Monday, July 30, 2007

I spent another hour on the root wing skin... this time laying out the correct side. After giving it a rough cut and reading over the directions, I decided I need a new tool. The hole finder I fabricated is not the correct type. Mine was under the assumption that the existing hole was accessible from beneath, also it was way to short.

This wing is getting close!

Project Status:
Wings: ~138.5h ( 1h, 1h, 0.5h, 2.5h, 4h, 1h, 1.5h, 1h, 1.5, 4.5, 1h, 1h, 2h, 4h, 1h, 3h, 1h, 2h, .5h, 1.5h, 2h, 2h, 2h, .5h, 1h, .5h, .5h, 2h,3h, 1h, 3h, 3h, 4h, 2h, 3h, 7h, 3h, 1h, 4h, 1h, 1h, 1h, 4h, 2h, 2h, 2h, 2h, 1h, 2h, 3h, 2h, 1h, 3h, 2h, 2h, 1h, 2h, 3h, 2h, 1h, 1h, 1.5, 2h, 2h, 3h, 2h, 1h, 3h, 2h, 1h )
Flaperons: ( DONE! ) 23.5 hours spent ( 3h, 1h, 1h, 1h, 1.5h, 3h, 6h, 3h, 4h, 1h )
Paint Design: 2 hours spent ( 1h, 1h )
Elevator DONE!: ~31.5 hours spent ( 3h, 1.5h, 3h, .5h, 3.5h, 2h, 4h, 1.5h, 2h, 4.5h, 1h, 6h )
Horizontal Stabilizer DONE!: ~28 hours spent, 3 pieces replaced ( 3h, 2h, 2h, 2h, .5h, 1.5h, 3.5h, 1.5h, 5, 4.5, 2h, .5h )
Rudder DONE!, minus horn : ~16 hours spent, ( ~8h, ~8h )
-----------------------
Total Done: ~240h

Sunday, July 29, 2007

Another two hours of progress...

First the wing root angle angle was crimped trimmed, drilled and placed.

Next I carefully measure the wing root skin. This took forever... only to figure out that I measure for the right wing... and I'm working on the left wing.

At least work wasn't lost.

On Monday I will measure for the left wing.

Project Status:
Wings: ~137.5h ( 1h, 1h, 0.5h, 2.5h, 4h, 1h, 1.5h, 1h, 1.5, 4.5, 1h, 1h, 2h, 4h, 1h, 3h, 1h, 2h, .5h, 1.5h, 2h, 2h, 2h, .5h, 1h, .5h, .5h, 2h,3h, 1h, 3h, 3h, 4h, 2h, 3h, 7h, 3h, 1h, 4h, 1h, 1h, 1h, 4h, 2h, 2h, 2h, 2h, 1h, 2h, 3h, 2h, 1h, 3h, 2h, 2h, 1h, 2h, 3h, 2h, 1h, 1h, 1.5, 2h, 2h, 3h, 2h, 1h, 3h, 2h )
Flaperons: ( DONE! ) 23.5 hours spent ( 3h, 1h, 1h, 1h, 1.5h, 3h, 6h, 3h, 4h, 1h )
Paint Design: 2 hours spent ( 1h, 1h )
Elevator DONE!: ~31.5 hours spent ( 3h, 1.5h, 3h, .5h, 3.5h, 2h, 4h, 1.5h, 2h, 4.5h, 1h, 6h )
Horizontal Stabilizer DONE!: ~28 hours spent, 3 pieces replaced ( 3h, 2h, 2h, 2h, .5h, 1.5h, 3.5h, 1.5h, 5, 4.5, 2h, .5h )
Rudder DONE!, minus horn : ~16 hours spent, ( ~8h, ~8h )
-----------------------
Total Done: ~239h

Saturday, July 28, 2007

Not satisfied with the edge distance between the fiberglass and aluminum of the Horner tip, I made a fix. Using some of the newly discovered extra aluminum packed in the crate, I made what is essentially a splice plate to extend the aluminum. It works really well and can not be seen since I have it tucked underneath the fiberglass.

I also fit the left wing's position lights into place. This was simpler than I expected. I made a template out of a box laying around. For the larger hole I used the unibit for an initial 7/8th" hole, enlarging it was a rasp for a perfect fit.

The light itself is of a different size than Zenith's so it has a bit of overhang, but does not look bad.

In total, about three hours were spent on Saturday.

Project Status:
Wings: ~135.5h ( 1h, 1h, 0.5h, 2.5h, 4h, 1h, 1.5h, 1h, 1.5, 4.5, 1h, 1h, 2h, 4h, 1h, 3h, 1h, 2h, .5h, 1.5h, 2h, 2h, 2h, .5h, 1h, .5h, .5h, 2h,3h, 1h, 3h, 3h, 4h, 2h, 3h, 7h, 3h, 1h, 4h, 1h, 1h, 1h, 4h, 2h, 2h, 2h, 2h, 1h, 2h, 3h, 2h, 1h, 3h, 2h, 2h, 1h, 2h, 3h, 2h, 1h, 1h, 1.5, 2h, 2h, 3h, 2h, 1h, 3h )
Flaperons: ( DONE! ) 23.5 hours spent ( 3h, 1h, 1h, 1h, 1.5h, 3h, 6h, 3h, 4h, 1h )
Paint Design: 2 hours spent ( 1h, 1h )
Elevator DONE!: ~31.5 hours spent ( 3h, 1.5h, 3h, .5h, 3.5h, 2h, 4h, 1.5h, 2h, 4.5h, 1h, 6h )
Horizontal Stabilizer DONE!: ~28 hours spent, 3 pieces replaced ( 3h, 2h, 2h, 2h, .5h, 1.5h, 3.5h, 1.5h, 5, 4.5, 2h, .5h )
Rudder DONE!, minus horn : ~16 hours spent, ( ~8h, ~8h )
-----------------------
Total Done: ~237h

Wednesday, July 25, 2007

An hour was spent getting the wing tip cover into place and drilled. On the next wing, my process will be to place the wing tip cover BEFORE the fiberglass tip to make sure I can get a good edge distance on the Horner part.

Zenith precut the wing tip covers giving you zero amount of play or trim. The quick build CNC parts can be a blessing and a curse.

Project Status:
Wings: ~132.5h ( 1h, 1h, 0.5h, 2.5h, 4h, 1h, 1.5h, 1h, 1.5, 4.5, 1h, 1h, 2h, 4h, 1h, 3h, 1h, 2h, .5h, 1.5h, 2h, 2h, 2h, .5h, 1h, .5h, .5h, 2h,3h, 1h, 3h, 3h, 4h, 2h, 3h, 7h, 3h, 1h, 4h, 1h, 1h, 1h, 4h, 2h, 2h, 2h, 2h, 1h, 2h, 3h, 2h, 1h, 3h, 2h, 2h, 1h, 2h, 3h, 2h, 1h, 1h, 1.5, 2h, 2h, 3h, 2h, 1h )
Flaperons: ( DONE! ) 23.5 hours spent ( 3h, 1h, 1h, 1h, 1.5h, 3h, 6h, 3h, 4h, 1h )
Paint Design: 2 hours spent ( 1h, 1h )
Elevator DONE!: ~31.5 hours spent ( 3h, 1.5h, 3h, .5h, 3.5h, 2h, 4h, 1.5h, 2h, 4.5h, 1h, 6h )
Horizontal Stabilizer DONE!: ~28 hours spent, 3 pieces replaced ( 3h, 2h, 2h, 2h, .5h, 1.5h, 3.5h, 1.5h, 5, 4.5, 2h, .5h )
Rudder DONE!, minus horn : ~16 hours spent, ( ~8h, ~8h )
-----------------------
Total Done: ~234h

Tuesday, July 24, 2007


I spent two hours getting the fiberglass wing tip fit as good as possible. It is not a perfect fit, and I decided to shim a bit on the leading holes, but the fit is not poor. The (L) angle that attaches to the spar extension was also cut and drilled into place. The manual suggested 250mm for the piece, but then I would not have had any overlap. 280mm turned out to be the magic number. 285 or 290 may have also worked with some trimming.

These tips are notorious on the Matronics list, so I feel like I almost got off easy.

What really would help ( LISTEN UP ZENITH!!! ) would be to ship the tips with flanges that are at least another 10mm.

I could get the wing tip flush, but I would not have had anything to drill into!

Project Status:
Wings: ~131.5h ( 1h, 1h, 0.5h, 2.5h, 4h, 1h, 1.5h, 1h, 1.5, 4.5, 1h, 1h, 2h, 4h, 1h, 3h, 1h, 2h, .5h, 1.5h, 2h, 2h, 2h, .5h, 1h, .5h, .5h, 2h,3h, 1h, 3h, 3h, 4h, 2h, 3h, 7h, 3h, 1h, 4h, 1h, 1h, 1h, 4h, 2h, 2h, 2h, 2h, 1h, 2h, 3h, 2h, 1h, 3h, 2h, 2h, 1h, 2h, 3h, 2h, 1h, 1h, 1.5, 2h, 2h, 3h, 2h )
Flaperons: ( DONE! ) 23.5 hours spent ( 3h, 1h, 1h, 1h, 1.5h, 3h, 6h, 3h, 4h, 1h )
Paint Design: 2 hours spent ( 1h, 1h )
Elevator DONE!: ~31.5 hours spent ( 3h, 1.5h, 3h, .5h, 3.5h, 2h, 4h, 1.5h, 2h, 4.5h, 1h, 6h )
Horizontal Stabilizer DONE!: ~28 hours spent, 3 pieces replaced ( 3h, 2h, 2h, 2h, .5h, 1.5h, 3.5h, 1.5h, 5, 4.5, 2h, .5h )
Rudder DONE!, minus horn : ~16 hours spent, ( ~8h, ~8h )
-----------------------
Total Done: ~233h

Monday, July 23, 2007

I spent three hours and completed ALL of section 6A. The top and bottom tip angles were both crimped and drilled into place. The wing skins ( top & bottom ) were trimmed. I even placed in the fiberglass tip for a test fit.

A big thanks to Brian who lent me the fluting pliers on short notice!

Project Status:
Wings: ~129.5h ( 1h, 1h, 0.5h, 2.5h, 4h, 1h, 1.5h, 1h, 1.5, 4.5, 1h, 1h, 2h, 4h, 1h, 3h, 1h, 2h, .5h, 1.5h, 2h, 2h, 2h, .5h, 1h, .5h, .5h, 2h,3h, 1h, 3h, 3h, 4h, 2h, 3h, 7h, 3h, 1h, 4h, 1h, 1h, 1h, 4h, 2h, 2h, 2h, 2h, 1h, 2h, 3h, 2h, 1h, 3h, 2h, 2h, 1h, 2h, 3h, 2h, 1h, 1h, 1.5, 2h, 2h, 3h )
Flaperons: ( DONE! ) 23.5 hours spent ( 3h, 1h, 1h, 1h, 1.5h, 3h, 6h, 3h, 4h, 1h )
Paint Design: 2 hours spent ( 1h, 1h )
Elevator DONE!: ~31.5 hours spent ( 3h, 1.5h, 3h, .5h, 3.5h, 2h, 4h, 1.5h, 2h, 4.5h, 1h, 6h )
Horizontal Stabilizer DONE!: ~28 hours spent, 3 pieces replaced ( 3h, 2h, 2h, 2h, .5h, 1.5h, 3.5h, 1.5h, 5, 4.5, 2h, .5h )
Rudder DONE!, minus horn : ~16 hours spent, ( ~8h, ~8h )
-----------------------
Total Done: ~231h

Sunday, July 22, 2007

I spent about four hours on the wing today before getting blocked. We put the nose skin back on ( I can't wait to not have to ratchet strap anything again ) The top and nose skin were drilled to together on the outboard side along with the spar extension. The slat supports were also drilled into place.

The wing tank stills needs to be tested, but I want to wait until my Jeep's tank needs a little fuel.

The blocking issue is the fluting / crimping that needs to be performed on some extrusion so the wing tip can be placed. It's amazing what extent some of the prefabrication on the CH-701 is, providing predrilled skins, assembled spars, ect... but in the same breath expect you to flute extrusion without even telling you "oh, by the way... buy a pair of fluting pliers" is just strange and inconsistent.

So I attempted to make a pair with some wood... that didn't work out to well. That excursion took a few hours. Hopefully I can find a pair to borrow... that or UPS will make a ton on overnight delivery from me.

Is it just me, or does the AMD Patriot ( aka Ch750 ) look more like a Cessna than the Cessna 162 Sky Catcher? And yes... I'm drooling over the 162... and yes I want to be the first to fly one when they make their way up here.

Project Status:
Wings: ~126.5h ( 1h, 1h, 0.5h, 2.5h, 4h, 1h, 1.5h, 1h, 1.5, 4.5, 1h, 1h, 2h, 4h, 1h, 3h, 1h, 2h, .5h, 1.5h, 2h, 2h, 2h, .5h, 1h, .5h, .5h, 2h,3h, 1h, 3h, 3h, 4h, 2h, 3h, 7h, 3h, 1h, 4h, 1h, 1h, 1h, 4h, 2h, 2h, 2h, 2h, 1h, 2h, 3h, 2h, 1h, 3h, 2h, 2h, 1h, 2h, 3h, 2h, 1h, 1h, 1.5, 2h, 2h )
Flaperons: ( DONE! ) 23.5 hours spent ( 3h, 1h, 1h, 1h, 1.5h, 3h, 6h, 3h, 4h, 1h )
Paint Design: 2 hours spent ( 1h, 1h )
Elevator DONE!: ~31.5 hours spent ( 3h, 1.5h, 3h, .5h, 3.5h, 2h, 4h, 1.5h, 2h, 4.5h, 1h, 6h )
Horizontal Stabilizer DONE!: ~28 hours spent, 3 pieces replaced ( 3h, 2h, 2h, 2h, .5h, 1.5h, 3.5h, 1.5h, 5, 4.5, 2h, .5h )
Rudder DONE!, minus horn : ~16 hours spent, ( ~8h, ~8h )
-----------------------
Total Done: ~228h

Saturday, July 21, 2007

I only spent two hours on Saturday, but they were a productive two hours. The ground wires for the fuel tank and sender were attached and crimped.

Also I decided after much debate to run the PVC conduit through the tip ribs taking advantage of their tooling hole to secure the PVC. The root tip rib will need to have it's tooling hole expanded slightly to fit the wire, and a grommet will have to be added.

The top skin had the filler cap hole cut. I intentionally cut a slightly larger hole than I needed, and I'm glad I did. The filler cap is just touching one edge of the hole. I'm not sure what to do about the small gap in the skin.

While looking for my wire crimper I found a scratch built CH-801 that was first started while I lived in Texas. It was finally finished a few years ago and is in good shape for being packed away and moved across the country a few times.

The wings, nosebowl, rudder and stabilizer had all been removed. There are a few punctures in the wing and fuselage, but those will be easily repairable. I spent some time repairing it and reattached everything.

It of course is a scratch built stick and tissue model. Right now it is hanging off my right wing next to my DH2 Beaver.

It's on wheels right now, but floats should be easy to fabricate up.

Project Status:
Wings: ~126.5h ( 1h, 1h, 0.5h, 2.5h, 4h, 1h, 1.5h, 1h, 1.5, 4.5, 1h, 1h, 2h, 4h, 1h, 3h, 1h, 2h, .5h, 1.5h, 2h, 2h, 2h, .5h, 1h, .5h, .5h, 2h,3h, 1h, 3h, 3h, 4h, 2h, 3h, 7h, 3h, 1h, 4h, 1h, 1h, 1h, 4h, 2h, 2h, 2h, 2h, 1h, 2h, 3h, 2h, 1h, 3h, 2h, 2h, 1h, 2h, 3h, 2h, 1h, 1h, 1.5, 2h, 2h )
Flaperons: ( DONE! ) 23.5 hours spent ( 3h, 1h, 1h, 1h, 1.5h, 3h, 6h, 3h, 4h, 1h )
Paint Design: 2 hours spent ( 1h, 1h )
Elevator DONE!: ~31.5 hours spent ( 3h, 1.5h, 3h, .5h, 3.5h, 2h, 4h, 1.5h, 2h, 4.5h, 1h, 6h )
Horizontal Stabilizer DONE!: ~28 hours spent, 3 pieces replaced ( 3h, 2h, 2h, 2h, .5h, 1.5h, 3.5h, 1.5h, 5, 4.5, 2h, .5h )
Rudder DONE!, minus horn : ~16 hours spent, ( ~8h, ~8h )
-----------------------
Total Done: ~228h

Friday, July 20, 2007

I spent about two hours on misc items that needed to get done on the wing. The filler cap hole template was made, but not without complications. I'm not sure how Zenith expects you to back drill into the scrap. If the tank is in place ( which it must be in other to align the template ) then you can not possibly fit a drill between the tank and the spar to drill into the template. Also, fitting a drill from a rib would be another feat.

Instead I used a sharpie to mark a hole in the template from the rib, drilled that, then used a sharpie to mark the hole from the rib, then precision drilled that hole.

The strobe wire was cut, and I expanded the two tank rib tooling holes to fit the wire. The rest of the wire is in PVC. My thought was if I could further expand the tooling holes to fit the PVC and therefore be able to feed the wire all the way down the wing. The two concerns I have are 1) would expanding that hole cause need for additional reinforcement? 2) would the required bending put strange stresses on the wing?

Project Status:
Wings: ~124.5h ( 1h, 1h, 0.5h, 2.5h, 4h, 1h, 1.5h, 1h, 1.5, 4.5, 1h, 1h, 2h, 4h, 1h, 3h, 1h, 2h, .5h, 1.5h, 2h, 2h, 2h, .5h, 1h, .5h, .5h, 2h,3h, 1h, 3h, 3h, 4h, 2h, 3h, 7h, 3h, 1h, 4h, 1h, 1h, 1h, 4h, 2h, 2h, 2h, 2h, 1h, 2h, 3h, 2h, 1h, 3h, 2h, 2h, 1h, 2h, 3h, 2h, 1h, 1h, 1.5, 2h )
Flaperons: ( DONE! ) 23.5 hours spent ( 3h, 1h, 1h, 1h, 1.5h, 3h, 6h, 3h, 4h, 1h )
Paint Design: 2 hours spent ( 1h, 1h )
Elevator DONE!: ~31.5 hours spent ( 3h, 1.5h, 3h, .5h, 3.5h, 2h, 4h, 1.5h, 2h, 4.5h, 1h, 6h )
Horizontal Stabilizer DONE!: ~28 hours spent, 3 pieces replaced ( 3h, 2h, 2h, 2h, .5h, 1.5h, 3.5h, 1.5h, 5, 4.5, 2h, .5h )
Rudder DONE!, minus horn : ~16 hours spent, ( ~8h, ~8h )
-----------------------
Total Done: ~226h

Thursday, July 19, 2007

I corked the left tank along with the tank channels and then spent time figuring out the path of insertion.

With the channels in place the fuel tank will not fit. Instead have the inboard channels clecoed, insert the fuel tank and then slip the outboard channels between the rib and tank via the lightening holes.

I measured as best as I could for the placement of the fuel drain and fuel supply holes, but missed a bit. The hole in the rib was closest and was only enlarged a tiny bit. I may consider adding some scrap aluminum to the fuel drain hole just to make it look better.

Project Status:
Wings: ~122.5h ( 1h, 1h, 0.5h, 2.5h, 4h, 1h, 1.5h, 1h, 1.5, 4.5, 1h, 1h, 2h, 4h, 1h, 3h, 1h, 2h, .5h, 1.5h, 2h, 2h, 2h, .5h, 1h, .5h, .5h, 2h,3h, 1h, 3h, 3h, 4h, 2h, 3h, 7h, 3h, 1h, 4h, 1h, 1h, 1h, 4h, 2h, 2h, 2h, 2h, 1h, 2h, 3h, 2h, 1h, 3h, 2h, 2h, 1h, 2h, 3h, 2h, 1h, 1h, 1.5 )
Flaperons: ( DONE! ) 23.5 hours spent ( 3h, 1h, 1h, 1h, 1.5h, 3h, 6h, 3h, 4h, 1h )
Paint Design: 2 hours spent ( 1h, 1h )
Elevator DONE!: ~31.5 hours spent ( 3h, 1.5h, 3h, .5h, 3.5h, 2h, 4h, 1.5h, 2h, 4.5h, 1h, 6h )
Horizontal Stabilizer DONE!: ~28 hours spent, 3 pieces replaced ( 3h, 2h, 2h, 2h, .5h, 1.5h, 3.5h, 1.5h, 5, 4.5, 2h, .5h )
Rudder DONE!, minus horn : ~16 hours spent, ( ~8h, ~8h )
-----------------------
Total Done: ~224

Wednesday, July 18, 2007

It took about an hour to get the fuel tank channels drilled into place on the left wing.

The approach I took was simple: predrill the ribs then match up the channels on the flange. The top hole on each channel was drilled on the workbench first and then clecoed to the matching hole on the rib. This made clamping easier.

The determine where the holes went on the rib I eyeball centered the channel marking the top and bottom edges, and then measured the edge distance as the top and bottom holes. The remaining holes were set evenly by eyeball measurement.

Project Status:
Wings: ~121h ( 1h, 1h, 0.5h, 2.5h, 4h, 1h, 1.5h, 1h, 1.5, 4.5, 1h, 1h, 2h, 4h, 1h, 3h, 1h, 2h, .5h, 1.5h, 2h, 2h, 2h, .5h, 1h, .5h, .5h, 2h,3h, 1h, 3h, 3h, 4h, 2h, 3h, 7h, 3h, 1h, 4h, 1h, 1h, 1h, 4h, 2h, 2h, 2h, 2h, 1h, 2h, 3h, 2h, 1h, 3h, 2h, 2h, 1h, 2h, 3h, 2h, 1h, 1h )
Flaperons: ( DONE! ) 23.5 hours spent ( 3h, 1h, 1h, 1h, 1.5h, 3h, 6h, 3h, 4h, 1h )
Paint Design: 2 hours spent ( 1h, 1h )
Elevator DONE!: ~31.5 hours spent ( 3h, 1.5h, 3h, .5h, 3.5h, 2h, 4h, 1.5h, 2h, 4.5h, 1h, 6h )
Horizontal Stabilizer DONE!: ~28 hours spent, 3 pieces replaced ( 3h, 2h, 2h, 2h, .5h, 1.5h, 3.5h, 1.5h, 5, 4.5, 2h, .5h )
Rudder DONE!, minus horn : ~16 hours spent, ( ~8h, ~8h )
-----------------------
Total Done: ~222.5
Most of the night was spent talking to neighbors about the project, and an hour was spent building.

The tank channels were cut to size and an A4 hole finder was fabricated.

I also stopped by a NAPA and acquired some wiring supplies for the fuel tank.

The hole finder was simple to make using some scrap from the slat hole skin supports that I made in the incorrect direction. I kept some of the flange to provide stiffness. At first I had the rivet head centering the tool, but that didn't work too well on A3 holes. Flipping the rivet so a partially pulled rivet's bulb does the centering worked much better.


Project Status:
Wings: ~120h ( 1h, 1h, 0.5h, 2.5h, 4h, 1h, 1.5h, 1h, 1.5, 4.5, 1h, 1h, 2h, 4h, 1h, 3h, 1h, 2h, .5h, 1.5h, 2h, 2h, 2h, .5h, 1h, .5h, .5h, 2h,3h, 1h, 3h, 3h, 4h, 2h, 3h, 7h, 3h, 1h, 4h, 1h, 1h, 1h, 4h, 2h, 2h, 2h, 2h, 1h, 2h, 3h, 2h, 1h, 3h, 2h, 2h, 1h, 2h, 3h, 2h, 1h )
Flaperons: ( DONE! ) 23.5 hours spent ( 3h, 1h, 1h, 1h, 1.5h, 3h, 6h, 3h, 4h, 1h )
Paint Design: 2 hours spent ( 1h, 1h )
Elevator DONE!: ~31.5 hours spent ( 3h, 1.5h, 3h, .5h, 3.5h, 2h, 4h, 1.5h, 2h, 4.5h, 1h, 6h )
Horizontal Stabilizer DONE!: ~28 hours spent, 3 pieces replaced ( 3h, 2h, 2h, 2h, .5h, 1.5h, 3.5h, 1.5h, 5, 4.5, 2h, .5h )
Rudder DONE!, minus horn : ~16 hours spent, ( ~8h, ~8h )
-----------------------
Total Done: ~221.5

Monday, July 16, 2007

It was a two hour battle to get the fuel sender into the tank, but I won.

Luckily there was a Tacoma Screw literally right on the other side of the highway from my office, and they carried unibits and a fly cutter that fit my drill.

First, unibits are expensive.

The night started with me testing the new fly cutter on some scrap metal. I clamped the metal to some beams to simulate the flexibility that the fuel tank would have. Then I made a pilot A4 hole. With the circle cutter, I found that the metal flexed ( predictable ) and caused the cutter to hit unevenly and snag. Luckily snagging did not cause any tears or dings.

The solution was to use the drill to score the metal and then hand rotate the cutter until the hole was made.

Next came the tedious process of deburring and slowly enlarging the hole from about 57mm to 59mm. I spent almost an hour on this alone so as to work slowly and not accidentally oversize the hole.

Finally the sender slipped in and I was able to tighten the screws. Unfortunately I had the unit upside down as I found out when I used the Ohm meter to test it.

Project Status:
Wings: ~119h ( 1h, 1h, 0.5h, 2.5h, 4h, 1h, 1.5h, 1h, 1.5, 4.5, 1h, 1h, 2h, 4h, 1h, 3h, 1h, 2h, .5h, 1.5h, 2h, 2h, 2h, .5h, 1h, .5h, .5h, 2h,3h, 1h, 3h, 3h, 4h, 2h, 3h, 7h, 3h, 1h, 4h, 1h, 1h, 1h, 4h, 2h, 2h, 2h, 2h, 1h, 2h, 3h, 2h, 1h, 3h, 2h, 2h, 1h, 2h, 3h, 2h )
Flaperons: ( DONE! ) 23.5 hours spent ( 3h, 1h, 1h, 1h, 1.5h, 3h, 6h, 3h, 4h, 1h )
Paint Design: 2 hours spent ( 1h, 1h )
Elevator DONE!: ~31.5 hours spent ( 3h, 1.5h, 3h, .5h, 3.5h, 2h, 4h, 1.5h, 2h, 4.5h, 1h, 6h )
Horizontal Stabilizer DONE!: ~28 hours spent, 3 pieces replaced ( 3h, 2h, 2h, 2h, .5h, 1.5h, 3.5h, 1.5h, 5, 4.5, 2h, .5h )
Rudder DONE!, minus horn : ~16 hours spent, ( ~8h, ~8h )
-----------------------
Total Done: ~220.5
Sunday was spent preparing for the fuel tanks. A few rivets on the bottom wing skin still had to be pulled by hand as well.

The manual is slightly confusing in it's instructions for bending the fuel floats, and I couldn't find the schematics anywhere in the plans. In the end it was best just to look at the photos for clarification. I'm not sure if my skills with pliers need work, or if I'm weak, but it really took strength to make the required bends.

I practiced with the circle cutter and found two major problems: 1) None of my drills can take the shaft 2) Hand rotating it only causes the metal to rip.

Therefore I need to figure out a better way to cut the circle OR I need to buy a drill press.

Project Status:
Wings: ~117h ( 1h, 1h, 0.5h, 2.5h, 4h, 1h, 1.5h, 1h, 1.5, 4.5, 1h, 1h, 2h, 4h, 1h, 3h, 1h, 2h, .5h, 1.5h, 2h, 2h, 2h, .5h, 1h, .5h, .5h, 2h,3h, 1h, 3h, 3h, 4h, 2h, 3h, 7h, 3h, 1h, 4h, 1h, 1h, 1h, 4h, 2h, 2h, 2h, 2h, 1h, 2h, 3h, 2h, 1h, 3h, 2h, 2h, 1h, 2h, 3h )
Flaperons: ( DONE! ) 23.5 hours spent ( 3h, 1h, 1h, 1h, 1.5h, 3h, 6h, 3h, 4h, 1h )
Paint Design: 2 hours spent ( 1h, 1h )
Elevator DONE!: ~31.5 hours spent ( 3h, 1.5h, 3h, .5h, 3.5h, 2h, 4h, 1.5h, 2h, 4.5h, 1h, 6h )
Horizontal Stabilizer DONE!: ~28 hours spent, 3 pieces replaced ( 3h, 2h, 2h, 2h, .5h, 1.5h, 3.5h, 1.5h, 5, 4.5, 2h, .5h )
Rudder DONE!, minus horn : ~16 hours spent, ( ~8h, ~8h )
-----------------------
Total Done: ~218.5

Sunday, July 15, 2007

Arlington 2007 ( Saturday )



Edit: Since the first posting of these photos, I became unhappy with the color balance of a few of these "prints". Since then many of these have been readjusted to my liking.

If you want any of these photos in a size larger than 1600x1200, just drop me a line.

Sunday, July 08, 2007



On Saturday was spent about two hours deburring, chromating, and riveting the bottom skins and spars together.

A new hand riveter had just arrived from Zenith which made the flaperon brackets much easier.

On Sunday we had a nice day at Friday Harbor.




Project Status:
Wings: ~114h ( 1h, 1h, 0.5h, 2.5h, 4h, 1h, 1.5h, 1h, 1.5, 4.5, 1h, 1h, 2h, 4h, 1h, 3h, 1h, 2h, .5h, 1.5h, 2h, 2h, 2h, .5h, 1h, .5h, .5h, 2h,3h, 1h, 3h, 3h, 4h, 2h, 3h, 7h, 3h, 1h, 4h, 1h, 1h, 1h, 4h, 2h, 2h, 2h, 2h, 1h, 2h, 3h, 2h, 1h, 3h, 2h, 2h, 1h, 2h )
Flaperons: ( DONE! ) 23.5 hours spent ( 3h, 1h, 1h, 1h, 1.5h, 3h, 6h, 3h, 4h, 1h )
Paint Design: 2 hours spent ( 1h, 1h )
Elevator DONE!: ~31.5 hours spent ( 3h, 1.5h, 3h, .5h, 3.5h, 2h, 4h, 1.5h, 2h, 4.5h, 1h, 6h )
Horizontal Stabilizer DONE!: ~28 hours spent, 3 pieces replaced ( 3h, 2h, 2h, 2h, .5h, 1.5h, 3.5h, 1.5h, 5, 4.5, 2h, .5h )
Rudder DONE!, minus horn : ~16 hours spent, ( ~8h, ~8h )
-----------------------
Total Done: ~215.5

Wednesday, July 04, 2007

Tuesday night we spent about an hour finishing the drilling into the spar on both sides. The bottom is drilled out to A4, and is partially deburred. Wednesday we should finish the deburring, corrosion protecting, and get the bottom skins riveted on.

My inspection plates arrived today, so I may install those as well.

Project Status:
Wings: ~112h ( 1h, 1h, 0.5h, 2.5h, 4h, 1h, 1.5h, 1h, 1.5, 4.5, 1h, 1h, 2h, 4h, 1h, 3h, 1h, 2h, .5h, 1.5h, 2h, 2h, 2h, .5h, 1h, .5h, .5h, 2h,3h, 1h, 3h, 3h, 4h, 2h, 3h, 7h, 3h, 1h, 4h, 1h, 1h, 1h, 4h, 2h, 2h, 2h, 2h, 1h, 2h, 3h, 2h, 1h, 3h, 2h, 2h, 1h )
Flaperons: ( DONE! ) 23.5 hours spent ( 3h, 1h, 1h, 1h, 1.5h, 3h, 6h, 3h, 4h, 1h )
Paint Design: 2 hours spent ( 1h, 1h )
Elevator DONE!: ~31.5 hours spent ( 3h, 1.5h, 3h, .5h, 3.5h, 2h, 4h, 1.5h, 2h, 4.5h, 1h, 6h )
Horizontal Stabilizer DONE!: ~28 hours spent, 3 pieces replaced ( 3h, 2h, 2h, 2h, .5h, 1.5h, 3.5h, 1.5h, 5, 4.5, 2h, .5h )
Rudder DONE!, minus horn : ~16 hours spent, ( ~8h, ~8h )
-----------------------
Total Done: ~213.5

Tuesday, July 03, 2007

Monday night I got the nose skin drilled on the wing. I also finished the pilot holes from the nose skin into the top part of the spar.

The kit that Zenith provides has the front edge of the top skin predrilled, but not the nose skin. This is a problem since the nose skin overlaps on top of the top skin. The get around this before placing the nose skin, the top skin had several holes drilled into it into the spar which were marked with a sharpie on the skin.

When the nose skin was ratcheted on, I slipped it underneath the top skin and drilled those few holes using the lowest speed of my drill so I could find the matching spar hole beneath it.

Once those holes were clecoed, I then drilled lightly through the skin, trying not to enter the spar.

Once all the holes were matched, I slipped the nose skin over top the top skin, clecoed through the skin into the few holes that were in the spar, and then drilled through the remaining matched holes into the spar.

To help move the nose ribs into place, I made a hook out of some PVC that was laying around.

A few days ago I ordered my fuselage kit along with the bubble door option. I also ordered Jon "Crash" Croke's fuselage construction DVDs. I'll have a review up in the next week or so.

Also on it way are inspection plates and my lighting system. I decided on going with a ready solution since I would still have to match a driver unit and get the lenses.

Here is the Wick's page on the GS LED unit I will use: http://www.wicksaircraft.com/catalog/product_cat.php/subid=7000/index.html

Project Status:
Wings: ~111h ( 1h, 1h, 0.5h, 2.5h, 4h, 1h, 1.5h, 1h, 1.5, 4.5, 1h, 1h, 2h, 4h, 1h, 3h, 1h, 2h, .5h, 1.5h, 2h, 2h, 2h, .5h, 1h, .5h, .5h, 2h,3h, 1h, 3h, 3h, 4h, 2h, 3h, 7h, 3h, 1h, 4h, 1h, 1h, 1h, 4h, 2h, 2h, 2h, 2h, 1h, 2h, 3h, 2h, 1h, 3h, 2h, 2h )
Flaperons: ( DONE! ) 23.5 hours spent ( 3h, 1h, 1h, 1h, 1.5h, 3h, 6h, 3h, 4h, 1h )
Paint Design: 2 hours spent ( 1h, 1h )
Elevator DONE!: ~31.5 hours spent ( 3h, 1.5h, 3h, .5h, 3.5h, 2h, 4h, 1.5h, 2h, 4.5h, 1h, 6h )
Horizontal Stabilizer DONE!: ~28 hours spent, 3 pieces replaced ( 3h, 2h, 2h, 2h, .5h, 1.5h, 3.5h, 1.5h, 5, 4.5, 2h, .5h )
Rudder DONE!, minus horn : ~16 hours spent, ( ~8h, ~8h )
-----------------------
Total Done: ~212.5

Monday, July 02, 2007

There was no working on the "Sky Jeep" over the weekend. Instead, the real Jeep was taken out and given a proper workout.

Picasa has now added the ability to not automatically start the embedded slide shows. Please hit play or forward to navigate.