Sunday, February 18, 2007

Saturday night we were able to sneak in about an hour and a half of work. Tasks completed included cutting the outboard rear wing channel for the wing tips, discovering that the inboard heavy duty rear wing channel required trimming, trimming them, figuring out the measurements and hole placements for the 7V4-3 ( doubler ) and then pre-drilling it.

Luckily all the trimming produced enough scrap to fill in for some 7V6-3. I found Zenith really does not provide enough of that piece. I can't imagine that it cost's that much, or would be too difficult to produce.

Project Status:
Wings: 34.5h ( 1h, 1h, 0.5h, 2.5h, 4h, 1h, 1.5h, 1h, 1.5, 4.5, 1h, 1h, 2h, 4h, 1h, 3h, 1h, 2h, .5h, 1.5h )
Flaperons: ( DONE! ) 23.5 hours spent ( 3h, 1h, 1h, 1h, 1.5h, 3h, 6h, 3h, 4h, 1h )
Paint Design: 2 hours spent ( 1h, 1h )
Elevator DONE!: ~31.5 hours spent ( 3h, 1.5h, 3h, .5h, 3.5h, 2h, 4h, 1.5h, 2h, 4.5h, 1h, 6h )
Horizontal Stabilizer DONE!: ~28 hours spent, 3 pieces replaced ( 3h, 2h, 2h, 2h, .5h, 1.5h, 3.5h, 1.5h, 5, 4.5, 2h, .5h )
Rudder DONE!, minus horn : ~16 hours spent, ( ~8h, ~8h )
-----------------------
Total Done: ~137 hours