3h, 4h, 3h, 3h, 4h, 3h, 4h, 4h, 6h, 3h, 3h, 4h, 2h)
Wings: ~157.5h ( 1h, 1h, 0.5h, 2.5h, 4h, 1h, 1.5h, 1h, 1.5, 4.5, 1h, 1h, 2h, 4h, 1h, 3h, 1h, 2h, .5h, 1.5h, 2h, 2h, 2h, .5h, 1h, .5h, .5h, 2h,3h, 1h, 3h, 3h, 4h, 2h, 3h, 7h, 3h, 1h, 4h, 1h, 1h, 1h, 4h, 2h, 2h, 2h, 2h, 1h, 2h, 3h, 2h, 1h, 3h, 2h, 2h, 1h, 2h, 3h, 2h, 1h, 1h, 1.5, 2h, 2h, 3h, 2h, 1h, 3h, 2h, 1h, 2h, 1h, 5h, 2h, 1h, 2h, 4h, 2h )
Flaperons: ( DONE! ) 23.5 hours spent ( 3h, 1h, 1h, 1h, 1.5h, 3h, 6h, 3h, 4h, 1h )
Paint Design: 2 hours spent ( 1h, 1h )
Elevator DONE!: ~31.5 hours spent ( 3h, 1.5h, 3h, .5h, 3.5h, 2h, 4h, 1.5h, 2h, 4.5h, 1h, 6h )
Horizontal Stabilizer DONE!: ~28 hours spent, 3 pieces replaced ( 3h, 2h, 2h, 2h, .5h, 1.5h, 3.5h, 1.5h, 5, 4.5, 2h, .5h )
Rudder DONE!, minus horn : ~16 hours spent, ( ~8h, ~8h )
-----------------------
Total Done: ~374h
The bigger effort was taking care of the flooding that took place. The driveway and workshops drains clogged with silt, causing several inches of standing water. By the time I realized what was happening, about 100 gallons had filled the garage. Luckily a neighbor had a 12 gallon wetvac that we used to sump the water out with and the clog was cleared with a snake.
PROGRESS:
Fuselage ~112h ( 3h, 3h, 2h, 3h, 7h, 2h, 5h, 2h, 3h, 2h, 2h, 3h, 6h, 2h, 2h, 1.5h, 2.5h, 1h, 2h, 3h, 2h, 3h, 4h, 1h, 2h, 1h, 3h, 4h, 3h, 3h, 4h, 3h, 4h, 4h, 6h, 3h, 3h, 4h, 2h)
Wings: ~157.5h ( 1h, 1h, 0.5h, 2.5h, 4h, 1h, 1.5h, 1h, 1.5, 4.5, 1h, 1h, 2h, 4h, 1h, 3h, 1h, 2h, .5h, 1.5h, 2h, 2h, 2h, .5h, 1h, .5h, .5h, 2h,3h, 1h, 3h, 3h, 4h, 2h, 3h, 7h, 3h, 1h, 4h, 1h, 1h, 1h, 4h, 2h, 2h, 2h, 2h, 1h, 2h, 3h, 2h, 1h, 3h, 2h, 2h, 1h, 2h, 3h, 2h, 1h, 1h, 1.5, 2h, 2h, 3h, 2h, 1h, 3h, 2h, 1h, 2h, 1h, 5h, 2h, 1h, 2h, 4h, 2h )
Flaperons: ( DONE! ) 23.5 hours spent ( 3h, 1h, 1h, 1h, 1.5h, 3h, 6h, 3h, 4h, 1h )
Paint Design: 2 hours spent ( 1h, 1h )
Elevator DONE!: ~31.5 hours spent ( 3h, 1.5h, 3h, .5h, 3.5h, 2h, 4h, 1.5h, 2h, 4.5h, 1h, 6h )
Horizontal Stabilizer DONE!: ~28 hours spent, 3 pieces replaced ( 3h, 2h, 2h, 2h, .5h, 1.5h, 3.5h, 1.5h, 5, 4.5, 2h, .5h )
Rudder DONE!, minus horn : ~16 hours spent, ( ~8h, ~8h )
-----------------------
Total Done: ~374h
Sunday, December 02, 2007
Saturday night we spent four hours getting the bottom half of the fuselage ready for drilling out to the final size holes. As part of that effort the tunnel was drilled into place, the seat belt points were drilled in, parts were trimmed and the flap stop was drilled into place and is ready for fabrication.
PROGRESS:
Fuselage ~110h ( 3h, 3h, 2h, 3h, 7h, 2h, 5h, 2h, 3h, 2h, 2h, 3h, 6h, 2h, 2h, 1.5h, 2.5h, 1h, 2h, 3h, 2h, 3h, 4h, 1h, 2h, 1h, 3h, 4h, 3h, 3h, 4h, 3h, 4h, 4h, 6h, 3h, 3h, 4h)
Wings: ~157.5h ( 1h, 1h, 0.5h, 2.5h, 4h, 1h, 1.5h, 1h, 1.5, 4.5, 1h, 1h, 2h, 4h, 1h, 3h, 1h, 2h, .5h, 1.5h, 2h, 2h, 2h, .5h, 1h, .5h, .5h, 2h,3h, 1h, 3h, 3h, 4h, 2h, 3h, 7h, 3h, 1h, 4h, 1h, 1h, 1h, 4h, 2h, 2h, 2h, 2h, 1h, 2h, 3h, 2h, 1h, 3h, 2h, 2h, 1h, 2h, 3h, 2h, 1h, 1h, 1.5, 2h, 2h, 3h, 2h, 1h, 3h, 2h, 1h, 2h, 1h, 5h, 2h, 1h, 2h, 4h, 2h )
Flaperons: ( DONE! ) 23.5 hours spent ( 3h, 1h, 1h, 1h, 1.5h, 3h, 6h, 3h, 4h, 1h )
Paint Design: 2 hours spent ( 1h, 1h )
Elevator DONE!: ~31.5 hours spent ( 3h, 1.5h, 3h, .5h, 3.5h, 2h, 4h, 1.5h, 2h, 4.5h, 1h, 6h )
Horizontal Stabilizer DONE!: ~28 hours spent, 3 pieces replaced ( 3h, 2h, 2h, 2h, .5h, 1.5h, 3.5h, 1.5h, 5, 4.5, 2h, .5h )
Rudder DONE!, minus horn : ~16 hours spent, ( ~8h, ~8h )
-----------------------
Total Done: ~372h
PROGRESS:
Fuselage ~110h ( 3h, 3h, 2h, 3h, 7h, 2h, 5h, 2h, 3h, 2h, 2h, 3h, 6h, 2h, 2h, 1.5h, 2.5h, 1h, 2h, 3h, 2h, 3h, 4h, 1h, 2h, 1h, 3h, 4h, 3h, 3h, 4h, 3h, 4h, 4h, 6h, 3h, 3h, 4h)
Wings: ~157.5h ( 1h, 1h, 0.5h, 2.5h, 4h, 1h, 1.5h, 1h, 1.5, 4.5, 1h, 1h, 2h, 4h, 1h, 3h, 1h, 2h, .5h, 1.5h, 2h, 2h, 2h, .5h, 1h, .5h, .5h, 2h,3h, 1h, 3h, 3h, 4h, 2h, 3h, 7h, 3h, 1h, 4h, 1h, 1h, 1h, 4h, 2h, 2h, 2h, 2h, 1h, 2h, 3h, 2h, 1h, 3h, 2h, 2h, 1h, 2h, 3h, 2h, 1h, 1h, 1.5, 2h, 2h, 3h, 2h, 1h, 3h, 2h, 1h, 2h, 1h, 5h, 2h, 1h, 2h, 4h, 2h )
Flaperons: ( DONE! ) 23.5 hours spent ( 3h, 1h, 1h, 1h, 1.5h, 3h, 6h, 3h, 4h, 1h )
Paint Design: 2 hours spent ( 1h, 1h )
Elevator DONE!: ~31.5 hours spent ( 3h, 1.5h, 3h, .5h, 3.5h, 2h, 4h, 1.5h, 2h, 4.5h, 1h, 6h )
Horizontal Stabilizer DONE!: ~28 hours spent, 3 pieces replaced ( 3h, 2h, 2h, 2h, .5h, 1.5h, 3.5h, 1.5h, 5, 4.5, 2h, .5h )
Rudder DONE!, minus horn : ~16 hours spent, ( ~8h, ~8h )
-----------------------
Total Done: ~372h
Subscribe to:
Posts (Atom)







