Wednesday, October 03, 2007

It took two hours to do a thirty minute job.

I accidentally way over trimmed the extended baggage panel ( 7F8-9B ). And by over trim, I mean I read the plans and the the directions...

The plans simply say "trim to fit", but I forgot that the panel was supposed to overlap the Zee Channel ( 7F8-10B ), so I thought the panel was 10mm too long, which made since since the baggage back was off by 10mm.

The remedy the situation I was able to find some extra 0.025 laing around that happened to be 800mm wide. I cut a piece 60mm deep and drilled it onto the front of the panel. Problem solved.

I did have to trim the extended panel in by 5mm on each side.

That will teach me for not triple checking against the HBH videos, plans AND manual.

Fuselage ~32h ( 3h, 3h, 2h, 3h, 7h, 2h, 5h, 2h, 3h, 2h )
Wings: ~157.5h ( 1h, 1h, 0.5h, 2.5h, 4h, 1h, 1.5h, 1h, 1.5, 4.5, 1h, 1h, 2h, 4h, 1h, 3h, 1h, 2h, .5h, 1.5h, 2h, 2h, 2h, .5h, 1h, .5h, .5h, 2h,3h, 1h, 3h, 3h, 4h, 2h, 3h, 7h, 3h, 1h, 4h, 1h, 1h, 1h, 4h, 2h, 2h, 2h, 2h, 1h, 2h, 3h, 2h, 1h, 3h, 2h, 2h, 1h, 2h, 3h, 2h, 1h, 1h, 1.5, 2h, 2h, 3h, 2h, 1h, 3h, 2h, 1h, 2h, 1h, 5h, 2h, 1h, 2h, 4h, 2h )
Flaperons: ( DONE! ) 23.5 hours spent ( 3h, 1h, 1h, 1h, 1.5h, 3h, 6h, 3h, 4h, 1h )
Paint Design: 2 hours spent ( 1h, 1h )
Elevator DONE!: ~31.5 hours spent ( 3h, 1.5h, 3h, .5h, 3.5h, 2h, 4h, 1.5h, 2h, 4.5h, 1h, 6h )
Horizontal Stabilizer DONE!: ~28 hours spent, 3 pieces replaced ( 3h, 2h, 2h, 2h, .5h, 1.5h, 3.5h, 1.5h, 5, 4.5, 2h, .5h )
Rudder DONE!, minus horn : ~16 hours spent, ( ~8h, ~8h )
-----------------------
Total Done: ~291h