We had a streak of great weather ( for the winter ). It would have been criminal not to take advantage of it.
Lake Cushman And Back from John Marzulli on Vimeo
Tuesday, January 29, 2008
Wednesday, January 23, 2008
The fuselage is corrosion protected, deburred and riveted together ( excluding the tubular frame ).
One thing to consider is the accessibility of the small piece ("L") angle that ties the side skins together with the seat pans on the outboard side. If I could call a mulligan then I would rivet the ("L") to the pan first, then cleco it to the side skin and rivet it with the rest of the seat.
Of course the momentous occasion was celebrated with the first sitting in the plane. The seats are as comfortable as can be hoped for. Skyshops really did a great job matching my colors and providing an overall well made product.
Next I will drill the engine mount to the firewall ( finally ) and make the instrument panel.
PROGRESS:
Fuselage ~190h ( 3h, 3h, 2h, 3h, 7h, 2h, 5h, 2h, 3h, 2h, 2h, 3h, 6h, 2h, 2h, 1.5h, 2.5h, 1h, 2h, 3h, 2h, 3h, 4h, 1h, 2h, 1h, 3h, 4h, 3h, 3h, 4h, 3h, 4h, 4h, 6h, 3h, 3h, 4h, 2h, 2h, 2h, 4h, 2h, 2h, 10h, 4h, 4h, 6h, 3h, 4h , 6h, 3h, 2h, 2h, 5h, 2h, 3h, 3h )
Wings: ~157.5h ( 1h, 1h, 0.5h, 2.5h, 4h, 1h, 1.5h, 1h, 1.5, 4.5, 1h, 1h, 2h, 4h, 1h, 3h, 1h, 2h, .5h, 1.5h, 2h, 2h, 2h, .5h, 1h, .5h, .5h, 2h,3h, 1h, 3h, 3h, 4h, 2h, 3h, 7h, 3h, 1h, 4h, 1h, 1h, 1h, 4h, 2h, 2h, 2h, 2h, 1h, 2h, 3h, 2h, 1h, 3h, 2h, 2h, 1h, 2h, 3h, 2h, 1h, 1h, 1.5, 2h, 2h, 3h, 2h, 1h, 3h, 2h, 1h, 2h, 1h, 5h, 2h, 1h, 2h, 4h, 2h, 3h, 3h, 3h )
Flaperons: ( DONE! ) 23.5 hours spent ( 3h, 1h, 1h, 1h, 1.5h, 3h, 6h, 3h, 4h, 1h )
Paint Design: 2 hours spent ( 1h, 1h )
Elevator DONE!: ~31.5 hours spent ( 3h, 1.5h, 3h, .5h, 3.5h, 2h, 4h, 1.5h, 2h, 4.5h, 1h, 6h )
Horizontal Stabilizer DONE!: ~28 hours spent, 3 pieces replaced ( 3h, 2h, 2h, 2h, .5h, 1.5h, 3.5h, 1.5h, 5, 4.5, 2h, .5h )
Rudder DONE!, minus horn : ~16 hours spent, ( ~8h, ~8h )
-----------------------
Total Done: ~452h
One thing to consider is the accessibility of the small piece ("L") angle that ties the side skins together with the seat pans on the outboard side. If I could call a mulligan then I would rivet the ("L") to the pan first, then cleco it to the side skin and rivet it with the rest of the seat.
Of course the momentous occasion was celebrated with the first sitting in the plane. The seats are as comfortable as can be hoped for. Skyshops really did a great job matching my colors and providing an overall well made product.
Next I will drill the engine mount to the firewall ( finally ) and make the instrument panel.
PROGRESS:
Fuselage ~190h ( 3h, 3h, 2h, 3h, 7h, 2h, 5h, 2h, 3h, 2h, 2h, 3h, 6h, 2h, 2h, 1.5h, 2.5h, 1h, 2h, 3h, 2h, 3h, 4h, 1h, 2h, 1h, 3h, 4h, 3h, 3h, 4h, 3h, 4h, 4h, 6h, 3h, 3h, 4h, 2h, 2h, 2h, 4h, 2h, 2h, 10h, 4h, 4h, 6h, 3h, 4h , 6h, 3h, 2h, 2h, 5h, 2h, 3h, 3h )
Wings: ~157.5h ( 1h, 1h, 0.5h, 2.5h, 4h, 1h, 1.5h, 1h, 1.5, 4.5, 1h, 1h, 2h, 4h, 1h, 3h, 1h, 2h, .5h, 1.5h, 2h, 2h, 2h, .5h, 1h, .5h, .5h, 2h,3h, 1h, 3h, 3h, 4h, 2h, 3h, 7h, 3h, 1h, 4h, 1h, 1h, 1h, 4h, 2h, 2h, 2h, 2h, 1h, 2h, 3h, 2h, 1h, 3h, 2h, 2h, 1h, 2h, 3h, 2h, 1h, 1h, 1.5, 2h, 2h, 3h, 2h, 1h, 3h, 2h, 1h, 2h, 1h, 5h, 2h, 1h, 2h, 4h, 2h, 3h, 3h, 3h )
Flaperons: ( DONE! ) 23.5 hours spent ( 3h, 1h, 1h, 1h, 1.5h, 3h, 6h, 3h, 4h, 1h )
Paint Design: 2 hours spent ( 1h, 1h )
Elevator DONE!: ~31.5 hours spent ( 3h, 1.5h, 3h, .5h, 3.5h, 2h, 4h, 1.5h, 2h, 4.5h, 1h, 6h )
Horizontal Stabilizer DONE!: ~28 hours spent, 3 pieces replaced ( 3h, 2h, 2h, 2h, .5h, 1.5h, 3.5h, 1.5h, 5, 4.5, 2h, .5h )
Rudder DONE!, minus horn : ~16 hours spent, ( ~8h, ~8h )
-----------------------
Total Done: ~452h
Sunday, January 20, 2008
Spent three hours drilling out the remaining holes and corrosion protecting. The gear strut fittings were somewhat brutal to drill as I broke a bit on the left and right side each.
PROGRESS:
Fuselage ~184h ( 3h, 3h, 2h, 3h, 7h, 2h, 5h, 2h, 3h, 2h, 2h, 3h, 6h, 2h, 2h, 1.5h, 2.5h, 1h, 2h, 3h, 2h, 3h, 4h, 1h, 2h, 1h, 3h, 4h, 3h, 3h, 4h, 3h, 4h, 4h, 6h, 3h, 3h, 4h, 2h, 2h, 2h, 4h, 2h, 2h, 10h, 4h, 4h, 6h, 3h, 4h , 6h, 3h, 2h, 2h, 5h, 2h, 3h, 3h )
Wings: ~157.5h ( 1h, 1h, 0.5h, 2.5h, 4h, 1h, 1.5h, 1h, 1.5, 4.5, 1h, 1h, 2h, 4h, 1h, 3h, 1h, 2h, .5h, 1.5h, 2h, 2h, 2h, .5h, 1h, .5h, .5h, 2h,3h, 1h, 3h, 3h, 4h, 2h, 3h, 7h, 3h, 1h, 4h, 1h, 1h, 1h, 4h, 2h, 2h, 2h, 2h, 1h, 2h, 3h, 2h, 1h, 3h, 2h, 2h, 1h, 2h, 3h, 2h, 1h, 1h, 1.5, 2h, 2h, 3h, 2h, 1h, 3h, 2h, 1h, 2h, 1h, 5h, 2h, 1h, 2h, 4h, 2h, 3h )
Flaperons: ( DONE! ) 23.5 hours spent ( 3h, 1h, 1h, 1h, 1.5h, 3h, 6h, 3h, 4h, 1h )
Paint Design: 2 hours spent ( 1h, 1h )
Elevator DONE!: ~31.5 hours spent ( 3h, 1.5h, 3h, .5h, 3.5h, 2h, 4h, 1.5h, 2h, 4.5h, 1h, 6h )
Horizontal Stabilizer DONE!: ~28 hours spent, 3 pieces replaced ( 3h, 2h, 2h, 2h, .5h, 1.5h, 3.5h, 1.5h, 5, 4.5, 2h, .5h )
Rudder DONE!, minus horn : ~16 hours spent, ( ~8h, ~8h )
-----------------------
Total Done: ~446h
PROGRESS:
Fuselage ~184h ( 3h, 3h, 2h, 3h, 7h, 2h, 5h, 2h, 3h, 2h, 2h, 3h, 6h, 2h, 2h, 1.5h, 2.5h, 1h, 2h, 3h, 2h, 3h, 4h, 1h, 2h, 1h, 3h, 4h, 3h, 3h, 4h, 3h, 4h, 4h, 6h, 3h, 3h, 4h, 2h, 2h, 2h, 4h, 2h, 2h, 10h, 4h, 4h, 6h, 3h, 4h , 6h, 3h, 2h, 2h, 5h, 2h, 3h, 3h )
Wings: ~157.5h ( 1h, 1h, 0.5h, 2.5h, 4h, 1h, 1.5h, 1h, 1.5, 4.5, 1h, 1h, 2h, 4h, 1h, 3h, 1h, 2h, .5h, 1.5h, 2h, 2h, 2h, .5h, 1h, .5h, .5h, 2h,3h, 1h, 3h, 3h, 4h, 2h, 3h, 7h, 3h, 1h, 4h, 1h, 1h, 1h, 4h, 2h, 2h, 2h, 2h, 1h, 2h, 3h, 2h, 1h, 3h, 2h, 2h, 1h, 2h, 3h, 2h, 1h, 1h, 1.5, 2h, 2h, 3h, 2h, 1h, 3h, 2h, 1h, 2h, 1h, 5h, 2h, 1h, 2h, 4h, 2h, 3h )
Flaperons: ( DONE! ) 23.5 hours spent ( 3h, 1h, 1h, 1h, 1.5h, 3h, 6h, 3h, 4h, 1h )
Paint Design: 2 hours spent ( 1h, 1h )
Elevator DONE!: ~31.5 hours spent ( 3h, 1.5h, 3h, .5h, 3.5h, 2h, 4h, 1.5h, 2h, 4.5h, 1h, 6h )
Horizontal Stabilizer DONE!: ~28 hours spent, 3 pieces replaced ( 3h, 2h, 2h, 2h, .5h, 1.5h, 3.5h, 1.5h, 5, 4.5, 2h, .5h )
Rudder DONE!, minus horn : ~16 hours spent, ( ~8h, ~8h )
-----------------------
Total Done: ~446h
Saturday, January 19, 2008
I finished drilling out the side skin attachments to the rear fuselage. I also fabbed the side skin doublers ( 7F16-6? ). Due to having already pilot drilled the seat gussets into place the first holes in the doubler were back drilled from the bottom. This required an extra person, a flashlight, an inspection mirror and an angle drill.
The only holes remaining are in the gear strut attachment.
Everything was deburred and is now ready for priming.
PROGRESS:
Fuselage ~181h ( 3h, 3h, 2h, 3h, 7h, 2h, 5h, 2h, 3h, 2h, 2h, 3h, 6h, 2h, 2h, 1.5h, 2.5h, 1h, 2h, 3h, 2h, 3h, 4h, 1h, 2h, 1h, 3h, 4h, 3h, 3h, 4h, 3h, 4h, 4h, 6h, 3h, 3h, 4h, 2h, 2h, 2h, 4h, 2h, 2h, 10h, 4h, 4h, 6h, 3h, 4h , 6h, 3h, 2h, 2h, 5h, 2h, 3h, 3h )
Wings: ~157.5h ( 1h, 1h, 0.5h, 2.5h, 4h, 1h, 1.5h, 1h, 1.5, 4.5, 1h, 1h, 2h, 4h, 1h, 3h, 1h, 2h, .5h, 1.5h, 2h, 2h, 2h, .5h, 1h, .5h, .5h, 2h,3h, 1h, 3h, 3h, 4h, 2h, 3h, 7h, 3h, 1h, 4h, 1h, 1h, 1h, 4h, 2h, 2h, 2h, 2h, 1h, 2h, 3h, 2h, 1h, 3h, 2h, 2h, 1h, 2h, 3h, 2h, 1h, 1h, 1.5, 2h, 2h, 3h, 2h, 1h, 3h, 2h, 1h, 2h, 1h, 5h, 2h, 1h, 2h, 4h, 2h )
Flaperons: ( DONE! ) 23.5 hours spent ( 3h, 1h, 1h, 1h, 1.5h, 3h, 6h, 3h, 4h, 1h )
Paint Design: 2 hours spent ( 1h, 1h )
Elevator DONE!: ~31.5 hours spent ( 3h, 1.5h, 3h, .5h, 3.5h, 2h, 4h, 1.5h, 2h, 4.5h, 1h, 6h )
Horizontal Stabilizer DONE!: ~28 hours spent, 3 pieces replaced ( 3h, 2h, 2h, 2h, .5h, 1.5h, 3.5h, 1.5h, 5, 4.5, 2h, .5h )
Rudder DONE!, minus horn : ~16 hours spent, ( ~8h, ~8h )
-----------------------
Total Done: ~443h
The only holes remaining are in the gear strut attachment.
Everything was deburred and is now ready for priming.
PROGRESS:
Fuselage ~181h ( 3h, 3h, 2h, 3h, 7h, 2h, 5h, 2h, 3h, 2h, 2h, 3h, 6h, 2h, 2h, 1.5h, 2.5h, 1h, 2h, 3h, 2h, 3h, 4h, 1h, 2h, 1h, 3h, 4h, 3h, 3h, 4h, 3h, 4h, 4h, 6h, 3h, 3h, 4h, 2h, 2h, 2h, 4h, 2h, 2h, 10h, 4h, 4h, 6h, 3h, 4h , 6h, 3h, 2h, 2h, 5h, 2h, 3h, 3h )
Wings: ~157.5h ( 1h, 1h, 0.5h, 2.5h, 4h, 1h, 1.5h, 1h, 1.5, 4.5, 1h, 1h, 2h, 4h, 1h, 3h, 1h, 2h, .5h, 1.5h, 2h, 2h, 2h, .5h, 1h, .5h, .5h, 2h,3h, 1h, 3h, 3h, 4h, 2h, 3h, 7h, 3h, 1h, 4h, 1h, 1h, 1h, 4h, 2h, 2h, 2h, 2h, 1h, 2h, 3h, 2h, 1h, 3h, 2h, 2h, 1h, 2h, 3h, 2h, 1h, 1h, 1.5, 2h, 2h, 3h, 2h, 1h, 3h, 2h, 1h, 2h, 1h, 5h, 2h, 1h, 2h, 4h, 2h )
Flaperons: ( DONE! ) 23.5 hours spent ( 3h, 1h, 1h, 1h, 1.5h, 3h, 6h, 3h, 4h, 1h )
Paint Design: 2 hours spent ( 1h, 1h )
Elevator DONE!: ~31.5 hours spent ( 3h, 1.5h, 3h, .5h, 3.5h, 2h, 4h, 1.5h, 2h, 4.5h, 1h, 6h )
Horizontal Stabilizer DONE!: ~28 hours spent, 3 pieces replaced ( 3h, 2h, 2h, 2h, .5h, 1.5h, 3.5h, 1.5h, 5, 4.5, 2h, .5h )
Rudder DONE!, minus horn : ~16 hours spent, ( ~8h, ~8h )
-----------------------
Total Done: ~443h
Friday, January 18, 2008
Some nights just do not got the way you want. The whole session ended just about where I thought I started.
First the rear and front fuselage would not cooperate and mate together. Then I realized that the middle baggage area truss was not riveted to the baggage area flooe, so I drilled out the rivets... to the doubler extension that I had to fab... only to find out I drilled out the wrong row of rivets and that the truss was upside down... and had to be drilled out.
Everything fits together now AND I riveted a portion of the rear fuselage that had been kept clecoed together just in case.
Instead of a photo, here is a quick tour of the Seattle skyline:
Seattle Skyline Tour from John Marzulli on Vimeo
PROGRESS:
Fuselage ~178h ( 3h, 3h, 2h, 3h, 7h, 2h, 5h, 2h, 3h, 2h, 2h, 3h, 6h, 2h, 2h, 1.5h, 2.5h, 1h, 2h, 3h, 2h, 3h, 4h, 1h, 2h, 1h, 3h, 4h, 3h, 3h, 4h, 3h, 4h, 4h, 6h, 3h, 3h, 4h, 2h, 2h, 2h, 4h, 2h, 2h, 10h, 4h, 4h, 6h, 3h, 4h , 6h, 3h, 2h, 2h, 5h, 2h, 3h )
Wings: ~157.5h ( 1h, 1h, 0.5h, 2.5h, 4h, 1h, 1.5h, 1h, 1.5, 4.5, 1h, 1h, 2h, 4h, 1h, 3h, 1h, 2h, .5h, 1.5h, 2h, 2h, 2h, .5h, 1h, .5h, .5h, 2h,3h, 1h, 3h, 3h, 4h, 2h, 3h, 7h, 3h, 1h, 4h, 1h, 1h, 1h, 4h, 2h, 2h, 2h, 2h, 1h, 2h, 3h, 2h, 1h, 3h, 2h, 2h, 1h, 2h, 3h, 2h, 1h, 1h, 1.5, 2h, 2h, 3h, 2h, 1h, 3h, 2h, 1h, 2h, 1h, 5h, 2h, 1h, 2h, 4h, 2h )
Flaperons: ( DONE! ) 23.5 hours spent ( 3h, 1h, 1h, 1h, 1.5h, 3h, 6h, 3h, 4h, 1h )
Paint Design: 2 hours spent ( 1h, 1h )
Elevator DONE!: ~31.5 hours spent ( 3h, 1.5h, 3h, .5h, 3.5h, 2h, 4h, 1.5h, 2h, 4.5h, 1h, 6h )
Horizontal Stabilizer DONE!: ~28 hours spent, 3 pieces replaced ( 3h, 2h, 2h, 2h, .5h, 1.5h, 3.5h, 1.5h, 5, 4.5, 2h, .5h )
Rudder DONE!, minus horn : ~16 hours spent, ( ~8h, ~8h )
-----------------------
Total Done: ~440h
First the rear and front fuselage would not cooperate and mate together. Then I realized that the middle baggage area truss was not riveted to the baggage area flooe, so I drilled out the rivets... to the doubler extension that I had to fab... only to find out I drilled out the wrong row of rivets and that the truss was upside down... and had to be drilled out.
Everything fits together now AND I riveted a portion of the rear fuselage that had been kept clecoed together just in case.
Instead of a photo, here is a quick tour of the Seattle skyline:
Seattle Skyline Tour from John Marzulli on Vimeo
PROGRESS:
Fuselage ~178h ( 3h, 3h, 2h, 3h, 7h, 2h, 5h, 2h, 3h, 2h, 2h, 3h, 6h, 2h, 2h, 1.5h, 2.5h, 1h, 2h, 3h, 2h, 3h, 4h, 1h, 2h, 1h, 3h, 4h, 3h, 3h, 4h, 3h, 4h, 4h, 6h, 3h, 3h, 4h, 2h, 2h, 2h, 4h, 2h, 2h, 10h, 4h, 4h, 6h, 3h, 4h , 6h, 3h, 2h, 2h, 5h, 2h, 3h )
Wings: ~157.5h ( 1h, 1h, 0.5h, 2.5h, 4h, 1h, 1.5h, 1h, 1.5, 4.5, 1h, 1h, 2h, 4h, 1h, 3h, 1h, 2h, .5h, 1.5h, 2h, 2h, 2h, .5h, 1h, .5h, .5h, 2h,3h, 1h, 3h, 3h, 4h, 2h, 3h, 7h, 3h, 1h, 4h, 1h, 1h, 1h, 4h, 2h, 2h, 2h, 2h, 1h, 2h, 3h, 2h, 1h, 3h, 2h, 2h, 1h, 2h, 3h, 2h, 1h, 1h, 1.5, 2h, 2h, 3h, 2h, 1h, 3h, 2h, 1h, 2h, 1h, 5h, 2h, 1h, 2h, 4h, 2h )
Flaperons: ( DONE! ) 23.5 hours spent ( 3h, 1h, 1h, 1h, 1.5h, 3h, 6h, 3h, 4h, 1h )
Paint Design: 2 hours spent ( 1h, 1h )
Elevator DONE!: ~31.5 hours spent ( 3h, 1.5h, 3h, .5h, 3.5h, 2h, 4h, 1.5h, 2h, 4.5h, 1h, 6h )
Horizontal Stabilizer DONE!: ~28 hours spent, 3 pieces replaced ( 3h, 2h, 2h, 2h, .5h, 1.5h, 3.5h, 1.5h, 5, 4.5, 2h, .5h )
Rudder DONE!, minus horn : ~16 hours spent, ( ~8h, ~8h )
-----------------------
Total Done: ~440h
Monday, January 14, 2008
Weekend roundup ( Friday, Saturday, Sunday )
First, my upholstery arrived late Friday. It looks great. I am making a big push to be able to finally sit in the plane... which leads me to the next part:
Drill out, debur, prime, rivet.
There are still a few holes that need to be drilled out that I am finding. Most everything is now covered in primer. The entire torque tube cover assembly is now riveted together. I also have the baggage compartment riveted together. To avoid some installation and reach issues the side skin gussets have been riveted.
I also fixed a mistake caused by misinterpreting the plans. For some reason I installed the interior gussets with the cutout for the rudder cables on the upper locations. These were drilled out and replacements were made without the cutout. The lower gussets were modified to include the rounded notch.
As getting in and out of the rear fuselage is a pain, it is highly suggested to install them the correct way before riveting any of the baggage area.
PROGRESS:
Fuselage ~175h ( 3h, 3h, 2h, 3h, 7h, 2h, 5h, 2h, 3h, 2h, 2h, 3h, 6h, 2h, 2h, 1.5h, 2.5h, 1h, 2h, 3h, 2h, 3h, 4h, 1h, 2h, 1h, 3h, 4h, 3h, 3h, 4h, 3h, 4h, 4h, 6h, 3h, 3h, 4h, 2h, 2h, 2h, 4h, 2h, 2h, 10h, 4h, 4h, 6h, 3h, 4h , 6h, 3h, 2h, 2h, 5h, 2h )
Wings: ~157.5h ( 1h, 1h, 0.5h, 2.5h, 4h, 1h, 1.5h, 1h, 1.5, 4.5, 1h, 1h, 2h, 4h, 1h, 3h, 1h, 2h, .5h, 1.5h, 2h, 2h, 2h, .5h, 1h, .5h, .5h, 2h,3h, 1h, 3h, 3h, 4h, 2h, 3h, 7h, 3h, 1h, 4h, 1h, 1h, 1h, 4h, 2h, 2h, 2h, 2h, 1h, 2h, 3h, 2h, 1h, 3h, 2h, 2h, 1h, 2h, 3h, 2h, 1h, 1h, 1.5, 2h, 2h, 3h, 2h, 1h, 3h, 2h, 1h, 2h, 1h, 5h, 2h, 1h, 2h, 4h, 2h )
Flaperons: ( DONE! ) 23.5 hours spent ( 3h, 1h, 1h, 1h, 1.5h, 3h, 6h, 3h, 4h, 1h )
Paint Design: 2 hours spent ( 1h, 1h )
Elevator DONE!: ~31.5 hours spent ( 3h, 1.5h, 3h, .5h, 3.5h, 2h, 4h, 1.5h, 2h, 4.5h, 1h, 6h )
Horizontal Stabilizer DONE!: ~28 hours spent, 3 pieces replaced ( 3h, 2h, 2h, 2h, .5h, 1.5h, 3.5h, 1.5h, 5, 4.5, 2h, .5h )
Rudder DONE!, minus horn : ~16 hours spent, ( ~8h, ~8h )
-----------------------
Total Done: ~437h
First, my upholstery arrived late Friday. It looks great. I am making a big push to be able to finally sit in the plane... which leads me to the next part:
Drill out, debur, prime, rivet.
There are still a few holes that need to be drilled out that I am finding. Most everything is now covered in primer. The entire torque tube cover assembly is now riveted together. I also have the baggage compartment riveted together. To avoid some installation and reach issues the side skin gussets have been riveted.
I also fixed a mistake caused by misinterpreting the plans. For some reason I installed the interior gussets with the cutout for the rudder cables on the upper locations. These were drilled out and replacements were made without the cutout. The lower gussets were modified to include the rounded notch.
As getting in and out of the rear fuselage is a pain, it is highly suggested to install them the correct way before riveting any of the baggage area.
PROGRESS:
Fuselage ~175h ( 3h, 3h, 2h, 3h, 7h, 2h, 5h, 2h, 3h, 2h, 2h, 3h, 6h, 2h, 2h, 1.5h, 2.5h, 1h, 2h, 3h, 2h, 3h, 4h, 1h, 2h, 1h, 3h, 4h, 3h, 3h, 4h, 3h, 4h, 4h, 6h, 3h, 3h, 4h, 2h, 2h, 2h, 4h, 2h, 2h, 10h, 4h, 4h, 6h, 3h, 4h , 6h, 3h, 2h, 2h, 5h, 2h )
Wings: ~157.5h ( 1h, 1h, 0.5h, 2.5h, 4h, 1h, 1.5h, 1h, 1.5, 4.5, 1h, 1h, 2h, 4h, 1h, 3h, 1h, 2h, .5h, 1.5h, 2h, 2h, 2h, .5h, 1h, .5h, .5h, 2h,3h, 1h, 3h, 3h, 4h, 2h, 3h, 7h, 3h, 1h, 4h, 1h, 1h, 1h, 4h, 2h, 2h, 2h, 2h, 1h, 2h, 3h, 2h, 1h, 3h, 2h, 2h, 1h, 2h, 3h, 2h, 1h, 1h, 1.5, 2h, 2h, 3h, 2h, 1h, 3h, 2h, 1h, 2h, 1h, 5h, 2h, 1h, 2h, 4h, 2h )
Flaperons: ( DONE! ) 23.5 hours spent ( 3h, 1h, 1h, 1h, 1.5h, 3h, 6h, 3h, 4h, 1h )
Paint Design: 2 hours spent ( 1h, 1h )
Elevator DONE!: ~31.5 hours spent ( 3h, 1.5h, 3h, .5h, 3.5h, 2h, 4h, 1.5h, 2h, 4.5h, 1h, 6h )
Horizontal Stabilizer DONE!: ~28 hours spent, 3 pieces replaced ( 3h, 2h, 2h, 2h, .5h, 1.5h, 3.5h, 1.5h, 5, 4.5, 2h, .5h )
Rudder DONE!, minus horn : ~16 hours spent, ( ~8h, ~8h )
-----------------------
Total Done: ~437h
Saturday, January 12, 2008
Tuesday, January 08, 2008
Monday night I drilled out almost all of the remaining holes in the forward fuselage. When the holes in 7F3-3SP got enlarged to A5 it became very apparent that distance between the holes was not sufficient for my standards. I ordered a new tube and a sheet of .040 from OnlineMetals.com so I could fab up new pieces. I finished the night by deburring a good bit of the fuselage.
Tuesday night I un-installed the passenger side 7F3-3SP lined it up with a flat edge of my new 0.040 sheet and clamped and back drilled all the holes that did not go into the diagonal tube. I then expanded the gusset about 20mm inboard so as to gain an additional 15mm or so on the diagonal. I left the width of the gusset the same as before at the fore and aft, connected up my lines, cut it out and cleaned it up.
The new piece fit perfectly. I then trimmed the tube, inserted it into the fuselage receiver, clamped, lined up and drilled. The new holes are dead on with about 4D space between holes. I back drilled the remaining holes in the frame and the lower gusset.
PROGRESS:
Fuselage ~166h ( 3h, 3h, 2h, 3h, 7h, 2h, 5h, 2h, 3h, 2h, 2h, 3h, 6h, 2h, 2h, 1.5h, 2.5h, 1h, 2h, 3h, 2h, 3h, 4h, 1h, 2h, 1h, 3h, 4h, 3h, 3h, 4h, 3h, 4h, 4h, 6h, 3h, 3h, 4h, 2h, 2h, 2h, 4h, 2h, 2h, 10h, 4h, 4h, 6h, 3h, 4h , 6h, 3h, 2h)
Wings: ~157.5h ( 1h, 1h, 0.5h, 2.5h, 4h, 1h, 1.5h, 1h, 1.5, 4.5, 1h, 1h, 2h, 4h, 1h, 3h, 1h, 2h, .5h, 1.5h, 2h, 2h, 2h, .5h, 1h, .5h, .5h, 2h,3h, 1h, 3h, 3h, 4h, 2h, 3h, 7h, 3h, 1h, 4h, 1h, 1h, 1h, 4h, 2h, 2h, 2h, 2h, 1h, 2h, 3h, 2h, 1h, 3h, 2h, 2h, 1h, 2h, 3h, 2h, 1h, 1h, 1.5, 2h, 2h, 3h, 2h, 1h, 3h, 2h, 1h, 2h, 1h, 5h, 2h, 1h, 2h, 4h, 2h )
Flaperons: ( DONE! ) 23.5 hours spent ( 3h, 1h, 1h, 1h, 1.5h, 3h, 6h, 3h, 4h, 1h )
Paint Design: 2 hours spent ( 1h, 1h )
Elevator DONE!: ~31.5 hours spent ( 3h, 1.5h, 3h, .5h, 3.5h, 2h, 4h, 1.5h, 2h, 4.5h, 1h, 6h )
Horizontal Stabilizer DONE!: ~28 hours spent, 3 pieces replaced ( 3h, 2h, 2h, 2h, .5h, 1.5h, 3.5h, 1.5h, 5, 4.5, 2h, .5h )
Rudder DONE!, minus horn : ~16 hours spent, ( ~8h, ~8h )
-----------------------
Total Done: ~428h
Tuesday night I un-installed the passenger side 7F3-3SP lined it up with a flat edge of my new 0.040 sheet and clamped and back drilled all the holes that did not go into the diagonal tube. I then expanded the gusset about 20mm inboard so as to gain an additional 15mm or so on the diagonal. I left the width of the gusset the same as before at the fore and aft, connected up my lines, cut it out and cleaned it up.
The new piece fit perfectly. I then trimmed the tube, inserted it into the fuselage receiver, clamped, lined up and drilled. The new holes are dead on with about 4D space between holes. I back drilled the remaining holes in the frame and the lower gusset.
PROGRESS:
Fuselage ~166h ( 3h, 3h, 2h, 3h, 7h, 2h, 5h, 2h, 3h, 2h, 2h, 3h, 6h, 2h, 2h, 1.5h, 2.5h, 1h, 2h, 3h, 2h, 3h, 4h, 1h, 2h, 1h, 3h, 4h, 3h, 3h, 4h, 3h, 4h, 4h, 6h, 3h, 3h, 4h, 2h, 2h, 2h, 4h, 2h, 2h, 10h, 4h, 4h, 6h, 3h, 4h , 6h, 3h, 2h)
Wings: ~157.5h ( 1h, 1h, 0.5h, 2.5h, 4h, 1h, 1.5h, 1h, 1.5, 4.5, 1h, 1h, 2h, 4h, 1h, 3h, 1h, 2h, .5h, 1.5h, 2h, 2h, 2h, .5h, 1h, .5h, .5h, 2h,3h, 1h, 3h, 3h, 4h, 2h, 3h, 7h, 3h, 1h, 4h, 1h, 1h, 1h, 4h, 2h, 2h, 2h, 2h, 1h, 2h, 3h, 2h, 1h, 3h, 2h, 2h, 1h, 2h, 3h, 2h, 1h, 1h, 1.5, 2h, 2h, 3h, 2h, 1h, 3h, 2h, 1h, 2h, 1h, 5h, 2h, 1h, 2h, 4h, 2h )
Flaperons: ( DONE! ) 23.5 hours spent ( 3h, 1h, 1h, 1h, 1.5h, 3h, 6h, 3h, 4h, 1h )
Paint Design: 2 hours spent ( 1h, 1h )
Elevator DONE!: ~31.5 hours spent ( 3h, 1.5h, 3h, .5h, 3.5h, 2h, 4h, 1.5h, 2h, 4.5h, 1h, 6h )
Horizontal Stabilizer DONE!: ~28 hours spent, 3 pieces replaced ( 3h, 2h, 2h, 2h, .5h, 1.5h, 3.5h, 1.5h, 5, 4.5, 2h, .5h )
Rudder DONE!, minus horn : ~16 hours spent, ( ~8h, ~8h )
-----------------------
Total Done: ~428h
Monday, January 07, 2008
The pilot and passenger seat pans are now both drilled into place. In addition the seat corner gussets were both fabricated and drilled into place, the backing ("L") of the seats is in place and several tie together gussets were put into place to deal with over trimming of the side extrusion.
In addition, most of the A3 holes were drilled out into A4, with some becoming A5.
Drilling seat backing ("L") angle into place took two people and the access hole. First I trimmed the piece to length and drew the centerline. Then I identified the center position ( left to right ) drilled the pilot side most hole that was not shared with extrusion. Then the helper from the outside clecoed the seat back, seat pan and ("L") together and removed some of the clecos that pushed against the ("L"). It was then a job of matching the line and back drilling through the seat, clecoing and then moving more towards the passenger side.
PROGRESS:
Fuselage ~161h ( 3h, 3h, 2h, 3h, 7h, 2h, 5h, 2h, 3h, 2h, 2h, 3h, 6h, 2h, 2h, 1.5h, 2.5h, 1h, 2h, 3h, 2h, 3h, 4h, 1h, 2h, 1h, 3h, 4h, 3h, 3h, 4h, 3h, 4h, 4h, 6h, 3h, 3h, 4h, 2h, 2h, 2h, 4h, 2h, 2h, 10h, 4h, 4h, 6h, 3h, 4h , 6h)
Wings: ~157.5h ( 1h, 1h, 0.5h, 2.5h, 4h, 1h, 1.5h, 1h, 1.5, 4.5, 1h, 1h, 2h, 4h, 1h, 3h, 1h, 2h, .5h, 1.5h, 2h, 2h, 2h, .5h, 1h, .5h, .5h, 2h,3h, 1h, 3h, 3h, 4h, 2h, 3h, 7h, 3h, 1h, 4h, 1h, 1h, 1h, 4h, 2h, 2h, 2h, 2h, 1h, 2h, 3h, 2h, 1h, 3h, 2h, 2h, 1h, 2h, 3h, 2h, 1h, 1h, 1.5, 2h, 2h, 3h, 2h, 1h, 3h, 2h, 1h, 2h, 1h, 5h, 2h, 1h, 2h, 4h, 2h )
Flaperons: ( DONE! ) 23.5 hours spent ( 3h, 1h, 1h, 1h, 1.5h, 3h, 6h, 3h, 4h, 1h )
Paint Design: 2 hours spent ( 1h, 1h )
Elevator DONE!: ~31.5 hours spent ( 3h, 1.5h, 3h, .5h, 3.5h, 2h, 4h, 1.5h, 2h, 4.5h, 1h, 6h )
Horizontal Stabilizer DONE!: ~28 hours spent, 3 pieces replaced ( 3h, 2h, 2h, 2h, .5h, 1.5h, 3.5h, 1.5h, 5, 4.5, 2h, .5h )
Rudder DONE!, minus horn : ~16 hours spent, ( ~8h, ~8h )
-----------------------
Total Done: ~423h
In addition, most of the A3 holes were drilled out into A4, with some becoming A5.
Drilling seat backing ("L") angle into place took two people and the access hole. First I trimmed the piece to length and drew the centerline. Then I identified the center position ( left to right ) drilled the pilot side most hole that was not shared with extrusion. Then the helper from the outside clecoed the seat back, seat pan and ("L") together and removed some of the clecos that pushed against the ("L"). It was then a job of matching the line and back drilling through the seat, clecoing and then moving more towards the passenger side.
PROGRESS:
Fuselage ~161h ( 3h, 3h, 2h, 3h, 7h, 2h, 5h, 2h, 3h, 2h, 2h, 3h, 6h, 2h, 2h, 1.5h, 2.5h, 1h, 2h, 3h, 2h, 3h, 4h, 1h, 2h, 1h, 3h, 4h, 3h, 3h, 4h, 3h, 4h, 4h, 6h, 3h, 3h, 4h, 2h, 2h, 2h, 4h, 2h, 2h, 10h, 4h, 4h, 6h, 3h, 4h , 6h)
Wings: ~157.5h ( 1h, 1h, 0.5h, 2.5h, 4h, 1h, 1.5h, 1h, 1.5, 4.5, 1h, 1h, 2h, 4h, 1h, 3h, 1h, 2h, .5h, 1.5h, 2h, 2h, 2h, .5h, 1h, .5h, .5h, 2h,3h, 1h, 3h, 3h, 4h, 2h, 3h, 7h, 3h, 1h, 4h, 1h, 1h, 1h, 4h, 2h, 2h, 2h, 2h, 1h, 2h, 3h, 2h, 1h, 3h, 2h, 2h, 1h, 2h, 3h, 2h, 1h, 1h, 1.5, 2h, 2h, 3h, 2h, 1h, 3h, 2h, 1h, 2h, 1h, 5h, 2h, 1h, 2h, 4h, 2h )
Flaperons: ( DONE! ) 23.5 hours spent ( 3h, 1h, 1h, 1h, 1.5h, 3h, 6h, 3h, 4h, 1h )
Paint Design: 2 hours spent ( 1h, 1h )
Elevator DONE!: ~31.5 hours spent ( 3h, 1.5h, 3h, .5h, 3.5h, 2h, 4h, 1.5h, 2h, 4.5h, 1h, 6h )
Horizontal Stabilizer DONE!: ~28 hours spent, 3 pieces replaced ( 3h, 2h, 2h, 2h, .5h, 1.5h, 3.5h, 1.5h, 5, 4.5, 2h, .5h )
Rudder DONE!, minus horn : ~16 hours spent, ( ~8h, ~8h )
-----------------------
Total Done: ~423h
Friday, January 04, 2008
We spent about three hours getting the seat floors ready. First figuring out the procedure, then determining what needed to be fabricated. The pilot side seat is mostly drilled into place. A gusset needs to be fabricated and a supporting piece of ("L") needs to be positioned.
Tip: When drilling the seat pan into the ("L") angle that runs along the torque tube cover, the proper place for the holes was significantly further in than 10mm ( referenced by the skin ). The curvature of the skin combined with the closed angle of the ("L) essentially moved the skin edge more inside than I expected. The 10mm edge line drawn on the skin translated to the holes being about 4mm from the radius of the ("L").
I also found that to place the ("L") the seat front channel had to be pulled forward away from the torque tube cover to allow space for the angle to get slipped in.
PROGRESS:
Fuselage ~151h ( 3h, 3h, 2h, 3h, 7h, 2h, 5h, 2h, 3h, 2h, 2h, 3h, 6h, 2h, 2h, 1.5h, 2.5h, 1h, 2h, 3h, 2h, 3h, 4h, 1h, 2h, 1h, 3h, 4h, 3h, 3h, 4h, 3h, 4h, 4h, 6h, 3h, 3h, 4h, 2h, 2h, 2h, 4h, 2h, 2h, 10h, 4h, 4h, 6h, 3h)
Wings: ~157.5h ( 1h, 1h, 0.5h, 2.5h, 4h, 1h, 1.5h, 1h, 1.5, 4.5, 1h, 1h, 2h, 4h, 1h, 3h, 1h, 2h, .5h, 1.5h, 2h, 2h, 2h, .5h, 1h, .5h, .5h, 2h,3h, 1h, 3h, 3h, 4h, 2h, 3h, 7h, 3h, 1h, 4h, 1h, 1h, 1h, 4h, 2h, 2h, 2h, 2h, 1h, 2h, 3h, 2h, 1h, 3h, 2h, 2h, 1h, 2h, 3h, 2h, 1h, 1h, 1.5, 2h, 2h, 3h, 2h, 1h, 3h, 2h, 1h, 2h, 1h, 5h, 2h, 1h, 2h, 4h, 2h )
Flaperons: ( DONE! ) 23.5 hours spent ( 3h, 1h, 1h, 1h, 1.5h, 3h, 6h, 3h, 4h, 1h )
Paint Design: 2 hours spent ( 1h, 1h )
Elevator DONE!: ~31.5 hours spent ( 3h, 1.5h, 3h, .5h, 3.5h, 2h, 4h, 1.5h, 2h, 4.5h, 1h, 6h )
Horizontal Stabilizer DONE!: ~28 hours spent, 3 pieces replaced ( 3h, 2h, 2h, 2h, .5h, 1.5h, 3.5h, 1.5h, 5, 4.5, 2h, .5h )
Rudder DONE!, minus horn : ~16 hours spent, ( ~8h, ~8h )
-----------------------
Total Done: ~413h
Tip: When drilling the seat pan into the ("L") angle that runs along the torque tube cover, the proper place for the holes was significantly further in than 10mm ( referenced by the skin ). The curvature of the skin combined with the closed angle of the ("L) essentially moved the skin edge more inside than I expected. The 10mm edge line drawn on the skin translated to the holes being about 4mm from the radius of the ("L").
I also found that to place the ("L") the seat front channel had to be pulled forward away from the torque tube cover to allow space for the angle to get slipped in.
PROGRESS:
Fuselage ~151h ( 3h, 3h, 2h, 3h, 7h, 2h, 5h, 2h, 3h, 2h, 2h, 3h, 6h, 2h, 2h, 1.5h, 2.5h, 1h, 2h, 3h, 2h, 3h, 4h, 1h, 2h, 1h, 3h, 4h, 3h, 3h, 4h, 3h, 4h, 4h, 6h, 3h, 3h, 4h, 2h, 2h, 2h, 4h, 2h, 2h, 10h, 4h, 4h, 6h, 3h)
Wings: ~157.5h ( 1h, 1h, 0.5h, 2.5h, 4h, 1h, 1.5h, 1h, 1.5, 4.5, 1h, 1h, 2h, 4h, 1h, 3h, 1h, 2h, .5h, 1.5h, 2h, 2h, 2h, .5h, 1h, .5h, .5h, 2h,3h, 1h, 3h, 3h, 4h, 2h, 3h, 7h, 3h, 1h, 4h, 1h, 1h, 1h, 4h, 2h, 2h, 2h, 2h, 1h, 2h, 3h, 2h, 1h, 3h, 2h, 2h, 1h, 2h, 3h, 2h, 1h, 1h, 1.5, 2h, 2h, 3h, 2h, 1h, 3h, 2h, 1h, 2h, 1h, 5h, 2h, 1h, 2h, 4h, 2h )
Flaperons: ( DONE! ) 23.5 hours spent ( 3h, 1h, 1h, 1h, 1.5h, 3h, 6h, 3h, 4h, 1h )
Paint Design: 2 hours spent ( 1h, 1h )
Elevator DONE!: ~31.5 hours spent ( 3h, 1.5h, 3h, .5h, 3.5h, 2h, 4h, 1.5h, 2h, 4.5h, 1h, 6h )
Horizontal Stabilizer DONE!: ~28 hours spent, 3 pieces replaced ( 3h, 2h, 2h, 2h, .5h, 1.5h, 3.5h, 1.5h, 5, 4.5, 2h, .5h )
Rudder DONE!, minus horn : ~16 hours spent, ( ~8h, ~8h )
-----------------------
Total Done: ~413h
Wednesday, January 02, 2008
First some building footage:
Grinding Metal from John Marzulli on Vimeo.
And then some flying video.
Flying and Sunset from John Marzulli on Vimeo.
Grinding Metal from John Marzulli on Vimeo.
And then some flying video.
Flying and Sunset from John Marzulli on Vimeo.
Subscribe to:
Posts (Atom)